Data exchange between TSOs and transmission-connected demand facilities
Article 52
1. Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following structural data to the TSO: (a) electrical data of the transformers connected to the transmission system; (b) characteristics of the load of the demand facility; and (c) characteristics of the reactive power control. 2. Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO: (a) scheduled active and forecasted reactive power consumption on a day-ahead and intraday basis, including any changes of those schedules or forecast; (b) any forecasted restriction in the reactive power control capability; (c) in case of participation in demand response, a schedule of its structural minimum and maximum power range to be curtailed; and (d) by exception to point (a), in regions with a central dispatch system, the data requested by the TSO for the preparation of its active power output schedule. 3. Unless otherwise provided by the TSO, each transmission-connected demand facility owner shall provide the following data to the TSO in real-time: (a) active and reactive power at the connection point; and (b) the minimum and maximum power range to be curtailed. 4. Each transmission-connected demand facility owner shall describe to its TSO its behaviour at the voltage ranges referred to in Article 27.