26.—(1) Any dispute between a consumer and a market support services licensee as to whether supply of electricity should be provided to that consumer —(a)
may be referred to the Authority by either party; and
(b)
on such a reference, is to be determined by the Authority, whose decision is final and conclusive between the parties.
(2) Notwithstanding that a dispute between a consumer and a market support services licensee has been referred to the Authority, the licensee must, subject to sections 21(3) and 41(13), supply electricity to the consumer until the dispute is determined by the Authority.
The Singapore legislation on this platform is subject to copyright of the Singapore Government and is used/reproduced for the purposes of this platform with the permission of the Attorney-General's Chambers. Users of this platform may check Singapore Statutes Online for the latest version of the Singapore legislation.