Commission Regulation (EU) 2015/1222 Article 20

Commission Regulation (EU) 2015/1222 Article 20

Introduction of flow-based capacity calculation methodology

Article 20

1.   For the day-ahead market time-frame and intraday market time-frame the approach used in the common capacity calculation methodologies shall be a flow-based approach, except where the requirement under paragraph 7 is met. 2.   No later than 10 months after the approval of the proposal for a capacity calculation region in accordance with Article 15(1), all TSOs in each capacity calculation region shall submit a proposal for a common coordinated capacity calculation methodology within the respective region. The proposal shall be subject to consultation in accordance with Article 12. The proposal for the capacity calculation methodology within regions pursuant to this paragraph in capacity calculation regions based on the ‘North-West Europe’ (‘NWE’) and ‘Central Eastern Europe’ (‘CEE’) as defined in points (b), and (d) of point 3.2 of Annex I to Regulation (EC) No 714/2009 as well as in regions referred to in paragraph 3 and 4, shall be complemented with a common framework for coordination and compatibility of flow-based methodologies across regions to be developed in accordance with paragraph 5. 3.   The TSOs from the capacity calculation region where Italy, as defined in point (c) of point 3.2 of Annex I to Regulation (EC) No 714/2009, is included, may extend the deadline without prejudice to the obligation in paragraph 1 for submitting the proposal for a common coordinated capacity calculation methodology using flow-based approach for the respective region pursuant to paragraph 2 up to six months after Switzerland joins the single day-ahead coupling. The proposal does not have to include bidding zone borders within Italy and between Italy and Greece. 4.   No later than six months after at least all South East Europe Energy Community Contracting Parties participate in the single day-ahead coupling, the TSOs from at least Croatia, Romania, Bulgaria and Greece shall jointly submit a proposal to introduce a common capacity calculation methodology using the flow-based approach for the day-ahead and intraday market time-frame. The proposal shall provide for an implementation date of the common capacity calculation methodology using the flow-based approach of no longer than two years after the participation of all SEE Energy Community Contracting Parties in the single day-ahead coupling. The TSOs from Member States which have borders with other regions are encouraged to join the initiatives to implement a common flow-based capacity calculation methodology with these regions. 5.   At the time when two or more adjacent capacity calculation regions in the same synchronous area implement a capacity calculation methodology using the flow-based approach for the day-ahead or the intraday market time-frame, they shall be considered as one region for this purpose and the TSOs from this region shall submit within six months a proposal for applying a common capacity calculation methodology using the flow-based approach for the day-ahead or intraday market time-frame. The proposal shall provide for an implementation date of the common cross regional capacity calculation methodology of no longer than 12 months after the implementation of the flow-based approach in these regions for the methodology for the day-ahead market time-frame, and 18 months for the methodology for the intraday time-frame. The timelines indicated in this paragraph may be adapted in accordance with paragraph 6. The methodology in the two capacity calculation regions which have initiated developing a common capacity calculation methodology may be implemented first before developing a common capacity calculation methodology with any further capacity calculation region. 6.   If the TSOs concerned are able to demonstrate that the application of common flow-based methodologies in accordance with paragraphs 4 and 5 would not yet be more efficient assuming the same level of operational security, they may jointly request the competent regulatory authorities to postpone the deadlines. 7.   TSOs may jointly request the competent regulatory authorities to apply the coordinated net transmission capacity approach in regions and bidding zone borders other than those referred to in paragraphs 2 to 4, if the TSOs concerned are able to demonstrate that the application of the capacity calculation methodology using the flow-based approach would not yet be more efficient compared to the coordinated net transmission capacity approach and assuming the same level of operational security in the concerned region. 8.   To enable market participants to adapt to any change in the capacity calculation approach, the TSOs concerned shall test the new approach alongside the existing approach and involve market participants for at least six months before implementing a proposal for changing their capacity calculation approach. 9.   The TSOs of each capacity calculation region applying the flow-based approach shall establish and make available a tool which enables market participants to evaluate the interaction between cross-zonal capacities and cross-zonal exchanges between bidding zones.

Read the full instrument → · Read this in context: Section 3 — Capacity calculation methodologies →

Other provisions in Section 3 — Capacity calculation methodologies

CitationArticle 20 of Commission Regulation (EU) 2015/1222 (LawPlayer, data as of 2026-11-02)

DATA NOTES

About the data

Sources

This page

Law
Article 20 of Commission Regulation (EU) 2015/1222 is headed “Introduction of flow-based capacity calculation methodology” and is a provision of EU legislation.
Text
The text of Article 20 of Commission Regulation (EU) 2015/1222 begins “1. For the day-ahead market time-frame and intraday market time-frame the approach used in the common capacity calculation methodologies…”.
Location
Article 20 of Commission Regulation (EU) 2015/1222 is placed under “TITLE II: REQUIREMENTS FOR TERMS, CONDITIONS AND METHODOLOGIES CONCERNING CAPACITY ALLOCATION AND CONGESTION MANAGEMENT › CHAPTER 1: Capacity calculation › Section 3: Capacity calculation methodologies”.
Previous
On LawPlayer, the provision listed immediately before Article 20 of Commission Regulation (EU) 2015/1222 is Article 19.
Next
On LawPlayer, the provision listed immediately after Article 20 of Commission Regulation (EU) 2015/1222 is Article 21.
Synced
LawPlayer last synced the text of Commission Regulation (EU) 2015/1222 from EUR-Lex (Publications Office of the European Union) on 2 November 2026.
Consolidated version
The text shown is taken from the EUR-Lex consolidated version of 15 March 2021. That date refers to the consolidated text as a whole and does not indicate that this article changed on that day; some amendments may not yet be included. Consolidated versions are documentation tools only and have no legal effect; the authentic texts are those published in the Official Journal of the European Union.
Article 20 of Commission Regulation (EU) 2015/1222 is reproduced on LawPlayer from EUR-Lex (Publications Office of the European Union).

Sources

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged. · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Data as of 2026-11-02Read the official text ↗

About

LawPlayer is a privately run legal research website for reading EU legislation article by article, built for lawyers, in-house counsel and students who need to check the legal text quickly.EU law entry

What to look at next