Commission Implementing Decision (EU) 2025/1332 of 9 July 2025 on the implementation of the Rail Baltica cross-border project on the North Sea – Baltic European Transport Corridor and the Baltic Sea – Black Sea – Aegean Sea European Transport Corridor in application of Regulation (EU) 2024/1679 of the European Parliament and of the Council and repealing Commission Implementing Decision (EU) 2018/1723 (notified under document C(2025) 3944)

Commission Implementing Decision (EU) 2025/1332 of 9 July 2025 on the implementation of the Rail Baltica cross-border project on the North Sea – Baltic European Transport Corridor and the Baltic Sea – Black Sea – Aegean Sea European Transport Corridor in application of Regulation (EU) 2024/1679 of the European Parliament and of the Council and repealing Commission Implementing Decision (EU) 2018/1723 (notified under document C(2025) 3944)

Implementing Decision (EU) 2025/1332 · Decision · 7 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Subject matter

Article 1

Open ↗

This Decision lays down the priorities, actions and in order timetable for the implementation of the cross-border project Rail Baltica (Tallinn-Pärnu-Riga-Panevėžys-Kaunas-Warszawa, with a connection to Vilnius), as well as related governance and reporting provisions.

Priorities for the first phase

Article 2

Open ↗

1.   During the first phase, until 31 December 2030, Estonia, Latvia, Lithuania and Poland shall prioritise the construction of the sections Tallinn-Pärnu-Salaspils-Misa-Panevėžys-Kaunas-Warszawa and work to the completion of those sections. During that phase, the connection to the Rail Baltica line of Riga and Vilnius respectively shall be ensured through the existing rail network. 2.   As regards the first phase, Estonia, Latvia and Lithuania may build the Rail Baltica line as a single track from Tallinn to Kaunas, provided that a double-track embankment and enough passing loops for a smooth operation are built. 3.   In parallel to the actions of the first phase referred to in paragraphs 1 and 2, Lithuania may implement energy, control-command and signalling subsystem installations on the existing European railway track in the section between Poland and Kaunas. 4.   Estonia, Latvia, and Lithuania may start undertaking actions from the second phase prior to the completion of the first phase, where that does not delay directly or indirectly the completion of the activities of the first phase.

Priorities for the second phase

Article 3

Open ↗

The Rail Baltica project shall not be considered complete before Tallinn, Riga, Vilnius and Warszawa are connected via the railway in European standard nominal track gauge of 1 435 mm built in double track on the entire route.

