Commission Regulation (EU) 2016/1447 Article 61

Commission Regulation (EU) 2016/1447 Article 61

EON for DC-connected power park modules

Article 61

1.   An EON shall entitle the owner of a DC-connected power park module to energise its internal network and auxiliaries by using the grid connection that is specified by the connection points. 2.   An EON shall be issued by the relevant system operator, subject to completion of preparation including agreement on the protection and control settings relevant to the connection points between the relevant system operator and the DC-connected power park module.

Read the full instrument → · Read this in context: CHAPTER 2 — Connection of new DC-connected power park modules →

Other provisions in CHAPTER 2 — Connection of new DC-connected power park modules

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 61 of Commission Regulation (EU) 2016/1447 (LawPlayer, data as of 2026-07-04)

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged.

What to look at next