Commission Decision (EU) 2016/152 of 1 October 2014 on State aid SA 27339 (12/C) (ex 11/NN) implemented by Germany for Zweibrücken airport and airlines using the airport (notified under document C(2014) 5063) (Text with EEA relevance)

Commission Decision (EU) 2016/152 of 1 October 2014 on State aid SA 27339 (12/C) (ex 11/NN) implemented by Germany for Zweibrücken airport and airlines using the airport (notified under document C(2014) 5063) (Text with EEA relevance)

Decision (EU) 2016/152 · Decision · 6 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Article 1

Open ↗

1.   The State aid, unlawfully put into effect by Germany in breach of Article 108(3) of the Treaty in favour of Flugplatz GmbH Aeroville Zweibrücken (‘FGAZ’)/ Flughafen Zweibrücken GmbH (‘FZG’) between 2000 and 2009 by means of direct investment grants, annual capital injections, the grant of a 100 % guarantee on a bank loan free of charge, and allowing FGAZ to participate in Land Rhineland-Pfalz's cash-pool, is incompatible with the internal market. 2.   The State aid, unlawfully put into effect by Germany in breach of Article 108(3) of the Treaty in favour of Germanwings, TUIFly and Ryanair/AMS by means of the airport services agreements and marketing services agreements concluded on 15 September 2006 (Germanwings), 1 April 2008 (TUIFly), and 22 September 2008/6 October 2008 (Ryanair/Airport Marketing Services (‘AMS’)) is incompatible with the internal market.

Article 2

Open ↗

1.   The loan granted to FZG by Sparkasse Südwestpfalz does not constitute State aid. 2.   The airport services agreement concluded by FZG with Germanwings on 30 June 2008 does not constitute State aid.

Article 3

Open ↗

1.   Germany shall recover the incompatible aid referred to in Article 1 from the beneficiaries. 2.   FGAZ and FZG shall be jointly liable to repay the State aid received by either of them. 3.   Ryanair and AMS shall be jointly liable to repay the State aid received by either of them. 4.   The sums to be recovered are as follows: (a) in respect of the direct investment grants granted by the Land Rhineland-Palatinate and the ZEF in favour of FZG: EUR 20 564 170 granted between 12 December 2000 and 31 December 2009, minus the costs of fire brigade services and the costs for which the airport operator is entitled to reimbursement pursuant to §8(3) Luftsicherheitsgesetz to the extent that they were covered by the direct investment grants; (b) in respect of the annual capital injections granted by the Land Rhineland-Palatinate and the ZEF in favour of FGAZ: EUR 26 629 000 granted between 2000 and 2009, minus the costs of fire brigade services and the costs for which the airport operator is entitled to reimbursement pursuant to §8(3) Luftsicherheitsgesetz to the extent that they were covered by the annual capital injections, and minus those sums granted before 12 December 2000; (c) in respect of the 100 % guarantee on the loan granted by the Land Rhineland-Palatinate in favour of FZG: the cash-equivalent of the value of the guarantee, to be determined pursuant to the Commission Notice on the application of Article 87 and 88 of the EC Treaty to State aid in the form of guarantees; (d) in respect of the participation of FGAZ in the cash-pool of Land Rhineland-Palatinate: the cash-equivalent of the advantageous loan conditions, to be determined pursuant to the Communication from the Commission on the revision of the method for setting the reference and discount rates of 12 December 2007, minus any advantage received on loans that were used to cover the costs of fire brigade services and the costs for which the airport operator is entitled to reimbursement pursuant to §8(3) Luftsicherheitsgesetz ; (e) in respect of the airport services agreement concluded between Germanwings and FZG on 15 September 2006: the amount of incompatible aid; (f) in respect of the airport services agreement concluded between TUIFly and FZG on 1 April 2008: the amount of incompatible aid; (g) in respect of the airport services agreement and marketing services agreements concluded between Ryanair and FZG on 22 September 2008 and between AMS and the Land Rhineland-Palatinate on 6 October 2008: the amount of incompatible aid. 5.   The sums to be recovered shall bear interest from the date on which they were put at the disposal of the beneficiaries until their actual recovery. 6.   Germany shall provide the exact dates on which the aid provided by the State was put at the disposal of the respective beneficiaries. 7.   The interest shall be calculated on a compound basis in accordance with Chapter V of Commission Regulation (EC) No 794/2004  ( 118 ) . 8.   Germany shall cancel all outstanding payments of the aid referred to in Article 1 with effect from the date of adoption of this Decision.

Article 4

Open ↗

1.   Recovery of the aid referred to in Article 1 shall be immediate and effective. 2.   Germany shall ensure that this Decision is implemented within four months following the date of notification of this Decision.