Actions and timetable

Article 4

Open ↗

1.   Estonia, Latvia, Lithuania and Poland shall ensure the implementation of the following actions for completing the first phase of the Rail Baltica project in a timely manner: (a) as regards the section Tallinn-Pärnu: (i) land acquisition shall be completed by 31 December 2026; (ii) the construction of the railway substructure shall begin by 31 December 2025; (iii) the construction of the railway infrastructure sub-system shall be completed by 31 December 2028; (b) as regards the section Pärnu-border between Estonia and Latvia: (i) the design of the railway infrastructure sub-system shall be completed by 31 December 2026; (ii) land acquisition shall be completed by 31 December 2026; (iii) the construction of the railway substructure shall begin and make sufficient progress by 31 December 2026; (iv) the construction of the railway infrastructure sub-system shall be completed by 31 December 2028; (c) as regards the section border between Estonia and Latvia-Salaspils: (i) the design of the railway infrastructure sub-system shall be completed by 31 December 2026; (ii) land acquisition shall be completed by 30 June 2027; (iii) the construction of the railway substructure shall begin and make sufficient progress by 31 December 2026; (iv) the construction of the railway infrastructure sub-system shall be completed by 31 December 2029; (d) as regards the section Salaspils-border between Latvia and Lithuania: (i) the design of the railway infrastructure subsystem shall be completed by 31 December 2025; (ii) land acquisition shall be completed by 31 December 2026; (iii) the construction of the railway substructure shall begin and make sufficient progress by 31 December 2025; (iv) the construction of the railway infrastructure sub-system border shall be completed by mid-2029; (e) as regards the section border between Latvia and Lithuania-Panevėžys: (i) the design of the railway infrastructure sub-system shall be completed by 31 December 2027; (ii) the construction of the railway substructure shall begin and make sufficient progress by 31 December 2027; (iii) the construction of the railway infrastructure sub-system shall be underway by mid-2029; (f) as regards the section Panevėžys-Kaunas: (i) the construction of the railway infrastructure sub-system (railway superstructure) shall begin and make sufficient progress by 31 December 2025 (ii) the construction of the railway substructure shall be completed by 31 December 2028; (iii) the railway infrastructure sub-system (railway superstructure) shall be completed by mid-2029; (g) as regards the section Kaunas-Warszawa (with a connection to Vilnius): (i) land acquisition shall be completed by 31 December 2026, except for the section between Kaunas to Vilnius; (ii) land acquisition shall be completed by 31 December 2027 for the section from Kaunas to Vilnius; (iii) the design of the railway infrastructure sub-system shall be completed by mid-2029 (including the connection to Vilnius); (iv) the railway infrastructure shall be completed by 31 December 2028 from the Lithuanian-Polish border to Marijampole to ensure a connection to the existing railway line consisting of the European standard nominal track gauge of 1 435 mm; (v) the railway infrastructure from Marijampole to Kaunas shall be completed by 31 December 2029; (h) as regards the section Warszawa-border between Lithuania and Poland: (i) the rail infrastructure upgrade works on the section Warszawa-Ełk shall be completed by 31 December 2029; (ii) the section Ełk-border border between Lithuania and Poland shall be completed by 31 December 2030; (i) as regards all sections Tallinn-Pärnu-Salaspils-Misa-Panevėžys-Kaunas-Warszawa: (i) the design for the electrification sub-system shall be completed by 31 December 2027; (ii) the design for the control command and signalling sub-system shall be completed by mid 2028; (iii) installation works for the electrification sub-system shall begin in the first quarter of 2027; (iv) the installation works for the control command and signalling sub-system shall begin in the first quarter of 2028; (v) the railway infrastructure shall be completed as a mix of single- and double-track railway line on double-track embankment for mixed traffic, suitable for minimum 740-m-long freight trains, electrified, in European standard nominal track gauge by 31 December 2030; (vi) the European Rail Traffic Management System (ERTMS) shall be deployed to achieve full interoperability, in accordance with Directive (EU) 2016/797 of the European Parliament and of the Council  ( 3 ) , by 31 December 2030; (vii) dynamic testing shall begin as from 2030. 2.   The actions under the second phase of Rail Baltica project consist of the remaining actions that are necessary to ensure that the Rail Baltica line is fully compliant with Regulation (EU) 2024/1679.

Governance and reporting

Article 5

Open ↗

1.   The European Coordinator for the North Sea-Baltic European Transport Corridor, representatives of the Commission and nominated representatives of Poland and Finland shall be invited to participate as observers in the meetings of the Supervisory Board of RB Rail AS. RB Rail AS may also decide to invite the European Coordinator or the Commission to strategic meetings of the project partners. 2.   The Rail Baltica Task Force shall meet upon invitation of the European Coordinator for the North Sea – Baltic European Transport Corridor at least twice per year. It shall be consulted about strategic decisions for the project. The European Coordinator of the North Sea – Baltic corridor shall keep the European Coordinator of the Baltic Sea – Black Sea – Aegean Sea informed about significant developments related to the Rail Baltica project and relevant for the two corridors. 3.   After consulting Estonia, Latvia, Lithuania and Poland, RB Rail AS shall provide updated information to the European Coordinator for the North Sea – Baltic corridor in writing at least once per year about the progress in implementing the actions referred to in Article 2 and shall where relevant notify any delay encountered, specifying the reasons for the delay and indicating the corrective measures taken. 4.   If force majeure has an impact on the implementation programme and its financing, the project partners and the European Coordinator for the North Sea – Baltic corridor shall consult each other to define corrective measures.

