Article 54

1.   Transmission system operators shall not own, develop, manage or operate energy storage facilities. 2.   By way of derogation from paragraph 1, Member States may allow transmission system operators to own, develop, manage or operate energy storage facilities, where they are fully integrated network components and the regulatory authority has granted its approval, or where all of the following conditions are fulfilled: (a)  other parties, following an open, transparent and non-discriminatory tendering procedure that is subject to review and approval by the regulatory authority, have not been awarded a right to own, develop, manage or operate such facilities, or could not deliver those services at a reasonable cost and in a timely manner; (b)  such facilities or non-frequency ancillary services are necessary for the transmission system operators to fulfil their obligations under this Directive for the efficient, reliable and secure operation of the transmission system and they are not used to buy or sell electricity in the electricity markets; and (c)  the regulatory authority has assessed the necessity of such a derogation, has carried out an ex ante review of the applicability of a tendering procedure, including the conditions of the tendering procedure, and has granted its approval. The regulatory authority may draw up guidelines or procurement clauses to help transmission system operators ensure a fair tendering procedure. 3.   The decision to grant a derogation shall be notified to the Commission and ACER together with relevant information about the request and the reasons for granting the derogation. 4.   The regulatory authorities shall perform, at regular intervals or at least every five years, a public consultation on the existing energy storage facilities in order to assess the potential availability and interest of other parties in investing in such facilities. Where the public consultation, as assessed by the regulatory authority, indicates that other parties are able to own, develop, operate or manage such facilities in a cost-effective manner, the regulatory authority shall ensure that transmission system operators' activities in this regard are phased-out within 18 months. As part of the conditions of that procedure, regulatory authorities may allow the transmission system operators to receive reasonable compensation, in particular to recover the residual value of their investment in the energy storage facilities. 5.   Paragraph 4 shall not apply to fully integrated network components or for the usual depreciation period of new battery storage facilities with a final investment decision until 2024, provided that such battery storage facilities are: (a)  connected to the grid at the latest two years thereafter; (b)  integrated into the transmission system; (c)  used only for the reactive instantaneous restoration of network security in the case of network contingencies where such restoration measure starts immediately and ends when regular re-dispatch can solve the issue; and (d)  not used to buy or sell electricity in the electricity markets, including balancing.

Read the full instrument → · Read this in context: Section 4 — Designation and certification of transmission system operators →

Other provisions in Section 4 — Designation and certification of transmission system operators

CitationArticle 54 of Directive (EU) 2019/944 (LawPlayer, data as of 2026-11-02)

DATA NOTES

About the data

Sources

This page

Law
Article 54 of Directive (EU) 2019/944 is headed “Ownership of energy storage facilities by transmission system operators” and is a provision of EU legislation.
Text
The text of Article 54 of Directive (EU) 2019/944 begins “1. Transmission system operators shall not own, develop, manage or operate energy storage facilities. 2. By way of derogation from…”.
Location
Article 54 of Directive (EU) 2019/944 is placed under “CHAPTER VI: UNBUNDLING OF TRANSMISSION SYSTEM OPERATORS › Section 4: Designation and certification of transmission system operators”.
Previous
On LawPlayer, the provision listed immediately before Article 54 of Directive (EU) 2019/944 is Article 53.
Next
On LawPlayer, the provision listed immediately after Article 54 of Directive (EU) 2019/944 is Article 55.
Synced
LawPlayer last synced the text of Directive (EU) 2019/944 from EUR-Lex (Publications Office of the European Union) on 2 November 2026.
Consolidated version
The text shown is taken from the EUR-Lex consolidated version of 12 October 2025. That date refers to the consolidated text as a whole and does not indicate that this article changed on that day; some amendments may not yet be included. Consolidated versions are documentation tools only and have no legal effect; the authentic texts are those published in the Official Journal of the European Union.
Article 54 of Directive (EU) 2019/944 is reproduced on LawPlayer from EUR-Lex (Publications Office of the European Union).

Sources

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged. · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Data as of 2026-11-02Read the official text ↗

About

On LawPlayer, every article of an EU act has its own page, linked to the full text and, where the act has them, to its Titles, Chapters and Sections; the same site also covers Taiwan's statutes, court judgments and company registration records, and the legislation of 13 other jurisdictions.EU law entry

What to look at next