SECTION 305. Validity of Building Permits. The issuance of a building permit shall not be construed as an approval or authorization to the permittee to disregard or violate any of the provisions of this Code. Whenever the issuance of a permit is based on approved plans and specifications which are subsequently found defective, the Building Official is not precluded from requiring permittee to effect the necessary corrections in said plans and specifications or from preventing or ordering the stoppage of any or all building operations being carried on thereunder which are in violation of this Code. A building permit issued under the provisions of this Code shall expire and become null and void if the building or work authorized therein is not commenced within a period of one year from the date of such permit, or if the building or work so authorized is suspended or abandoned at any time after it has been commenced, for a period of 120 days.

Read the full instrument → · Open the chapter this section belongs to: CHAPTER 3 PERMITS AND INSPECTION →

Other provisions in CHAPTER 3 PERMITS AND INSPECTION

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of July 4, 2026

CitationPD 1096 Section 305 (LawPlayer, data as of July 4, 2026)

Source: Supreme Court E-Library, Republic of the Philippines. Philippine laws are public documents (works of the government).