s 52 Occupier may execute work where owner defaults in execution of work

52.—(1) Whenever an owner of any premises defaults in the execution of any work required under this Act to be executed by the owner, an occupier of the premises may, with the approval of the Director‑General, cause the work to be executed. (2) The expense of the work executed under subsection (1) must be paid to the occupier by the owner of the premises or the amount may be deducted from the rent from time to time becoming due from the occupier to the owner. (3) The occupier of the premises may, in the absence of any special agreement to the contrary, retain possession until the expense of the work executed under subsection (1) has been fully reimbursed to the occupier.

Read this section in the full act → · Open PART 12 →

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. Read the official text ↗

Source: Singapore Statutes Online (Attorney-General's Chambers), © Government of Singapore.

The Singapore legislation on this platform is subject to copyright of the Singapore Government and is used/reproduced for the purposes of this platform with the permission of the Attorney-General's Chambers. Users of this platform may check Singapore Statutes Online for the latest version of the Singapore legislation.

What to look at next