2011/88/EU: Commission Decision of 9 June 2010 on state aid C 1/09 (ex NN 69/08) granted by Hungary to MOL Nyrt. (notified under document C(2010) 3553) Text with EEA relevance

2011/88/EU: Commission Decision of 9 June 2010 on state aid C 1/09 (ex NN 69/08) granted by Hungary to MOL Nyrt. (notified under document C(2010) 3553) Text with EEA relevance

Decision · 5 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Article 1

Open ↗

1.   The combination of the fixed mining fee defined in the extension agreement concluded between the Hungarian State and MOL Nyrt. on 22 December 2005 and the subsequent amendments to Act XLVIII of 1993 on Mining constitutes state aid to MOL Nyrt. within the meaning of Article 107(1) TFEU. 2.   The state aid referred to in Article 1(1), unlawfully granted by Hungary to MOL Nyrt., in breach of Article 108(3) TFEU, is incompatible with the internal market. 3.   Hungary shall refrain from granting the state aid referred to in paragraph 1 within 2 months following the date of notification of the present Decision.

Article 2

Open ↗

1.   Hungary shall recover the aid referred to in Article 1 from the beneficiary. 2.   The state aid totals HUF 28 444,7 million for 2008 and HUF 1 942,1 million for 2009. As regards 2010, the amount of aid has to be calculated by Hungary until the measure is abolished. 3.   The sums to be recovered shall bear interest from the date on which they were put at the disposal of the beneficiary until the date on which they are actually recovered. 4.   The interest shall be calculated on a compound basis in accordance with Chapter V of Regulation (EC) No 794/2004 as amended by Regulation (EC) No 271/2008.

Article 3

Open ↗

1.   Recovery of the aid referred to in Article 1 shall be immediate and effective. 2.   Hungary shall ensure that this Decision is implemented within 4 months of its notification.

Article 4

Open ↗

1.   Within 2 months following notification of this Decision, Hungary shall submit the following information to the Commission: (a) the total amount (principal and recovery interest) to be recovered from the beneficiary, including the calculation of the aid amount for 2010; (b) a detailed description of the measures already taken and planned to comply with this Decision; (c) documents demonstrating that the beneficiary has been ordered to repay the aid. 2.   Hungary shall keep the Commission informed of the progress of the national measures taken to implement this Decision until recovery of the aid referred to in Article 1 has been completed. It shall immediately submit, on simple request by the Commission, information on the measures already taken and planned to comply with this Decision. It shall also provide detailed information concerning the amounts of aid and recovery interest already recovered from the beneficiary.

Other acts of the same type
Commission Decision (EU) 2018/479 of 20 March 2018 on the long-term national aid scheme for agriculture in the northern regions of Sweden (notified under document C(2018) 1622)Council Decision (EU) 2018/487 of 20 March 2018 amending Decision 1999/70/EC concerning the external auditors of the national central banks, as regards the external auditors of the Oesterreichische NationalbankCommission Implementing Decision (EU) 2018/499 of 20 March 2018 setting up the European Infrastructure of Open Screening Platforms for Chemical Biology European Research Infrastructure Consortium (EU-OPENSCREEN ERIC) (notified under document C(2018) 1482) (Text with EEA relevance. )Council Decision (EU) 2018/539 of 20 March 2018 on the conclusion of the Bilateral Agreement between the European Union and the United States of America on prudential measures regarding insurance and reinsuranceCouncil Implementing Decision (CFSP) 2018/421 of 19 March 2018 implementing Decision 2013/255/CFSP concerning restrictive measures against SyriaCouncil Decision (CFSP) 2018/459 of 19 March 2018 amending Decision 2011/173/CFSP concerning restrictive measures in view of the situation in Bosnia and HerzegovinaCouncil Implementing Decision (EU) 2018/485 of 19 March 2018 authorising Denmark to apply a special measure derogating from Article 75 of Directive 2006/112/EC on the common system of value added taxCouncil Decision (EU) 2018/639 of 19 March 2018 on the signing, on behalf of the Union, and provisional application of the Agreement for scientific and technological cooperation between the European Union and the Kingdom of Morocco setting out the terms and conditions for the participation of the Kingdom of Morocco in the Partnership for Research and Innovation in the Mediterranean Area (PRIMA)Council Implementing Decision (CFSP) 2018/417 of 16 March 2018 implementing Decision 2010/231/CFSP concerning restrictive measures against SomaliaDecision (EU) 2018/546 of the European Central Bank of 15 March 2018 on delegation of the power to adopt own funds decisions (ECB/2018/10)Commission Implementing Decision (EU) 2018/477 of 15 March 2018 concerning exemptions from the extended anti-dumping duty on certain bicycle parts originating in the People's Republic of China pursuant to Commission Regulation (EC) No 88/97 (notified under document C(2018) 1506)Commission Decision of 14 March 2018 on the Facility for Refugees in Turkey amending Commission Decision C(2015) 9500 as regards the contribution to the Facility for Refugees in Turkey

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

Contents

What to look at next