§ 26 — When liability order must be given

26.—(1) The Authority must give in accordance with subsection (2), (3) or (4) (whichever is applicable) a liability order stating an estimate of the amount or the amount of land betterment charge that is payable.(2) For a chargeable consent that is —(a)

a planning permission or conservation permission; or

(b)

by way of varying of a restrictive covenant in a State title relating to any land that is not a controlled activity restrictive covenant or subdivision control restrictive covenant,

the liability order must be given as soon as practicable after one of the following dates, whichever is applicable:

(c)

the date a planning permission or conservation permission (as the case may be) is granted in respect of the development of the land to which the permission or authorisation relates, where —(i)

no provisional permission is granted with respect to the development of the land; and

(ii)

no lodgment is made of any plans for the development that may be deemed authorised without express written permission;

(d)

the date where the competent authority or Land Planning Minister notifies the Authority that the competent authority or Land Planning Minister (as the case may be) intends to grant written permission under section 14 or 17(4) (as the case may be) of the Planning Act 1998 — where any provisional permission is granted with respect to the development of the land and that provisional permission does not lapse because of one or more extensions.[Act 23 of 2023 wef 18/12/2023]

(3) For a chargeable consent that is accepting a lodgment of any plans for a development of the land deemed authorised without express written permission, the liability order must be given as soon as practicable after the date the lodgment is accepted.

(4) For a chargeable consent that is by way of varying a controlled activity restrictive covenant or a subdivision control restrictive covenant in a State title, the liability order must be given as soon as practicable after the date the chargeable consent is given.

—(1) The Authority must give in accordance with subsection (2), (3) or (4) (whichever is applicable) a liability order stating an estimate of the amount or the amount of land betterment charge that is payable.

(2) For a chargeable consent that is —(a)

a planning permission or conservation permission; or

(b)

by way of varying of a restrictive covenant in a State title relating to any land that is not a controlled activity restrictive covenant or subdivision control restrictive covenant,

the liability order must be given as soon as practicable after one of the following dates, whichever is applicable:

(c)

the date a planning permission or conservation permission (as the case may be) is granted in respect of the development of the land to which the permission or authorisation relates, where —(i)

no provisional permission is granted with respect to the development of the land; and

(ii)

no lodgment is made of any plans for the development that may be deemed authorised without express written permission;

(d)

the date where the competent authority or Land Planning Minister notifies the Authority that the competent authority or Land Planning Minister (as the case may be) intends to grant written permission under section 14 or 17(4) (as the case may be) of the Planning Act 1998 — where any provisional permission is granted with respect to the development of the land and that provisional permission does not lapse because of one or more extensions.[Act 23 of 2023 wef 18/12/2023]

(3) For a chargeable consent that is accepting a lodgment of any plans for a development of the land deemed authorised without express written permission, the liability order must be given as soon as practicable after the date the lodgment is accepted.

(4) For a chargeable consent that is by way of varying a controlled activity restrictive covenant or a subdivision control restrictive covenant in a State title, the liability order must be given as soon as practicable after the date the chargeable consent is given.