My bookmarksSign up free

2009/287/EC: Commission Decision of 25 September 2007 on… Article 4

2009/287/EC: Commission Decision of 25 September 2007 on… Article 4

Article 4

1.   The compensation provided for in the Act constitutes state aid within the meaning of Article 87(1) of the EC Treaty to the electricity generators listed in Appendix 2 to that Act. 2.   The state aid referred to in Article 4(1) is compatible with the common market on the basis of the Stranded Costs Methodology. 3.   The maximum amount of compensation provided for in the Act shall be the amount following deduction of the total revenue generated by the assets under the PPAs and which is available to cover investment costs.

Read the full instrument →

Other provisions in 2009/287/EC: Commission Decision of 25 September 2007 on…

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 4 of 2009/287/EC: Commission Decision of 25 September 2007 on… (LawPlayer, data as of 2026-07-04)

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged.

What to look at next