2011/269/EU: Commission Decision of 27 October 2010 on State aid C 14/09 (ex NN 17/09) granted by Hungary to Péti Nitrogénművek Zrt. (notified under document C(2010) 7274) Text with EEA relevance

2011/269/EU: Commission Decision of 27 October 2010 on State aid C 14/09 (ex NN 17/09) granted by Hungary to Péti Nitrogénművek Zrt. (notified under document C(2010) 7274) Text with EEA relevance

Decision · 6 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Article 1

The EUR 52 million investment loan and the HUF 10 billion current facilities loan granted by Hungary to Péti Nitrogénművek Zrt. constitute State aid within the meaning of Article 107(1) TFEU.

Article 2

1.   The State aid unlawfully granted by Hungary to Péti Nitrogénművek Zrt. in breach of Article 108(3) TFEU is partly compatible, partly incompatible with the internal market. 2.   The unlawful State aid consisting in the difference between the subsidised interest rate under the Temporary Framework and the relevant reference rate is compatible with the internal market. 3.   The unlawful State aid consisting in the difference between the effective remuneration of the measures and the subsidised interest rate under the Temporary Framework is incompatible with the internal market. 4.   Hungary shall refrain from granting the State aid referred to in paragraph 3 with effect from the date of notification of this decision.

Article 3

1.   Hungary shall recover the aid referred to in Article 2(3) from the beneficiary. 2.   The sums to be recovered shall bear interest from the date on which they were put at the disposal of the beneficiary until the date on which they are actually recovered. 3.   The interest shall be calculated on a compound basis in accordance with Chapter V of Regulation (EC) No 794/2004.

Article 4

1.   Recovery of the aid referred to in Article 2(3) shall be immediate and effective. 2.   Hungary shall ensure that this Decision is implemented within 4 months of its notification.

Article 5

1.   Within 2 months following notification of this Decision, Hungary shall submit the following information to the Commission: (a) the total amount (principal and recovery interest) to be recovered from the beneficiary; (b) a detailed description of the measures already taken and planned to comply with this Decision; (c) supporting documents demonstrating that the beneficiary has been ordered to repay the aid. 2.   Hungary shall keep the Commission informed of the progress of the national measures taken to implement this Decision until recovery of the aid referred to in Article 2(3) with interest has been completed. It shall immediately submit, on simple request by the Commission, information on the measures already taken and planned to comply with this Decision. It shall also provide detailed information concerning the amounts of aid and recovery interest already recovered from the beneficiary.

Article 6

This Decision is addressed to the Republic of Hungary.

Other acts of the same type
Commission Implementing Decision (EU) 2022/531 of 31 March 2022 authorising the placing on the market of products containing, consisting of or produced from genetically modified soybean GMB151 (BCS-GM151-6) pursuant to Regulation (EC) No 1829/2003 of the European Parliament and of the Council (notified under document C(2022)1893) (Only the German text is authentic) (Text with EEA relevance)Commission Implementing Decision (EU) 2022/560 of 31 March 2022 renewing the authorisation for the placing on the market of products containing, consisting of or produced from genetically modified cotton GHB614 (BCS-GHØØ2-5) pursuant to Regulation (EC) No 1829/2003 of the European Parliament and of the Council (notified under document C(2022) 1891) (Only the German text is authentic) (Text with EEA relevance)Commission Implementing Decision (EU) 2022/677 of 31 March 2022 laying down rules for the application of Regulation (EC) No 1223/2009 of the European Parliament and of the Council as regards the glossary of common ingredient names for use in the labelling of cosmetic products (Text with EEA relevance)Commission Decision (EU) 2022/506 of 29 March 2022 updating Annex A to the Monetary Agreement between the European Union and the Principality of MonacoCommission Decision (EU) 2022/507 of 29 March 2022 confirming the participation of Ireland in Regulation (EU) 2021/1147 of the European Parliament and of the Council establishing the Asylum, Migration and Integration FundDecision (EU, Euratom) 2022/521 of the European Parliament, the Council and the Commission of 28 March 2022 appointing the members of the Supervisory Committee of the European Anti-Fraud Office (OLAF)Commission Decision (EU) 2022/494 of 25 March 2022 confirming the participation of Ireland in Regulation (EU) 2021/693 of the European Parliament and of the Council establishing the Justice ProgrammeCommission Implementing Decision (EU) 2022/500 of 25 March 2022 establishing the military aggression of Russia against Ukraine as the occurrence of an exceptional event causing a significant disruption of marketsDecision (EU) 2022/548 of the European Parliament and of the Council of 24 March 2022 on the mobilisation of the European Globalisation Adjustment Fund for Displaced Workers following an application from France – EGF/2021/007 FR/SelectaCouncil Decision (CFSP) 2022/471 of 23 March 2022 amending Decision (CFSP) 2022/338 on an assistance measure under the European Peace Facility for the supply to the Ukrainian Armed Forces of military equipment, and platforms, designed to deliver lethal forceCouncil Decision (CFSP) 2022/472 of 23 March 2022 amending Decision (CFSP) 2022/339 on an assistance measure under the European Peace Facility to support the Ukrainian Armed ForcesCommission Implementing Decision (EU) 2022/484 of 23 March 2022 providing for derogations from Regulation (EU) No 1307/2013 of the European Parliament and of the Council and from Commission Delegated Regulation (EU) No 639/2014 as regards the implementation of certain conditions relating to the greening payment for claim year 2022 (notified under document C(2022) 1875)

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

What to look at next