Cost sharing between NEMOs and TSOs in different Member States

Article 80

1.   All relevant NEMOs and TSOs shall provide a yearly report to the regulatory authorities in which the costs of establishing, amending and operating single day-ahead and intraday coupling are explained in detail. This report shall be published by the Agency taking due account of sensitive commercial information. Costs directly related to single day-ahead and intraday coupling shall be clearly and separately identified and auditable. The report shall also provide full details of contributions made to NEMO costs by TSOs in accordance with Article 76(2). 2.   The costs referred to in paragraph 1 shall be broken down into: (a) common costs resulting from coordinated activities of all NEMOs or TSOs participating in the single day-ahead and intraday coupling; (b) regional costs resulting from activities of NEMOs or TSOs cooperating in a certain region; (c) national costs resulting from activities of the NEMOs or TSOs in that Member State. 3.   Common costs referred to in paragraph 2(a) shall be shared among the TSOs and NEMOs in the Member States and third countries participating in the single day-ahead and intraday coupling. To calculate the amount to be paid by the TSOs and NEMOs in each Member State and, if applicable, third countries, one eighth of the common cost shall be divided equally between each Member State and third country, five eighths shall be divided between each Member State and third country proportionally to their consumption, and two eighths shall be divided equally between the participating NEMOs. To take into account changes in the common costs or changes in the participating TSOs and NEMOs, the calculation of common costs shall be regularly adapted. 4.   NEMOs and TSOs cooperating in a certain region shall jointly agree on a proposal for the sharing of regional costs in accordance with paragraph 2(b). The proposal shall then be individually approved by the competent national authorities of each of the Member States in the region. NEMOs and TSOs cooperating in a certain region may alternatively use the cost sharing arrangements set out in paragraph 3. 5.   The cost sharing principles shall apply to costs incurred from the entry into force of this Regulation. This is without prejudice to existing solutions used for the development of single day-ahead and intraday coupling and costs incurred prior to the entry into force of this Regulation shall be shared among the NEMOs and TSOs based on the existing agreements governing such solutions.

Read the full instrument → · Read this in context: CHAPTER 3 — Capacity allocation and congestion management cost recovery →

Other provisions in CHAPTER 3 — Capacity allocation and congestion management cost recovery

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 80 of Commission Regulation (EU) 2015/1222 (LawPlayer, data as of 2026-07-04)

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged.

What to look at next