Commission Decision (EU) 2019/56 of 28 May 2018 on aid scheme SA.34045 (2013/c) (ex 2012/NN) implemented by Germany for baseload consumers under Paragraph 19 StromNEV (notified under document C(2018) 3166) (Text with EEA relevance.)

Commission Decision (EU) 2019/56 of 28 May 2018 on aid scheme SA.34045 (2013/c) (ex 2012/NN) implemented by Germany for baseload consumers under Paragraph 19 StromNEV (notified under document C(2018) 3166) (Text with EEA relevance.)

Decision (EU) 2019/56 · Decision · 6 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Article 1

Open ↗

1.   The full exemption of baseload consumers in Germany from paying network charges, which Germany has unlawfully put into effect in 2012 and 2013, constitutes State aid within the meaning of Article 107(1) of the Treaty insofar as those consumers were exempted from paying network charges corresponding to the network costs caused by them or, where those network costs amounted to less than the minimum network charges of 20 % of the published network charges, from paying those minimum network charges. 2.   The State aid referred to in paragraph 1 was put into effect by Germany in breach of Article 108(3) of the Treaty and is incompatible with the internal market.

Article 2

Open ↗

Individual aid granted under the scheme referred to in Article 1 does not constitute State aid if, at the time it is granted, it fulfils the conditions laid down by the regulation adopted pursuant to Article 2 of Council Regulation (EC) No 994/98  ( 116 ) which is applicable at the time the aid is granted.

Article 3

Open ↗

(1)   Germany shall recover the incompatible aid granted under the scheme referred to in Article 1 from the beneficiaries. (2)   The sums to be recovered shall bear interest from the date on which they were put at the disposal of the beneficiaries until their actual recovery. (3)   The interest shall be calculated on a compound basis in accordance with Chapter V of Commission Regulation (EC) No 794/2004  ( 117 ) . (4)   Germany shall cancel all outstanding payments of aid under the scheme referred to in Article 1 with effect from the date of adoption of this Decision.

Article 4

Open ↗

(1)   Recovery of the aid granted under the scheme referred to in Article 1 shall be immediate and effective. (2)   Germany shall ensure that this Decision is implemented within four months following the date of notification of this Decision.

Article 5

Open ↗

(1)   Within two months following notification of this Decision, Germany shall submit the following information: (a) the list of beneficiaries that have received aid under the scheme referred to in Article 1 and the total amount of aid received by each of them under the scheme; (b) the total amount (principal and recovery interests) to be recovered from each beneficiary; (c) a detailed description of the measures already taken and those planned to comply with this Decision; (d) documents demonstrating that the beneficiaries have been ordered to repay the aid referred to in Article 1. (2)   Germany shall keep the Commission informed of the progress of the national measures taken to implement this Decision until recovery of the aid granted under the scheme referred to in Article 1 has been completed. Upon a simple request by the Commission, Germany shall immediately submit information on the measures already taken and those planned to comply with this Decision. It shall also provide detailed information concerning the amounts of aid and interest already recovered from the beneficiaries.

Article 6

Open ↗

This Decision is addressed to the Federal Republic of Germany.

Other acts of the same type
Council Decision (CFSP) 2025/2637 of 22 December 2025 amending Decision (CFSP) 2024/1484 concerning restrictive measures in view of the situation in RussiaCouncil Decision (CFSP) 2025/2648 of 22 December 2025 amending Decision 2014/512/CFSP concerning restrictive measures in view of Russia’s actions destabilising the situation in UkraineCommission Implementing Decision (EU) 2026/67 of 22 December 2025 amending Implementing Decision (EU) 2022/696 granting a derogation requested by Ireland pursuant to Council Directive 91/676/EEC concerning the protection of waters against pollution caused by nitrates from agricultural sources (notified under document C(2025) 9263)Commission Implementing Decision (EU) 2025/2571 of 19 December 2025 amending Commission Implementing Decision (EU) 2021/1773 pursuant to Directive (EU) 2016/680 of the European Parliament and of the Council on the adequate protection of personal data by the United Kingdom (notified under document C(2025) 8782)Commission Implementing Decision (EU) 2025/2574 of 19 December 2025 amending Commission Implementing Decision (EU) 2021/1772 pursuant to Regulation (EU) 2016/679 of the European Parliament and of the Council on the adequate protection of personal data by the United Kingdom (notified under document C(2025) 8771)Council Implementing Decision (EU) 2025/2642 of 22 December 2025 on the establishment of the Annual Solidarity Pool for 2026Decision (EU) 2026/77 of the European Central Bank of 19 December 2025 amending Decision (EU) 2019/166 on the Market Infrastructure Board (ECB/2019/3) (ECB/2025/43)Decision (EU) 2026/86 of the European Central Bank of 19 December 2025 amending Decision (EU) 2016/456 (ECB/2016/3) as regards investigations in relation to the prevention of fraud, corruption and any other illegal activities affecting the financial interests of the Union and amending Decision (EU) 2020/1575 (ECB/2020/54) as regards the follow-up to suspected breaches of professional duties where the person concerned is a high-level ECB official (ECB/2025/45)Commission Decision (EU) 2025/2570 of 18 December 2025 establishing the mission charter for the Internal Audit Service of the CommissionCommission Implementing Decision (EU) 2025/2591 of 18 December 2025 granting a derogation to certain Member States pursuant to Regulation (EU) No 952/2013 of the European Parliament and of the Council to use means other than electronic data-processing techniques for the exchange and storage of information instead of component 2, phase 6, of the New Computerised Transit System (notified under document C(2025) 8776)Commission Decision (EU) 2025/2616 of 18 December 2025 on renewing the mandate of the European Coordinator for the Baltic synchronisation project designated by the Decision (EU) 2024/3223Council Decision (CFSP) 2025/2617 of 18 December 2025 amending Decision 2014/512/CFSP concerning restrictive measures in view of Russia’s actions destabilising the situation in Ukraine

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

Contents

What to look at next