2014/536/EU: Commission Decision of 14 August 2014 granting the Hellenic Republic a derogation from certain provisions of Directive 2009/72/EC of the European Parliament and of the Council

2014/536/EU: Commission Decision of 14 August 2014 granting the Hellenic Republic a derogation from certain provisions of Directive 2009/72/EC of the European Parliament and of the Council

Directive 2009/72/EC · Decision · 6 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Article 1

Open ↗

This decision applies to small and micro isolated systems as identified in the Table. For the purpose of this Decision, Crete is a small isolated system whereas all other isolated systems are micro isolated systems.

Article 2

Open ↗

1.   A derogation is granted from the provisions of Article 33 of Directive 2009/72/EC for small and micro isolated systems. 2.   This derogation shall be valid until 17 February 2016 or the full installation of the infrastructure as provided for in Article 237(7) of the NII Code, whatever comes later. In any event, this derogation shall cease to apply on 17 February 2019. 3.   The Greek authorities shall by 17 February 2015 draw up a plan for the infrastructure investments as provided for in Article 237(7) of the NII Code, specifying, separately for each NII isolated system, by which date the infrastructure shall be fully installed. This plan shall prioritise Crete and Rhodes. 4.   From 17 February 2016, and thereafter on an annual basis until 17 February 2019, the Greek authorities shall draw-up a report specifying, for each NII isolated system: (a) whether market opening has occurred; (b) the status of the infrastructure investments with relation to the relevant plan (c) the substantial and material problems that persist for market opening; and (d) whether those problems can be directly attributed to the non-completion of the infrastructure investment as provided for in Article 237(7) of the NII Code.

Article 3

Open ↗

1.   A derogation is granted from the provisions of Article 7(1) of Directive 2009/72/EC according to which authorisations for refurbishing, upgrading and expanding existing conventional capacity within micro isolated systems can be granted directly to PPC. 2.   For the purpose of this derogation: (a) existing conventional generation capacity shall include projects for refurbishing, upgrading and expanding conventional generation capacity for which a valid license issued by RAE exists on the date of notification of this Decision; (b) the full demolishment of the main generation capacity on an existing site and its replacement by a new electricity generation installation shall not constitute existing capacity but construction of new capacity; (c) the placement of temporary conventional generation capacity within the perimeter of existing capacity shall constitute expanding existing capacity. 3.   Upon expiry of the authorisation granted in accordance with the first paragraph, such authorisation can be prolonged, on RAE's sole discretion, provided the delays are due to reasons entirely beyond the control of PPC. 4.   This derogation shall no longer apply to authorisations granted pursuant to the first paragraph that have expired or cancelled. 5.   All other provisions of Article 7 Directive 2009/72/EC continue to apply in full. 6.   This derogation is valid until 1 January 2021.

Article 4

Open ↗

1.   The derogations provided for in this Decision shall no longer apply to small and micro isolated systems once they are interconnected with the interconnected system. 2.   The Greek authorities: (a) when authorising or tendering for new capacity within a given NII isolated system, shall systematically consider the alternative of interconnecting the isolated system of which the given NII is part. An authorisation for new capacity shall be refused if constructing an interconnector is more cost effective. Costs shall comprise all costs to supply electricity to end-customers within the isolated system, including NII PSO compensation; (b) shall ensure that the cost-benefit study for important transmission works by ADMIE as provided for in Article 108 of Law 4001/2011 shall only consider efficient costs of investing and operating the projected interconnection. It shall not consider revenues lost by or depreciation in value of the conventional generation assets already installed on the NIIs; (c) shall publish, in conjunction with ADMIE's ten-year investment plan as provided for in Article 108 of Law 4001/2011, the overall costs, including the NII PSO compensation, of supplying electricity customers in each of the NII isolated systems. Unless the construction of an interconnector is integrated in ADMIE's ten-year investment plan as provided for in Article 108 of Law 4001/2011 as approved by RAE, the Greek Authorities shall, upon their own initiative or upon simple request by a third party, organise a tender as provided for in Article 22(7)(b) of Directive 2009/72/EC for the construction of an interconnector connecting one or several NII isolated systems. An interconnector shall be constructed if its construction lowers the overall costs, including the NII PSO compensation, of supplying electricity to customers located on the NIIs; (d) shall set a clear deadline for the completion of the construction of an interconnector. If the interconnector is not constructed or is not constructed within the set time frame, the Greek Authorities shall seek damages for the non-realised costs savings.

Other acts of the same type
Council Decision (EU) 2018/2068 of 29 November 2018 on the signing, on behalf of the Union, of the Sustainable Fisheries Partnership Agreement between the European Union and the Kingdom of Morocco, the Implementation Protocol thereto and the exchange of letters accompanying the AgreementCommission Implementing Decision of 28 November 2018 on the publication in the Official Journal of the European Union of the single document referred to in Article 94(1)(d) of Regulation (EU) No 1308/2013 of the European Parliament and of the Council and of the reference to the publication of the product specification for a name in the wine sector (Cebreros (PDO))Council Implementing Decision (CFSP) 2018/1868 of 28 November 2018 implementing Decision (CFSP) 2015/1333 concerning restrictive measures in view of the situation in LibyaCommission Decision (EU) 2018/1905 of 28 November 2018 on the proposed citizens' initiative entitled ‘EU wide referendum whether the European Citizens want the United Kingdom to remain or to leave!’ (notified under document C(2018) 8006)Commission Implementing Decision of 27 November 2018 on the publication in the Official Journal of the European Union of an application for amendment of a specification for a name in the wine sector referred to in Article 105 of Regulation (EU) No 1308/2013 of the European Parliament and of the Council (Cataluña/Catalunya (PDO))Commission Implementing Decision (EU) 2018/1855 of 27 November 2018 on greenhouse gas emissions covered by Decision No 406/2009/EC of the European Parliament and of the Council for the year 2016 for each Member StateCouncil Decision of 26 November 2018 adopting the Council’s position on draft amending budget No 6 of the European Union for the financial year 2018Commission Implementing Decision of 26 November 2018 on the publication in the Official Journal of the European Union of the application for approval of an amendment, which is not minor, to a product specification referred to in Article 53 of Regulation (EU) No 1151/2012 of the European Parliament and of the Council for the name ‘Lechazo de Castilla y León’ (PGI)Council Decision (EU) 2018/1867 of 26 November 2018 on the position to be adopted, on behalf of the European Union, within the EEA Joint Committee, concerning the amendment of Annex IX (Financial Services) to the EEA Agreement (Omnibus II) (Text with EEA relevance.)Council Decision (EU) 2018/1869 of 26 November 2018 on the signing, on behalf of the Union, of the Agreement between the European Union and the Federative Republic of Brazil amending the Agreement between the European Union and the Federative Republic of Brazil on short-stay visa waiver for holders of diplomatic, service or official passportsCouncil Decision (EU) 2018/1870 of 26 November 2018 on the signing, on behalf of the Union, of the Agreement between the European Union and the Federative Republic of Brazil amending the Agreement between the European Union and the Federative Republic of Brazil on short-stay visa waiver for holders of ordinary passportsCouncil Decision (EU) 2018/1875 of 26 November 2018 establishing the position to be adopted on behalf of the European Union within the Committee of Technical Experts of the Intergovernmental Organisation for International Carriage by Rail (OTIF) as regards certain amendments to the Uniform Technical Prescriptions — General Provisions — Subsystems (UTP GEN-B) and the Uniform Technical Prescriptions — Telematics applications for freight services (UTP TAF)

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

Contents

What to look at next