Commission Regulation (EU) 2017/1485 Article 50

Commission Regulation (EU) 2017/1485 Article 50

Real-time data exchange

Article 50

1.   Unless otherwise provided by the TSO, each power generating facility owner of a power generating module which is a SGU in accordance with Article 2(1)(a) and (e) connected to the distribution system shall provide the TSO and the DSO to which it has the connection point, in real-time, at least the following data: (a) status of the switching devices and circuit breakers at the connection point; and (b) active and reactive power flows, current, and voltage at the connection point. 2.   Each TSO shall define in coordination with the responsible DSOs which SGUs may be exempted from providing the real-time data listed in paragraph 1 directly to the TSO. In such cases, the responsible TSOs and DSOs shall agree on the aggregated real-time data of the SGUs concerned to be delivered to the TSO.

Read the full instrument → · Read this in context: CHAPTER 5 — Data exchange between TSOs, DSOs and distribution-connected power generating modules →

Other provisions in CHAPTER 5 — Data exchange between TSOs, DSOs and distribution-connected power generating modules

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 50 of Commission Regulation (EU) 2017/1485 (LawPlayer, data as of 2026-07-04)

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged.

What to look at next