art 5 Power to deviate
In constructing or maintaining the scheduled work, the undertaker may— (a) deviate laterally from the line or situation shown on the deposited plan within the limits of deviation for that work shown on that plan, and (b) deviate vertically from the levels shown on the deposited section to any extent not exceeding 2 metres upwards or downwards as may be necessary or convenient.