My bookmarksSign up free
Source

Commission Decision (EU) 2016/2069 of 1 October 2014 concerning measures SA.14093 (C76/2002) implemented by Belgium in favour of Brussels South Charleroi Airport and Ryanair (notified under document C(2014) 6849) (Text with EEA relevance )

Commission Decision (EU) 2016/2069 of 1 October 2014 concerning measures SA.14093 (C76/2002) implemented by Belgium in favour of Brussels South Charleroi Airport and Ryanair (notified under document C(2014) 6849) (Text with EEA relevance )

Decision (EU) 2016/2069 · Decision · 8 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Article 1

Open ↗

1.   The aid measures granted to Ryanair Ltd (hereinafter ‘Ryanair’), namely the undertaking of the Walloon Government to Ryanair of 6 November 2001, the contract between BSCA and Ryanair of 2 December 2001, the Promocy agreement of 12 December 2001, the contract between Promocy and Leading Verge of 31 January 2002, the Ministerial Order of 11 June 2004, the letter from BSCA to Ryanair of 24 June 2004, the commercial agreement between BSCA and Ryanair of 9 December 2005, the amendment of 6 December 2010 to the contract between BSCA and Ryanair, and the sale of BSCA's shares in Promocy on 31 March 2010, do not constitute State aid to Ryanair under Article 107(1) of the Treaty on the Functioning of the European Union. 2.   The aid measures granted to Brussels South Charleroi Airport (hereinafter ‘BSCA’), consisting of the agreement between the Société wallonne des aéroports (hereinafter ‘SOWAER’) and BSCA of 4 April 2006, Amendment No 5 to the agreement between the Walloon Region and BSCA of 10 March 2006, and Amendment No 6 to the agreement between the Walloon Region and BSCA of 15 January 2008, do not constitute State aid to BSCA under Article 107(1) of the Treaty on the Functioning of the European Union.

Article 2

Open ↗

1.   The aid measures unlawfully granted by Belgium, in breach of Article 108(3) of the Treaty on the Functioning of the European Union, to BSCA under the sub-concession agreement of 15 April 2002 between SOWAER and BSCA and Amendment No 3 of 29 March 2002 to the agreement between the Walloon Region and BSCA, and also under the investment decision of the Walloon Region of 3 April 2003, constitute State aid compatible with the internal market on the basis of Article 107(3)(c) of the Treaty on the Functioning of the European Union up to 3 April 2014. 2.   Assuming that it does constitute State aid within the meaning of Article 107(1) of the Treaty on the Functioning of the European Union, the capital increase in BSCA subscribed on 3 December 2002 by SOWAER is State aid compatible with the internal market on the basis of Article 107(3)(c) of the Treaty on the Functioning of the European Union.

Article 3

Open ↗

The aid measures unlawfully granted by Belgium, in breach of Article 108(3) of the Treaty on the Functioning of the European Union, to BSCA under the sub-concession agreement of 15 April 2002 between SOWAER and BSCA and Amendment No 3 of 29 March 2002 to the agreement between the Walloon Region and BSCA, and also under the investment decision of the Walloon Region of 3 April 2003, constitute State aid incompatible with the internal market on the basis of Article 107(1) of said Treaty from 4 April 2014.

Article 4

Open ↗

1.   Belgium shall put an end to the aid measures referred to in Article 3 by increasing the concession fee payable by BSCA at least to the level of the market price concession fee and by recovering from the beneficiary the aid amounts received under the aid measures referred to in Article 3 as from 4 April 2014. 2.   The amounts to be recovered shall bear interest from the date on which they were placed at the disposal of the beneficiary to the date of their effective recovery. 3.   The interest shall be calculated on a compound basis in accordance with Chapter V of Regulation (EC) No 794/2004. 4.   Belgium shall cancel all pending payments with regard to the aid measures referred to in Article 3 from the date of adoption of this decision.

Article 5

Open ↗

1.   The recovery of the aid referred to in Article 3 shall be immediate and effective. 2.   Belgium shall ensure that this decision is implemented within four months of the date of its notification.

