Article 36

Open ↗

For research, pilot and demonstration projects referred to in Articles 14, 15 and 16 periodical reports shall be drawn up by the beneficiary or beneficiaries. Such reports shall be used to describe the technical progress made. On completion of the work, a final report comprising an assessment of exploitation and impact shall be provided by the beneficiary or beneficiaries. That report shall be published by the Commission in full or in summarised form depending on the strategic relevance of the project and following consultation, if necessary, of the relevant Advisory Group. The Commission may require the beneficiary or beneficiaries to provide final reports on the accompanying measures referred to in Article 17 as well as on the support and preparatory actions referred to in Article 18 and may decide to have them published.

Annual review

Article 37

Open ↗

The Commission shall conduct an annual review of activities under the Research Programme and the progress of the RTD work. The report containing the review shall be forwarded to the Coal and Steel Committee. The Commission may appoint independent experts and highly qualified experts to assist with this annual review.

Monitoring and assessment of the Research Programme

Article 38

Open ↗

1.   The Commission shall carry out a monitoring exercise of the Research Programme, including an assessment of the expected benefits. A report on that exercise shall be issued by the end of 2013, and thereafter every seven years. These reports shall be made public on the Community Research and Development Information Service (CORDIS) or corresponding website. 2.   The Commission shall assess the Research Programme on completion of the projects financed during every period of seven years. The benefits of the RTD to society and to the relevant sectors shall also be assessed. The assessment report shall be published. 3.   In carrying out the monitoring and assessment referred to in paragraphs 1 and 2, the Commission shall be assisted by panels of highly qualified experts appointed by the Commission.

Appointment of independent and highly qualified experts

Article 39

Open ↗

For the appointment of independent and highly qualified experts referred to in Article 18, Article 28(2) and Article 38, the provisions set out in Articles 14 and 17 of the Regulation (EC) No 1906/2006  ( 8 ) , shall apply by analogy.

Back to 2008/376/EC: Council Decision of 29 April 2008 on the… — full text

Articles on this page are reproduced verbatim from official open data. See the attribution line.

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

What to look at next