s 8 Due date for payment

8.—(1) Where a construction contract provides for the date on which a progress payment becomes due and payable, the progress payment becomes due and payable on the earlier of the following dates:(a) the date as specified in or determined in accordance with the terms of the contract; (b) the date immediately upon the expiry of 35 days after —(i) if the claimant is a taxable person under the Goods and Services Tax Act 1993 who has submitted to the respondent a tax invoice for the progress payment — the date the tax invoice is submitted to the respondent; or (ii) in any other case — the date on which or the period within which the payment response is required to be provided under section 11(1) (whether or not a payment response is provided). (2) Where a construction contract does not provide for the date on which a progress payment becomes due and payable, the progress payment becomes due and payable immediately upon the expiry of 14 days after —(a) if the claimant is a taxable person under the Goods and Services Tax Act 1993 who has submitted to the respondent a tax invoice for the progress payment — the date the tax invoice is submitted to the respondent; or (b) in any other case — the date on which or the period within which the payment response is required to be provided under section 11(1) (whether or not a payment response is provided). (3) Where a supply contract provides for the date on which a progress payment becomes due and payable, the progress payment becomes due and payable on the earlier of the following dates:(a) the date as specified in or determined in accordance with the terms of the contract; (b) the date immediately upon the expiry of 60 days after the relevant payment claim is served under section 10. (4) Where a supply contract does not provide for the date on which a progress payment becomes due and payable, the progress payment becomes due and payable immediately upon the expiry of 30 days after the relevant payment claim is served under section 10. (5) The interest payable on the unpaid amount of a progress payment that has become due and payable is at the higher of the following rates:(a) the rate specified in or determined in accordance with the terms of the contract; (b) the rate prescribed in respect of judgment debts under the Supreme Court of Judicature Act 1969.[47/2018] (6) For the purpose of subsections (1) and (2) and subject to the Goods and Services Tax Act 1993, the claimant may submit the tax invoice mentioned in subsection (1)(b)(i) or (2)(a) at any time after the payment response mentioned in subsection (1)(b)(ii) or (2)(b) (as the case may be) is provided, despite anything to the contrary in the contract.

Read this section in the full act → · Open PART 2 →

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. Read the official text ↗

Source: Singapore Statutes Online (Attorney-General's Chambers), © Government of Singapore.

The Singapore legislation on this platform is subject to copyright of the Singapore Government and is used/reproduced for the purposes of this platform with the permission of the Attorney-General's Chambers. Users of this platform may check Singapore Statutes Online for the latest version of the Singapore legislation.

What to look at next