My bookmarksSign up free

Commission Regulation (EU) 2017/459 Article 28

Commission Regulation (EU) 2017/459 Article 28

Approval and publication

Article 28

1.   Following the consultation and finalisation of the design phase for an incremental capacity project in accordance with Article 27, the involved transmission system operators shall submit the project proposal for an incremental capacity project to the relevant national regulatory authorities for coordinated approvals. The project proposal shall also be published by the involved transmission system operators in one or more official languages of the Member State and to the extent possible in English and shall include at least the following information: (a) all offer levels, reflecting the range of expected demand for incremental capacity at the relevant interconnection points as a result of the processes provided for in paragraph 3 of Article 27 and Article 26; (b) the general rules and conditions that a network user must accept to participate and access capacity in the binding capacity allocation phase of the incremental capacity process, including any collaterals to be provided by network users and how possible delays in the provision of capacity or the event of a disruption to the project are dealt with contractually; (c) timelines of the incremental capacity project, including any changes since the consultation described in paragraph 3 of Article 27, and measures to prevent delays and minimise the impact of delays; (d) the parameters defined in Article 22(1); (e) whether an exceptionally extended time horizon for contracting capacity for an additional period of up to 5 years beyond the allocation of up to 15 years after the start of the operational use may be required, in accordance with Article 30; (f) where applicable, the proposed alternative allocation mechanism including its justification pursuant to Article 30(2) as well as the conditions approved by the transmission system operator for the binding phase pursuant to Article 30(3); (g) where a fixed price approach is followed for the incremental capacity project, the elements described in Article 24(b) of Regulation (EU) 2017/460. 2.   Within 6 months of receipt of the complete project proposal by the last of the relevant regulatory authorities, those national regulatory authorities shall publish coordinated decisions on the project proposal defined in paragraph 1 in one or more official languages of the Member State and to the extent possible in English. The decisions shall include justifications. National regulatory authorities shall inform each other of the receipt of the project proposal and its completeness in order to determine the start of the 6 months period. When preparing the national regulatory authority's decision, each national regulatory authority shall consider the views of the other national regulatory authorities involved. In any case national regulatory authorities shall take into account any detrimental effects on competition or the effective functioning of the internal gas market associated with the incremental capacity projects concerned. If a relevant national regulatory authority objects to the submitted project proposal, it shall inform the other involved national regulatory authorities as soon as possible. In such a situation, all the national regulatory authorities involved shall take all reasonable steps to work together and reach a common agreement. Where the relevant national regulatory authorities cannot reach an agreement on the proposed alternative allocation mechanism within the 6 months period referred to in the first subparagraph, the Agency shall decide on the alternative allocation mechanism to be implemented, following the process set out in Article 8(1) of Regulation (EC) No 713/2009. 3.   Upon the publication of the decisions of the relevant national regulatory authorities pursuant to paragraph 2 and no later than 2 months before the offer of incremental capacity in the annual yearly capacity auction, the transmission system operators shall publish jointly a notice in one or more official languages of the Member State and to the extent possible in English including the following minimum information (a) the information defined in paragraph 1 as approved by the national regulatory authorities; (b) a template of the contract(s) related to the capacity offered.

Read the full instrument → · Read this in context: CHAPTER V — INCREMENTAL CAPACITY PROCESS →

Other provisions in CHAPTER V — INCREMENTAL CAPACITY PROCESS

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 28 of Commission Regulation (EU) 2017/459 (LawPlayer, data as of 2026-07-04)

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged.

What to look at next