Article 5

Open ↗

1.   Within two months following notification of this Decision, Germany shall submit the following information: (a) the total amount of aid received by the beneficiaries, and in particular: (i) the amount of direct investment grants, capital injections, and the cash-equivalent of advantageous loans that covered the costs of fire brigade services and costs for which the airport operator is entitled to reimbursement pursuant to §8(3) LuftSiG; (ii) information on the creditworthiness of FGAZ/FZG when the 100 % guarantee was issued and when each loan from the cash-pool was provided, with a view to enabling the Commission to determine the cash-equivalent of the guarantee and the advantageous conditions of the cash-pool loans in line with the Commission Notice on the application of Article 87 and 88 of the EC Treaty to State aid in the form of guarantees and Communication from the Commission on the revision of the method for setting the reference and discount rates of 12 December 2007, respectively; (b) the total amount (principal and recovery interests) to be recovered from each beneficiary; (c) a detailed description of the measures already taken and planned to comply with this Decision; (d) documents demonstrating that the beneficiaries have been ordered to repay the aid. 2.   Germany shall keep the Commission informed of the progress of the national measures taken to implement this Decision until recovery of the aid referred to in Article 1 has been completed. It shall immediately submit, on simple request by the Commission, information on the measures already taken and planned to comply with this Decision. It shall also provide detailed information concerning the amounts of aid and recovery interest already recovered from the beneficiaries.

Article 6

Open ↗

This Decision is addressed to the Federal Republic of Germany.

Other acts of the same type
2013/765/EU: Commission Implementing Decision of 13 December 2013 amending the recognition of Det Norske Veritas pursuant to Regulation (EC) No 391/2009 of the European Parliament and of the Council on common rules and standards for ship inspection and survey organisations (notified under document C(2013) 8876) Text with EEA relevance2013/766/EU: Commission Implementing Decision of 13 December 2013 approving certain amended programmes for the eradication, control and monitoring of animal diseases and zoonoses for the year 2013, amending Decision 2008/897/EC approving annual and multiannual programmes for 2009 and following years and amending Implementing Decision 2012/761/EU as regards the Union financial contribution for certain programmes approved by that Decision (notified under document C(2013) 8891)2013/790/EU: Council Decision of 13 December 2013 on the acceptance on behalf of the European Union of the Amendment to Articles 25 and 26 of the Convention on the Protection and Use of Transboundary Watercourses and International Lakes2013/791/Euratom: Council Decision of 13 December 2013 amending Decision 2007/198/Euratom establishing the European Joint Undertaking for ITER and the Development of Fusion Energy and conferring advantages upon it2013/759/EU: Council Decision of 12 December 2013 regarding transitional EDF management measures from 1 January 2014 until the entry into force of the 11th European Development Fund2013/761/EU: Commission Decision of 12 December 2013 on the notification by the United Kingdom of Great Britain and Northern Ireland of a transitional national plan referred to in Article 32 of Directive 2010/75/EU of the European Parliament and of the Council on industrial emissions (notified under document C(2013) 8815)2013/763/EU: Commission Implementing Decision of 12 December 2013 on excluding from European Union financing certain expenditure incurred by the Member States under the Guarantee Section of the European Agricultural Guidance and Guarantee Fund (EAGGF), under the European Agricultural Guarantee Fund (EAGF) and under the European Agricultural Fund for Rural Development (EAFRD) (notified under document C(2013) 8743)2013/751/EU: Commission Decision of 11 December 2013 on the notification by the Republic of Lithuania of a transitional national plan referred to in Article 32 of Directive 2010/75/EU of the European Parliament and of the Council on industrial emissions (notified under document C(2013) 8636)2013/752/EU: Commission Implementing Decision of 11 December 2013 amending Decision 2006/771/EC on harmonisation of the radio spectrum for use by short-range devices and repealing Decision 2005/928/EC (notified under document C(2013) 8776) Text with EEA relevance2013/753/EU: Commission Implementing Decision of 11 December 2013 amending Decision 2012/226/EU on the second set of common safety targets for the rail system (notified under document C(2013) 8780) Text with EEA relevance2013/769/EU: Commission Implementing Decision of 11 December 2013 refusing the request by Hungary to introduce a Quick Reaction Mechanism special measure derogating from Article 193 of Council Directive 2006/112/EC on the common system of value added tax (notified under document C(2013) 9007)2013/787/EU: Decision of the European Parliament and of the Council of 11 December 2013 on mobilisation of the European Globalisation Adjustment Fund, in accordance with point 28 of the Interinstitutional Agreement of 17 May 2006 between the European Parliament, the Council and the Commission on budgetary discipline and sound financial management (application EGF/2012/011 DK/Vestas from Denmark)

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

Contents

What to look at next