2011/746/: Commission Decision of 23 February 2011 on State aid granted by Italy to Portovesme Srl, ILA SpA, Eurallumina SpA and Syndial SpA (State aid measures C 38/B/04 (ex NN 58/04) and C 13/06 (ex N 587/05) (notified under document C(2011) 956) Text with EEA relevance

2011/746/: Commission Decision of 23 February 2011 on State aid granted by Italy to Portovesme Srl, ILA SpA, Eurallumina SpA and Syndial SpA (State aid measures C 38/B/04 (ex NN 58/04) and C 13/06 (ex N 587/05) (notified under document C(2011) 956) Text with EEA relevance

Decision · 6 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Article 1

Open ↗

1.   The State aid which Italy plans to grant to Portovesme Srl, Eurallumina SpA, ILA SpA and Syndial SpA under Article 11(12) of Decree-Law No 35 of 14 March 2005, converted into statute by Law No 80/2005 of 14 May 2005, is incompatible with the internal market. 2.   The aid may accordingly not be granted.

Article 2

Open ↗

The State aid unlawfully granted by Italy in breach of Article 108(3) TFEU, on the basis of Article 1 of the Prime Ministerial Decree of 6 February 2004, amounting to EUR 12 845 892,82 for Portovesme Srl, EUR 5 208 152,05 for Eurallumina SpA, and EUR 291 120,27 for ILA SpA, is incompatible with the internal market.

Article 3

Open ↗

1.   Italy shall recover the aid referred to in Article 2 from the beneficiaries. 2.   The sums to be recovered shall bear interest from the date on which they were put at the disposal of the beneficiary until their actual recovery. 3.   The interest shall be calculated on a compound basis in accordance with Chapter V of Regulation (EC) No 794/2004. 4.   Italy shall cancel all future payments of the aid referred to in Article 2 with effect from the date of adoption of this Decision.

Article 4

Open ↗

1.   Recovery of the aid referred to in Article 2 shall be immediate and effective. 2.   Italy shall ensure that this Decision is implemented within 4 months following the date of notification of this Decision.

Article 5

Open ↗

1.   Within two months following notification of this Decision, Italy shall submit the following information to the Commission: (a) the total amount (principal and recovery interest) to be recovered from the beneficiary; (b) a detailed description of the measures already taken and planned to comply with this Decision; (c) documents demonstrating that the beneficiary has been ordered to repay the aid. 2.   Italy shall keep the Commission informed of the progress of the national measures taken to implement this Decision until recovery of the aid referred to in Article 2 has been completed. At the Commission’s request, it shall immediately submit information on the measures already taken and planned to comply with this Decision. It shall also provide detailed information concerning the amounts of aid and recovery interest already recovered from the beneficiary.

Other acts of the same type
Commission Implementing Decision (EU) 2016/2229 of 9 December 2016 terminating the partial interim review pursuant to Article 11(3) of Regulation (EU) 2016/1036 of the European Parliament and of the Council of the anti-dumping measures applicable to imports of sodium gluconate originating in the People's Republic of China, limited to one Chinese exporting producer, Shandong KaisonCommission Implementing Decision (EU) 2016/2241 of 9 December 2016 providing for the temporary marketing of seed of certain varieties of the species Beta vulgaris L., not satisfying the requirements of Council Directive 2002/54/EC (notified under document C(2016) 8105) (Text with EEA relevance )Commission Implementing Decision (EU) 2016/2242 of 9 December 2016 providing for the temporary marketing of seed of Hordeum vulgare L. variety Scrabble, not satisfying the requirements of Council Directive 66/402/EEC (notified under document C(2016) 8106) (Text with EEA relevance )Commission Implementing Decision (EU) 2016/2328 of 9 December 2016 adopting a tenth update of the list of sites of Community importance for the Mediterranean biogeographical region (notified under document C(2016) 8142)Commission Implementing Decision (EU) 2016/2329 of 9 December 2016 adopting a fourth update of the list of sites of Community importance for the Black Sea biogeographical region (notified under document C(2016) 8182)Commission Implementing Decision (EU) 2016/2331 of 9 December 2016 adopting a tenth update of the list of sites of Community importance for the Boreal biogeographical region (notified under document C(2016) 8184)Commission Implementing Decision (EU) 2016/2334 of 9 December 2016 adopting a tenth update of the list of sites of Community importance for the Continental biogeographical region (notified under document C(2016) 8191)Commission Implementing Decision (EU) 2016/2335 of 9 December 2016 adopting a tenth update of the list of sites of Community importance for the Atlantic biogeographical region (notified under document C(2016) 8193)Council Decision (CFSP) 2016/2217 of 8 December 2016 amending Decision (CFSP) 2016/849 concerning restrictive measures against the Democratic People's Republic of KoreaCouncil Decision (EU) 2016/2311 of 8 December 2016 authorising certain Member States to accept, in the interest of the European Union, the accession of Kazakhstan to the 1980 Hague Convention on the Civil Aspects of International Child AbductionCouncil Decision (EU) 2016/2312 of 8 December 2016 authorising the Republic of Austria and Romania to accept, in the interest of the European Union, the accession of Peru to the 1980 Hague Convention on the Civil Aspects of International Child AbductionCouncil Decision (EU) 2016/2313 of 8 December 2016 authorising certain Member States to accept, in the interest of the European Union, the accession of the Republic of Korea to the 1980 Hague Convention on the Civil Aspects of International Child Abduction

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

Contents

What to look at next