Article 2

France shall take the steps necessary to ensure that for the entire duration of the aid referred to in Article 1 the beneficiary of the aid cannot provide energy from the plant to an operator which holds more than 40 % of the electricity generation capacity on the French market, whether under a tolling agreement or under a long-term contract of sale for the energy produced by the plant.

Read the full instrument →

Other provisions in Commission Decision (EU) 2017/1540

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 2 of Commission Decision (EU) 2017/1540 (LawPlayer, data as of 2026-07-04)

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged.