Commission Decision (EU) 2026/341 of 11 August 2025 granting the Republic of Poland a derogation from Article 22(4), point (b) of Regulation (EU) 2019/943 of the European Parliament and of the Council as regards the Polish capacity mechanism (notified under document C(2025) 5575)

Commission Decision (EU) 2026/341 of 11 August 2025 granting the Republic of Poland a derogation from Article 22(4), point (b) of Regulation (EU) 2019/943 of the European Parliament and of the Council as regards the Polish capacity mechanism (notified under document C(2025) 5575)

Decision (EU) 2026/341 · Decision · 4 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Article 1

Open ↗

A derogation is granted to the Republic of Poland from Article 22(4), point (b) of Regulation (EU) 2019/943 as regards the emission limit for the existing capacity mechanism approved by the Commission before 4 July 2019, subject to the following conditions: (a) Poland amends the NRAA to take into account the issues described in recital (145) above. In particular, the NRAA shall: (i) estimate the amount of electricity to be exported by Poland in the future on the basis of the result of a modelling exercise and using reasonable assumptions; and (ii) estimate the likelihood of retirement, mothballing and new-build of generation assets on the basis of estimated revenues and costs over a period of 10 years, rather than for a single year; and (iii) justify the assumptions on the maintenance patterns on the basis of actual maintenance schedules and explain how those patterns relate to the estimates in the NRAA in order to demonstrate that they constitute a national specificity of the Polish generator fleet; (b) the Polish NRA verifies whether the total amount of capacity to be procured under the updated NRAA is justified and, in particular, whether it reflects the needs of the system in situations of simultaneous scarcity.

Article 2

Open ↗

The Republic of Poland may allow generation capacity that started commercial production before 4 July 2019 and that emits more than 550 g of CO 2 of fossil fuel origin per kWh of electricity to be exceptionally committed or receive payments or commitments for future payments after 1 July 2025 in supplementary auctions under the existing capacity mechanism approved by the Commission before 4 July 2019.

Article 3

Open ↗

The derogation granted under Article 1 shall apply until 31 December 2028, provided that the conditions set out in Article 64(2c) of Regulation (EU) 2019/943 are complied with for the entire duration of the derogation.

Other acts of the same type
2013/483/EU: Council Decision of 30 September 2013 on the application of Regulation No 41 of the United Nations Economic Commission for Europe on uniform provisions concerning the approval of motor cycles with regard to noise Text with EEA relevance2013/493/EU: Commission Implementing Decision of 30 September 2013 determining the third and last set of regions for the start of operations of the Visa Information System (VIS) (notified under document C(2013) 5914)Council Decision 2013/477/CFSP of 27 September 2013 amending Decision 2010/573/CFSP concerning restrictive measures against the leadership of the Transnistrian region of the Republic of Moldova2013/478/EU: Commission Decision of 27 September 2013 amending Decision 1999/352/EC, ECSC, Euratom establishing the European Anti-fraud Office2013/481/EU: Council Decision of 26 September 2013 amending Decision 1999/70/EC concerning the external auditors of the national central banks, as regards the external auditors of the Banco de EspañaCouncil Implementing Decision 2013/469/CFSP of 23 September 2013 implementing Decision 2011/101/CFSP concerning restrictive measures against Zimbabwe2013/472/EU: Commission Implementing Decision of 23 September 2013 granting derogations for implementing Regulation (EC) No 452/2008 of the European Parliament and of the Council concerning the production and development of statistics on education and lifelong learning with regard to Belgium, Greece, Spain, France, Italy, Poland and Portugal (notified under document C(2013) 5897)2013/475/EU: Council Decision of 23 September 2013 on the position to be taken on behalf of the European Union within the Bilateral Oversight Board under the Agreement between the United States of America and the European Community on cooperation in the regulation of civil aviation safety, concerning Decision No 0004 amending Annex 1 to the Agreement2013/486/EU: Council Decision of 23 September 2013 on the signing, on behalf of the European Union, of the Voluntary Partnership Agreement between the European Union and the Republic of Indonesia on forest law enforcement, governance and trade in timber products to the European Union2013/488/EU: Council Decision of 23 September 2013 on the security rules for protecting EU classified information2014/20/EU: Council Decision of 23 September 2013 on the signing, on behalf of the Union, and the provisional application of the Cooperation Agreement between the European Union and its Member States, of the one part, and the Swiss Confederation, of the other, on the European Satellite Navigation Programmes2014/640/EU: Council Decision of 23 September 2013 on the position to be taken on behalf of the European Union within the Committee on Cultural Cooperation set up by the Protocol on cultural cooperation to the Free Trade Agreement between the European Union and its Member States, of the one part, and the Republic of Korea, of the other part, as regards the adoption of the rules of procedure of the Committee on Cultural Cooperation

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

Contents

What to look at next