Energisation operational notification for type D power-generating modules

Article 34

1.   An EON shall entitle the power-generating facility owner to energise its internal network and auxiliaries for the power-generating modules by using the grid connection that is specified for the connection point. 2.   An EON shall be issued by the relevant system operator, subject to completion of preparations including agreement on the protection and control settings relevant to the connection point between the relevant system operator and the power-generating facility owner.

Read the full instrument → · Read this in context: CHAPTER 1 — Connection of new power-generating modules →

Other provisions in CHAPTER 1 — Connection of new power-generating modules

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 34 of Commission Regulation (EU) 2016/631 (LawPlayer, data as of 2026-07-04)