資料由法律人 LawPlayer整理提供·Singapore statutory provision · curated by LawPlayer
Section 22FZB — Periodic audit of energy efficiency of building cooling system
(1)Subject to subsection (2), the Commissioner of Building Control may, by notice served on the owner of any of the following buildings, require an audit to be carried out as to whether the cooling system of the building meets the prescribed energy efficiency standard applicable to such cooling system (called in this Division an energy audit):
(a)any building in respect of which an application for planning permission is submitted to the competent authority under the Planning Act 1998 on or after 1 December 2010;
(b)any Type 2 building which has undergone a major energy use change under this Division.[22/2012] [Act 28 of 2024 wef 30/09/2025]
(2)A notice under subsection (1) may be issued —
(a)to the owner of any building in respect of which the application for planning permission is submitted to the competent authority under the Planning Act 1998 on or after 1 December 2010 —
(i)at any time after the temporary occupation permit or, if no temporary occupation permit is issued, the certificate of statutory completion is issued in respect of that building; and
(ii)thereafter at intervals of not less than 3 years after the date of the last notice under this section; and
(b)to the owner of any Type 2 building which has undergone a major energy use change —
(i)at any time on or after the third anniversary of the date of the approval of the as‑built score mentioned in section 22FZA(1)(b)(i); and[Act 28 of 2024 wef 30/09/2025]
(ii)thereafter at intervals of not less than 3 years after the date of the last notice under this section.[22/2012] [Act 28 of 2024 wef 30/09/2025]
(3)The owner of a building on whom a notice is served under subsection (1) must, within the period specified in the notice under that subsection —
(a)appoint a specified individual to carry out the energy audit; [Act 28 of 2024 wef 30/09/2025]
(b)if the cooling system does not meet the applicable prescribed energy efficiency standard, carry out any maintenance work or take any other measures in relation to the cooling system to ensure that it meets the applicable prescribed energy efficiency standard; and
(c)submit the report of the energy audit to the Commissioner of Building Control in such form and manner as the Commissioner of Building Control may specify.[22/2012] [Act 12 of 2020 wef 01/01/2022]
(4)Any owner of a building who, without reasonable excuse, contravenes subsection (3) shall be guilty of an offence and shall be liable on conviction to a fine not exceeding $20,000 and, in the case of a continuing offence, to a further fine not exceeding $500 for every day or part of a day during which the offence continues after conviction.[22/2012]
(5)The Commissioner of Building Control may, on the application of an owner of a building in any particular case, modify any requirement in relation to the prescribed energy efficiency standard for the cooling system of the building, subject to any conditions that the Commissioner of Building Control may impose.[22/2012] [Act 28 of 2024 wef 30/09/2025]
Cite this section
BCA1989, s 22FZB (Singapore Statutes Online). Retrieved via LawPlayer, https://lawplayer.com/sg/act/BCA1989/22FZB
Source: Singapore Statutes Online (sso.agc.gov.sg), © Singapore Government
本頁資料來源:Singapore Statutes Online (AGC)·整理提供:法律人 LawPlayer· lawplayer.com