Commission Implementing Decision (EU) 2025/1040 of 16 May 2025 on the inconsistency of certain performance targets included in the draft national and functional airspace block performance plans submitted by Belgium, Denmark, Germany, Estonia, Ireland, Greece, France, Latvia, Luxembourg, the Netherlands and Slovakia pursuant to Regulation (EC) No 549/2004 of the European Parliament and of the Council with the Union-wide performance targets for the fourth reference period of the Single European Sky performance and charging scheme (notified under document C(2025) 2930)

Commission Implementing Decision (EU) 2025/1040 of 16 May 2025 on the inconsistency of certain performance targets included in the draft national and functional airspace block performance plans submitted by Belgium, Denmark, Germany, Estonia, Ireland, Greece, France, Latvia, Luxembourg, the Netherlands and Slovakia pursuant to Regulation (EC) No 549/2004 of the European Parliament and of the Council with the Union-wide performance targets for the fourth reference period of the Single European Sky performance and charging scheme (notified under document C(2025) 2930)

Implementing Decision (EU) 2025/1040 · Decision · 5 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Article 1

Open ↗

The performance targets listed in the Annex to this Decision, which are included in the draft functional airspace block performance plan submitted by Belgium, Germany, France, Luxembourg and the Netherlands, and in the draft national performance plans submitted by Denmark, Estonia, Ireland, Greece, Latvia and Slovakia, are inconsistent with the Union-wide performance targets for the fourth reference period (‘RP4’) set out in Implementing Decision (EU) 2024/1688.

Article 2

Open ↗

Greece shall revise its en route capacity targets for 2025 and 2026, expressed as the average minutes of en route air traffic flow management delay per flight, to make them consistent with the Union-wide performance targets in the key performance area of capacity set out in Article 4 of Implementing Decision (EU) 2024/1688. Where the Network Operations Plan of 2 July 2024 drawn up in accordance with Article 9 of Commission Implementing Regulation (EU) 2019/123 recommends specific additional measures to improve capacity performance, account shall be taken of those measures when revising the capacity performance targets referred to in the first paragraph.

Article 3

Open ↗

Belgium, Denmark, Germany, Estonia, Ireland, Greece, Latvia, Luxembourg, the Netherlands and Slovakia shall revise downwards the cost-efficiency targets set for their en route charging zones, expressed as determined unit cost (DUC). When revising their cost-efficiency targets, those Member States shall: (a) ensure that the revised cost-efficiency targets are consistent both with the Union-wide DUC trend and with the Union-wide long-term DUC trend, referred to, respectively, in point 1.4(a) and (b) of Annex IV to Implementing Regulation (EU) 2019/317; (b) reduce the level of determined costs accordingly, in particular in respect of calendar year 2029; (c) use the latest traffic forecasts, expressed in service units, in accordance with Article 10(2) of Implementing Regulation (EU) 2019/317. By way of derogation from the first paragraph, point (a), where the baseline value of the relevant en route charging zone fulfils the criterion laid down in point 1.4(c) of Annex IV to Implementing Regulation (EU) 2019/317, the Member State concerned shall ensure that the revised cost-efficiency targets are consistent at least with the Union-wide DUC trend or with the Union-wide long-term DUC trend. Where a Member State invokes, in its revised draft performance plan to be submitted in accordance with Article 14(3), second subparagraph, of Implementing Regulation (EU) 2019/317, a deviation under point 1.4(d) of Annex IV to that Implementing Regulation, it shall ensure that such a deviation is substantiated with adequate information and justifications. In particular, the Member State concerned shall demonstrate that any measures invoked to justify a deviation from Union-wide cost-efficiency targets relate solely to additional operational resources or technical capabilities necessary to meet the capacity targets.

Article 4

Open ↗

This Decision is addressed to the Kingdom of Belgium, the Kingdom of Denmark, the Federal Republic of Germany, the Republic of Estonia, Ireland, the Hellenic Republic, the French Republic, the Republic of Latvia, the Grand Duchy of Luxembourg, the Kingdom of the Netherlands and the Slovak Republic.

