Commission Regulation (EU) No 1301/2014 of 18 November 2014 on the technical specifications for interoperability relating to the ‘energy’ subsystem of the rail system in the Union Text with EEA relevance

Commission Regulation (EU) No 1301/2014 of 18 November 2014 on the technical specifications for interoperability relating to the ‘energy’ subsystem of the rail system in the Union Text with EEA relevance

Regulation (EU) No 1301/2014 · Regulation · 13 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Subject matter

Article 1

The technical specification for interoperability (TSI) relating to the ‘energy’ subsystem of the rail system in the entire European Union, as set out in the Annex, is hereby adopted.

Scope

Article 2

1.   The TSI shall apply to any new, upgraded or renewed ‘energy’ subsystem of the rail system in the European Union as defined in point 2.2 of Annex II to Directive 2008/57/EC. 2.   Without prejudice to Articles 7 and 8 and point 7.2 of the Annex, the TSI shall apply to new railway lines in the European Union, which are placed in service from 1 January 2015. 3.   The TSI shall not apply to existing infrastructure of the rail system in the European Union, which is already placed in service on all or part of the network of any Member State on 1 January 2015, except when it is subject to renewal or upgrading in accordance with Article 20 of Directive 2008/57/EC and Section 7.3 of the Annex. 4.   The TSI shall apply to the following networks: (a) the trans-European conventional rail system network as defined in Annex I, Section 1.1 of Directive 2008/57/EC; (b) the trans-European high-speed rail system network (TEN) as defined in Annex I, Section 2.1 of Directive 2008/57/EC; (c) other parts of the network of the rail system in the Union; and excludes the cases referred to in Article 1(3) of Directive 2008/57/EC. 5.   The TSI shall apply to networks with the following nominal track gauges: 1 435 mm, 1 520 mm, 1 524 mm, 1 600 mm and 1 668 mm. 6.   Metric gauge is excluded from the technical scope of this TSI.

Open points

Article 3

1.   With regard to the issues classified as ‘open points’ referred to in Appendix F of the TSI, the conditions to be complied with for verifying the interoperability pursuant to Article 17(3) of Directive 2008/57/EC shall be the national rules applicable in the Member State which authorises the placing in service of the subsystem covered by this Regulation. 2.   Within six months of the entry into force of this Regulation, each Member State shall inform the other Member States and the Commission of the following information, unless such information has already been sent to them under Commission Decisions 2008/284/EC and 2011/274/EU: (a) the national rules referred to in paragraph 1; (b) the conformity assessment and verification procedures to be carried out to apply the national rules referred to in paragraph 1; (c) the bodies designated in accordance with Article 17(3) of Directive 2008/57/EC to carry out the conformity assessment and verification procedures with respect to the open points.

Specific cases

Article 4

1.   With regard to specific cases referred to in point 7.4.2 of the Annex to this Regulation, the conditions to be met for the verification of interoperability pursuant to Article 17(3) of Directive 2008/57/EC shall be the national rules applicable in the Member State which authorises the placing in service of the subsystem covered by this Regulation. 2.   Within six months of the entry into force of this Regulation, each Member State shall send to the other Member States and to the Commission the following information: (a) the national rules referred to in paragraph 1; (b) the conformity assessment and verification procedures to be carried out to apply the national rules referred to in paragraph 1; (c) the bodies designated in accordance with Article 17(3) of Directive 2008/57/EC to carry out the conformity assessment and verification procedures in the specific cases referred to in point 7.4.2 of the Annex.

Notification of bilateral agreements

Article 5

1.   Member States shall notify the Commission, no later than 1 July 2015, any existing national, bilateral, multilateral or international agreements between Member States and railway undertaking(s), infrastructure managers or non-member countries which are required by the very specific or local nature of the intended rail service or which deliver significant levels of local or regional interoperability. That obligation does not apply to agreements which have already been notified under Commission Decision 2008/284/EC. 2.   Member States shall notify the Commission of any future agreements or amendments to existing agreements.

Projects at an advanced stage of development

Article 6

In accordance with Article 9(3) of Directive 2008/57/EC, each Member State shall communicate to the Commission within one year of the entry into force of this Regulation the list of projects being implemented within its territory and are at an advanced stage of development.

