Commission Decision (EU) 2019/293 of 8 November 2018 on the State aid SA.43785 (2018/C) (ex 2015/PN, ex 2018/NN) implemented by Romania for restructuring Complexul Energetic Hunedoara (notified under document C(2018) 7308) (Text with EEA relevance.)

Commission Decision (EU) 2019/293 of 8 November 2018 on the State aid SA.43785 (2018/C) (ex 2015/PN, ex 2018/NN) implemented by Romania for restructuring Complexul Energetic Hunedoara (notified under document C(2018) 7308) (Text with EEA relevance.)

Decision (EU) 2019/293 · Decision · 6 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Article 1

Open ↗

The International Bank for Reconstruction and Development loan (IBRD loan) guaranteed by the Romanian State and for which CE Hunedoara became the successor beneficiary was not unlawfully granted to CE Hunedoara, in breach of Article 108(3) of the Treaty on the Functioning of the European Union.

Article 2

Open ↗

The following loans in favour of CE Hunedoara and in the amounts set out in points (a) to (d), constitute State aid which was unlawfully granted (or not reimbursed as regards point (d)) by Romania, in breach of Article 108(3) of the Treaty on the Functioning of the European Union and are incompatible with the internal market: (a) Romanian Commercial Bank loan contracted by the Ministry of Finance and further made available to CE Hunedoara by way of subsidiary loan agreement (BCR loan) — RON 83 485 450. (b) Romanian Development Bank loan contracted by the Ministry of Finance and further made available to CE Hunedoara by way of subsidiary loan agreement (BRD loan) — RON 68 371 170. (c) loan provided for the payment of the incompatible aid requested to be recovered by the Decision regarding the incompatible aid (the loan to repay the incompatible aid) — RON 34 785 015. (d) loan representing aid granted in accordance with the rescue aid decision and interest (the rescue aid loan) — as effectively disbursed for the amount of RON 98 476 900 and not reimbursed after six months of disbursement.

Article 3

Open ↗

1.   Romania shall recover the incompatible aid, referred to in Article 2 from the beneficiary. 2.   The actual sums to be recovered shall equal the amounts effectively disbursed to the beneficiary and not reimbursed by the latter to the Romanian State; these sums shall also bear interest from the date on which they were put at the disposal of the beneficiary until their actual recovery. 3.   The interest shall be calculated on a compound basis in accordance with Chapter V of Commission Regulation (EC) No 794/2004  ( 44 ) . 4.   Romania shall cancel all outstanding payments of the aid referred to in Article 2 with effect from the date of adoption of this decision.

Article 4

Open ↗

1.   Recovery of the aid referred to in Article 2 shall be immediate and effective, without prejudice of appropriate measures which Romania may adopt with a view to preserving the continued operation of electricity generation assets which are necessary to supply electricity and heating, provided such measures are proportionate, reasonable, and limited in time and scope to what is indispensable to maintain the value of the assets. 2.   Romania shall ensure that this Decision is implemented within four months following the date of notification of this Decision.

Article 5

Open ↗

1.   Within two months following notification of this Decision, Romania shall submit the following information to the Commission: (a) the total amount (principal and recovery interests) to be recovered from the beneficiary; (b) a detailed description of the measures already taken and planned to comply with this Decision; (c) a detailed description of the measures already taken and planned to preserve the continued operation of electricity generation assets; (d) documents demonstrating that the beneficiary has been ordered to repay the aid. 2.   Romania shall keep the Commission informed of the progress of the national measures taken to implement this Decision until recovery of the aid referred to in Article 2 has been completed. It shall immediately submit, on simple request by the Commission, information on the measures already taken and planned to comply with this Decision. It shall also provide detailed information concerning the amounts of aid and recovery interest already recovered from the beneficiary.

Other acts of the same type
Council Decision (CFSP) 2023/421 of 24 February 2023 amending Decision 2012/642/CFSP concerning restrictive measures in view of the situation in Belarus and the involvement of Belarus in the Russian aggression against UkraineCommission Implementing Decision (EU) 2023/423 of 24 February 2023 on a pilot project to implement the administrative cooperation provisions relating to regulated professions set out in Directives 2005/36/EC and (EU) 2018/958 of the European Parliament and of the Council by means of the Internal Market Information System and to integrate the database of regulated professions into that system (Text with EEA relevance)Commission Implementing Decision (EU) 2023/424 of 24 February 2023 amending Implementing Decision (EU) 2019/450 as regards the publication of references of European Assessment Documents for special drawn sheet glass and other construction products (Text with EEA relevance)Council Decision (CFSP) 2023/408 of 23 February 2023 amending Decision 2013/255/CFSP concerning restrictive measures in view of the situation in SyriaCommission Implementing Decision (EU) 2023/415 of 22 February 2023 renewing the authorisation for the placing on the market of products containing, consisting of or produced from genetically modified soybean A5547-127 (ACS-GMØØ6-4) pursuant to Regulation (EC) No 1829/2003 of the European Parliament and of the Council (notified under document C(2023) 1126) (Only the German text is authentic) (Text with EEA relevance)Commission Implementing Decision (EU) 2023/416 of 22 February 2023 authorising the placing on the market of products containing, consisting of or produced from genetically modified oilseed rape MON 94100 (MON-941ØØ-2) pursuant to Regulation (EC) No 1829/2003 of the European Parliament and of the Council (notified under document C(2023) 1135) (Only the Dutch text is authentic) (Text with EEA relevance)Commission Implementing Decision (EU) 2023/437 of 22 February 2023 on the request for registration of the European citizens’ initiative entitled ‘Ensuring a dignified reception of migrants in Europe’, pursuant to Regulation (EU) 2019/788 of the European Parliament and of the Council (notified under document C(2023) 1121) (Only the English text is authentic)Council Decision (EU) 2023/412 of 21 February 2023 as regards the extension of the period of entitlement for audiovisual co-productions as provided for in Article 5 of the Protocol on Cultural Cooperation to the Free Trade Agreement between the European Union and its Member States, of the one part, and the Republic of Korea, of the other partCouncil Decision (EU) 2023/413 of 21 February 2023 as regards the extension of the period of entitlement for audiovisual co-productions as provided for in Article 5 of the Protocol on Cultural Cooperation to the Free Trade Agreement between the European Union and its Member States, of the one part, and the Republic of Korea, of the other partCouncil Decision (EU) 2023/456 of 21 February 2023 on the position to be adopted, on behalf of the European Union, within the EEA Joint Committee, as regards the amendment to Annex XI (Electronic communication, audiovisual services and information society) and Protocol 37 containing the list provided for in Article 101 of the EEA Agreement (Text with EEA relevance)Council Decision (CFSP) 2023/380 of 20 February 2023 amending Decision 2013/184/CFSP concerning restrictive measures in view of the situation in Myanmar/BurmaCouncil Implementing Decision (CFSP) 2023/381 of 20 February 2023 implementing Decision 2011/235/CFSP concerning restrictive measures directed against certain persons and entities in view of the situation in Iran

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

Contents

What to look at next