Supplementary provisions

ANNEXSupplementary provisions

Open ↗

ANNEX Performance targets found to be inconsistent with the Union-wide performance targets for the fourth reference period 1.    TARGETS INCLUDED IN THE DRAFT FABEC PERFORMANCE PLAN SUBMITTED BY BELGIUM, GERMANY, FRANCE, LUXEMBOURG AND THE NETHERLANDS KEY PERFORMANCE AREA OF COST-EFFICIENCY En route charging zone of Belgium-Luxembourg 2019 baseline value 2024 baseline value 2025 2026 2027 2028 2029 Targets and baseline values in the key performance area of cost-efficiency, expressed as determined unit cost (in real terms at 2022 prices) EUR 94,14 EUR 104,26 EUR 104,94 EUR 106,08 EUR 106,14 EUR 104,43 EUR 103,83 En route charging zone of Germany 2019 baseline value 2024 baseline value 2025 2026 2027 2028 2029 Targets and baseline values in the key performance area of cost-efficiency, expressed as determined unit cost (in real terms at 2022 prices) EUR 71,71 EUR 74,90 EUR 73,16 EUR 73,06 EUR 73,10 EUR 71,87 EUR 70,54 En route charging zone of the Netherlands 2019 baseline value 2024 baseline value 2025 2026 2027 2028 2029 Targets and baseline values in the key performance area of cost-efficiency, expressed as determined unit cost (in real terms at 2022 prices) EUR 86,52 EUR 104,60 EUR 103,51 EUR 103,61 EUR 106,50 EUR 106,28 EUR 105,95 2.    TARGETS INCLUDED IN THE DRAFT PERFORMANCE PLAN OF DENMARK KEY PERFORMANCE AREA OF COST-EFFICIENCY En route charging zone of Denmark 2019 baseline value 2024 baseline value 2025 2026 2027 2028 2029 Targets and baseline values in the key performance area of cost-efficiency, expressed as determined unit cost (in real terms at 2022 prices) DKK 466,58 DKK 543,10 DKK 529,76 DKK 521,41 DKK 515,34 DKK 506,93 DKK 500,26 EUR 62,74 EUR 73,02 EUR 71,23 EUR 70,11 EUR 69,29 EUR 68,16 EUR 67,26 3.    TARGETS INCLUDED IN THE DRAFT PERFORMANCE PLAN OF ESTONIA KEY PERFORMANCE AREA OF COST-EFFICIENCY En route charging zone of Estonia 2019 baseline value 2024 baseline value 2025 2026 2027 2028 2029 Targets and baseline values in the key performance area of cost-efficiency, expressed as determined unit cost (in real terms at 2022 prices) EUR 38,12 EUR 54,69 EUR 50,46 EUR 52,95 EUR 54,37 EUR 54,54 EUR 55,69 4.    TARGETS INCLUDED IN THE DRAFT PERFORMANCE PLAN OF GREECE KEY PERFORMANCE AREA OF CAPACITY Greece 2025 2026 2027 2028 2029 Targets in the key performance area of capacity , expressed in minutes of en route ATFM delay per flight 0,69 0,50 0,19 0,16 0,16 KEY PERFORMANCE AREA OF COST-EFFICIENCY En route charging zone of Greece 2019 baseline value 2024 baseline value 2025 2026 2027 2028 2029 Targets and baseline values in the key performance area of cost-efficiency, expressed as determined unit cost (in real terms at 2022 prices) EUR 28,84 EUR 25,04 EUR 24,67 EUR 24,01 EUR 24,95 EUR 26,40 EUR 25,72 5.    TARGETS INCLUDED IN THE DRAFT PERFORMANCE PLAN OF IRELAND KEY PERFORMANCE AREA OF COST-EFFICIENCY En route charging zone of Ireland 2019 baseline value 2024 baseline value 2025 2026 2027 2028 2029 Targets and baseline values in the key performance area of cost-efficiency, expressed as determined unit cost (in real terms at 2022 prices) EUR 27,59 EUR 27,29 EUR 28,61 EUR 29,72 EUR 29,75 EUR 29,84 EUR 30,14 6.    TARGETS INCLUDED IN THE DRAFT PERFORMANCE PLAN OF LATVIA KEY PERFORMANCE AREA OF COST-EFFICIENCY En route charging zone of Latvia 2019 baseline value 2024 baseline value 2025 2026 2027 2028 2029 Targets and baseline values in the key performance area of cost-efficiency, expressed as determined unit cost (in real terms at 2022 prices) EUR 28,57 EUR 37,97 EUR 48,73 EUR 53,56 EUR 57,79 EUR 61,14 EUR 63,75 7.    TARGETS INCLUDED IN THE DRAFT PERFORMANCE PLAN OF SLOVAKIA KEY PERFORMANCE AREA OF COST-EFFICIENCY En route charging zone of Slovakia 2019 baseline value 2024 baseline value 2025 2026 2027 2028 2029 Targets and baseline values in the key performance area of cost-efficiency, expressed as determined unit cost (in real terms at 2022 prices) EUR 56,20 EUR 60,11 EUR 62,58 EUR 61,85 EUR 61,12 EUR 59,71 EUR 58,34

