Commission Regulation (EU) 2017/1485 Article 73

Commission Regulation (EU) 2017/1485 Article 73

Year-ahead up to and including week-ahead operational security analysis

Article 73

1.   Each TSO shall perform year-ahead and, where applicable, week-ahead operational security analyses in order to detect at least the following constraints: (a) power flows and voltages exceeding operational security limits; (b) violations of stability limits of the transmission system identified in accordance with Article 38(2) and (6); and (c) violations of short-circuit thresholds of the transmission system. 2.   When a TSO detects a possible constraint, it shall design remedial actions in accordance with Articles 20 to 23. If remedial actions without costs are not available and the constraint is linked to the planned unavailability of some relevant assets, the constraint shall constitute an outage planning incompatibility and the TSO shall initiate outage coordination in accordance with Article 95 or 100 depending of the time of the year when this action is initiated.

Read the full instrument → · Read this in context: TITLE 2 — OPERATIONAL SECURITY ANALYSIS →

Other provisions in TITLE 2 — OPERATIONAL SECURITY ANALYSIS

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 73 of Commission Regulation (EU) 2017/1485 (LawPlayer, data as of 2026-07-04)

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged.

What to look at next