The aid which Germany is proposing to implement for Saxonylon Textil GmbH, a subsidiary of the Tolaram Group, and which comprises a grant of DEM 35,208 million and an investment allowance of DEM 7,138 million is incompatible with the common market.
The aid may accordingly not be implemented.
Germany shall inform the Commission, within two months of notification of this Decision, of the measures taken to comply with it.
This Decision is addressed to Germany.
Done at Brussels, 20 July 1999.
For the Commission
Karel VAN MIERT
Member of the Commission
(1) OJ L 83, 27.3.1999, p. 1.
(2) OJ C 39, 13.2.1999, p. 2.
(3) OJ C 39, 13.2.1999, p. 2.
(4) Commission letter (SG) D/7104, of 18 September 1997.
(5) OJ C 94, 30.3.1996, p. 11.
(6) OJ C 24, 29.1.1999, p. 18.
(7) Commission letter SG(95) D/17154, of 27 December 1995, and corrigendum SG(96) D/3794, of 11 April 1996.