Addressees

Article 7

Open ↗

This Decision is addressed to the Republic of Estonia, the Republic of Latvia, the Republic of Lithuania, the Republic of Poland and the Republic of Finland.

Other acts of the same type
Council Decision (EU) 2021/650 of 19 April 2021 on the signing, on behalf of the Union, of the Agreement in the form of an Exchange of Letters between the European Union and the United States of America pursuant to Article XXVIII of the General Agreement on Tariffs and Trade (GATT) 1994 relating to the modification of concessions on all the tariff rate quotas included in the EU Schedule CLXXV as a consequence of the United Kingdom’s withdrawal from the European UnionCouncil Decision (EU) 2021/651 of 19 April 2021 on the signing, on behalf of the Union, of the Agreement in the form of an Exchange of Letters between the European Union and the Argentine Republic pursuant to Article XXVIII of the General Agreement on Tariffs and Trade (GATT) 1994 relating to the modification of concessions on all the tariff-rate quotas included in the EU Schedule CLXXV as a consequence of the United Kingdom’s withdrawal from the European UnionCommission Decision (EU) 2021/660 of 19 April 2021 amending Decision (EU) 2020/491 on relief from import duties and VAT exemption on importation granted for goods needed to combat the effects of the COVID-19 outbreak during 2020 (notified under document C(2021) 2693)Council Implementing Decision (CFSP) 2021/636 of 16 April 2021 implementing Decision 2013/798/CFSP concerning restrictive measures against the Central African RepublicCouncil Decision (CFSP) 2021/613 of 15 April 2021 amending Decision (CFSP) 2016/1693 concerning restrictive measures against ISIL (Da’esh) and Al-Qaeda and persons, groups, undertakings and entities associated with themCommission Implementing Decision (EU) 2021/627 of 15 April 2021 laying down rules on keeping and accessing of the logs in the European Travel Information and Authorisation System (ETIAS) pursuant to Regulation (EU) 2018/1240 of the European Parliament and of the CouncilCommission Implementing Decision (EU) 2021/659 of 15 April 2021 concerning exemptions from the extended anti-dumping duty on certain bicycle parts originating in the People’s Republic of China pursuant to Regulation (EC) No 88/97 (notified under document C(2021) 2416)Commission Implementing Decision (EU) 2021/609 of 14 April 2021 amending Implementing Decision (EU) 2020/439 as regards harmonised standards on packaging for terminally sterilised medical devices and sterilisation of health care productsCommission Implementing Decision (EU) 2021/610 of 14 April 2021 amending Implementing Decision (EU) 2020/437 as regards harmonised standards on medical vehicles and their equipment, anaesthetic and respiratory equipment, biological evaluation of medical devices, packaging for terminally sterilised medical devices, sterilisation of health care products, clinical investigation of medical devices for human subjects, non-active surgical implants, medical devices utilising animal tissues and their derivatives, electroacoustics and medical electrical equipmentCommission Implementing Decision (EU) 2021/611 of 14 April 2021 amending Implementing Decision (EU) 2020/438 as regards harmonised standards on biological evaluation of medical devices, packaging for terminally sterilised medical devices, sterilisation of health care products and clinical investigation of medical devices for human subjectsCommission Decision (EU, Euratom) 2021/625 of 14 April 2021 on the establishment of the primary dealer network and the definition of eligibility criteria for lead and co-lead mandates for syndicated transactions for the purposes of the borrowing activities by the Commission on behalf of the Union and of the European Atomic Energy CommunityCommission Implementing Decision (EU) 2021/626 of 14 April 2021 establishing the InvestEU Portal and setting out its technical specifications

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

Contents

What to look at next