Late submission of applications
Article 18
Except in cases of force majeure and exceptional circumstances, submission of an aid application after the time limit laid down in accordance with Article 16 shall lead to a 1 % reduction per working day in the amounts to which the aid applicant would have been entitled if the aid application had been lodged within the time limit. If the delay amounts to more than 25 calendar days, the application shall be considered inadmissible.
Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04
CitationArticle 18 of Commission Implementing Regulation (EU) No 181/2014 (LawPlayer, data as of 2026-07-04)