Renegotiation of Power Purchase and Energy Conversion Agreements between Government Entities.
Section 69
SEC. 69. Renegotiation of Power Purchase and Energy Conversion Agreements between Government Entities. — Within three (3) months from the effectivity of this Act, all power purchase and energy conversion agreements between the PNOC-Energy Development Corporation (PNOC-EDC) and NPC, including but not limited to the Palinpinon, Tongonan and Mt. Apo Geothermal complexes, shall be reviewed by the ERC and the terms thereof amended to remove any hidden costs or extraordinary mark-ups in the cost of power or steam above their true costs. All amended contracts shall be submitted to the Joint Congressional Power Commission for approval. The ERC shall ensure that all savings realized from the reduction of said mark-ups shall be passed on to all end-users.