Article 6

Open ↗

1.   Belgium shall submit the following information to the Commission within two months of the notification of this decision: (a) the dates on which BSCA has paid the concession fees in 2014 and the calculation of the recovery interest; (b) a detailed description of the measures already adopted and planned for the purpose of complying with this decision; (c) the documents proving that the beneficiary has been ordered to repay the aid. 2.   Belgium shall keep the Commission informed of the progress of the national measures adopted pursuant to this decision until the recovery of the aid referred to in Article 3 has been concluded. At the Commission's request, it shall immediately submit information on the measures already adopted and planned for the purpose of complying with this decision. It shall also provide detailed information on the aid amounts and interest already recovered from the beneficiary.

Supplementary provisions

ANNEXSupplementary provisions

Open ↗

ANNEX Information on amounts received, to be recovered and already recovered Identity of the beneficiary Total amount of the aid received  ( *1 ) Total amount of the aid to be recovered  ( *1 ) (Principal) Total amount already repaid  ( *1 ) Principal Interest                                                                       ( *1 )   EUR Million

Other acts of the same type
Commission Implementing Decision (EU) of 28 February 2024 establishing a list of geographical indications protected under Regulation (EU) 2019/787 of the European Parliament and of the Council to be filed as applications for international registration pursuant to Article 2 of Regulation (EU) 2019/1753 of the European Parliament and of the CouncilCommission Implementing Decision of 28 February 2024 establishing a list of geographical indications protected under Regulation (EU) No 1308/2013 of the European Parliament and of the Council to be filed as applications for international registration pursuant to Article 2 of Regulation (EU) 2019/1753 of the European Parliament and of the CouncilCommission Implementing Decision of 28 February 2024 establishing a list of geographical indications protected under Regulation (EU) No 1151/2012 of the European Parliament and of the Council to be filed as applications for international registration pursuant to Article 2 of Regulation (EU) 2019/1753 of the European Parliament and of the CouncilCommission Implementing Decision (EU) 2024/731 of 28 February 2024 postponing the expiry date of the approval of indoxacarb for use in biocidal products of product-type 18 in accordance with Regulation (EU) No 528/2012 of the European Parliament and of the CouncilCommission Implementing Decision (EU) 2024/732 of 28 February 2024 postponing the expiry date of the approval of aluminium phosphide for use in biocidal products of product-types 14 and 18 in accordance with Regulation (EU) No 528/2012 of the European Parliament and of the CouncilCommission Implementing Decision (EU) 2024/733 of 28 February 2024 postponing the expiry date of the approval of cholecalciferol for use in biocidal products of product-type 14 in accordance with Regulation (EU) No 528/2012 of the European Parliament and of the CouncilCommission Implementing Decision (EU) 2024/787 of 28 February 2024 postponing the expiry date of the approval of magnesium phosphide for use in biocidal products of product-type 18 in accordance with Regulation (EU) No 528/2012 of the European Parliament and of the CouncilCommission Decision (EU) 2024/721 of 27 February 2024 establishing, pursuant to Directive 2000/60/EC of the European Parliament and of the Council, the values of the Member State monitoring system classifications as a result of the intercalibration exercise and repealing Commission Decision (EU) 2018/229 (notified under document C(2024) 1113)Commission Implementing Decision (EU) 2024/734 of 27 February 2024 postponing the expiry date of the approval of brodifacoum, bromadiolone, chlorophacinone, coumatetralyl, difenacoum, difethialone and flocoumafen for use in biocidal products of product-type 14 in accordance with Regulation (EU) No 528/2012 of the European Parliament and of the CouncilCommission Decision (EU) 2024/699 of 26 February 2024 approving, on behalf of the European Union, the amendment of Annex X to the Comprehensive and Enhanced Partnership Agreement between the European Union and the European Atomic Energy Community and their Member States, of the one part, and the Republic of Armenia, of the other partCouncil Implementing Decision (CFSP) 2024/756 of 26 February 2024 implementing Decision (CFSP) 2015/1333 concerning restrictive measures in view of the situation in LibyaCouncil Decision (CFSP) 2024/769 of 26 February 2024 amending Decision 2012/642/CFSP concerning restrictive measures in view of the situation in Belarus and the involvement of Belarus in the Russian aggression against Ukraine

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

Contents

What to look at next