Other acts of the same type
Commission Implementing Decision (EU) 2025/896 of 12 May 2025 amending the Annex to Implementing Decision (EU) 2023/2447 concerning emergency measures in relation to outbreaks of highly pathogenic avian influenza in certain Member States (notified under document C(2025) 3047)Council Decision (EU) 2025/915 of 12 May 2025 establishing the position to be adopted on behalf of the European Union in the World Trade Organization as regards the incorporation of the Agreement on Electronic Commerce into the Agreement establishing the World Trade OrganizationCouncil Decision (EU) 2025/942 of 12 May 2025 on the position to be taken on behalf of the European Union within the Trade Specialised Committee on Administrative Cooperation in VAT and Recovery of Taxes and Duties established by the Trade and Cooperation Agreement between the European Union and the European Atomic Energy Community, of the one part, and the United Kingdom of Great Britain and Northern Ireland, of the other partCouncil Decision (EU) 2025/961 of 12 May 2025 on the conclusion, on behalf of the European Union, of the Protocol on the implementation of the Fisheries Partnership Agreement between the European Community and the Republic of Guinea-Bissau (2024–2029)Council Decision (EU) 2025/962 of 12 May 2025 on the conclusion, on behalf of the European Union, of the Agreement between the European Union, Iceland, the Principality of Liechtenstein and the Kingdom of Norway on an EEA Financial Mechanism for the period May 2021–April 2028, the Agreement between the Kingdom of Norway and the European Union on a Norwegian Financial Mechanism for the period May 2021–April 2028, the Additional Protocol to the Agreement between the European Economic Community and the Kingdom of Norway and the Additional Protocol to the Agreement between the European Economic Community and Iceland (Text with EEA relevance)Council Decision (EU) 2025/1115 of 12 May 2025 on the position to be taken on behalf of the European Union within the Group of Experts on the European Agreement concerning the Work of Crews of Vehicles Engaged in International Road Transport (AETR) and within the Working Party on Road Transport of the United Nations Economic Commission for Europe as regards a proposal to align the AETR with the main recent amendments to Regulation (EC) No 561/2006Decision (EU) 2025/1018 of the European Parliament and of the Council of 7 May 2025 on the mobilisation of the European Globalisation Adjustment Fund for Displaced Workers following an application from Belgium – EGF/2024/003 BE/Van HoolDecision of the Bureau of the European Parliament of 5 May 2025 concerning Rules on access to the European ParliamentDecision of the Bureau of the European Parliament of 5 May 2025 laying down the Rules on the European Order of MeritDecision of the Bureau of the European Parliament of 5 May 2025 laying down the Rules on conditionality and on the declaration and publication of meetings of Parliament’s managers with interest representatives and with representatives of public authorities of third countriesCouncil Decision (EU) 2025/894 of 5 May 2025 on the position to be taken on behalf of the European Union within the EPA Council and within the Committee of Senior Officials established by the Economic Partnership Agreement between the European Union, of the one part, and the Republic of Kenya, Member of the East African Community, of the other part as regards the adoption of the Rules of Procedure for the EPA Council, of the Rules of Procedure for Dispute Settlement and the Code of Conduct for Arbitrators and Mediators, and of the Rules of Procedure for the Committee of Senior OfficialsCommission Implementing Decision (EU) 2025/859 of 30 April 2025 amending Implementing Decision (EU) 2024/2207 concerning certain emergency measures relating to sheep pox and goat pox in Greece (notified under document C(2025) 2733)

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

Contents

What to look at next