‘EC’ certificate of verification

Article 7

1.   An ‘EC’ certificate of verification for a subsystem that contains interoperability constituents which do not have an ‘EC’ declaration of conformity or suitability for use, may be issued during a transitional period ending on 31 May 2021, provided that the requirements laid down in point 6.3 of the Annex are met. 2.   The production, upgrade or renewal of the subsystem with use of the non-certified interoperability constituents shall be completed within the transitional period set out in paragraph 1, including its placing in service. 3.   During the transitional period set out in paragraph 1: (a) the reasons for non-certification of any interoperability constituents shall be properly identified by the notified body before granting the ‘EC’ certificate pursuant to Article 18 of Directive 2008/57/EC; (b) the national safety authorities, pursuant to Article 16(2)(c) of Directive 2004/49/EC  ( 5 ) , shall report on the use of non-certified interoperability constituents in the context of authorisation procedures in their annual report referred to in Article 18 of Directive 2004/49/EC. 4.   From 1 January 2016, newly produced interoperability constituents shall be covered by the EC declaration of conformity or suitability for use.

Conformity assessment

Article 8

1.   The procedures for assessment of conformity, suitability for use and ‘EC’ verification set out in Section 6 of the Annex shall be based on the modules established in Commission Decision 2010/713/EU  ( 6 ) . 2.   The type or design examination certificate of interoperability constituents shall be valid for a seven-year period. During that period, new constituents of the same type are permitted to be placed into service without a new conformity assessment. 3.   Certificates referred to in paragraph 2 which have been issued according to the requirements of Commission Decision 2011/274/EU (TSI ENE CR) or Commission Decision 2008/284/EC (TSI ENE HS) remain valid, without a need for a new conformity assessment, until the expiry date originally established. In order to renew a certificate, the design or type shall be reassessed only against new or modified requirements set out in the Annex to this Regulation.

Implementation

Article 9

1.   Section 7 of the Annex sets out the steps to be followed for the implementation of a fully interoperable energy subsystem. Without prejudice to Article 20 of Directive 2008/57/EC, Member States shall prepare a national implementation plan, describing their actions to comply with this TSI, in accordance with Section 7 of the Annex. Member States shall send their national implementation plan to the other Member States and the Commission by 31 December 2015. Member States that have already sent their implementation plan do not have to send it again. 2.   Pursuant to Article 20 of Directive 2008/57/EC, when a new authorisation is required and if the TSI is not fully applied, Member States shall notify the following information to the Commission: — the reason why the TSI is not fully applied, — the technical characteristics applicable instead of the TSI, — the bodies responsible for applying the verification procedure referred to in Article 18 of the Directive 2008/57/EC. 3.   Member States shall send to the Commission a report on the implementation of Article 20 of Directive 2008/57/EC concerning the energy subsystem three years after the entry into force of this Regulation. This report shall be discussed in the Committee set up by Article 29 of Directive 2008/57/EC and, where appropriate, the TSI in the Annex shall be adapted. 4.   In addition to the implementation of the on-ground energy data collecting system (DCS) defined in point 7.2.4 of the Annex and without prejudice to provisions of point 4.2.8.2.8 of the Annex of Commission Regulation (EU) No 1302/2014  ( 7 ) , Member States shall ensure that an on-ground settlement system capable to receive data from a DCS and accept it for billing is implemented, two years after the closing of the open points mentioned in point 4.2.17 of the Annex. The on-ground settlement system shall be able to exchange compiled energy billing data (CEBD) with other settlement systems, validate the CEBD and allocate the consumption data to the correct parties. This shall be done by taking into account the relevant legislation concerning the energy market.

Innovative solutions

Article 10

1.   In order to keep pace with technological progress, innovative solutions may be required, which do not comply with the specifications set out in the Annex or for which the assessment methods set out in the Annex cannot be applied. 2.   Innovative solutions may relate to the energy subsystem, its parts and its interoperability constituents. 3.   If an innovative solution is proposed, the manufacturer or his authorised representative established within the Union shall declare how it deviates from or complements the relevant provisions of this TSI and submit the deviations to the Commission for analysis. The Commission may request the opinion of the Agency on the proposed innovative solution. 4.   The Commission shall deliver an opinion on the proposed innovative solution. If this opinion is positive, the appropriate functional and interface specifications and the assessment method, which need to be included in the TSI in order to allow the use of this innovative solution, shall be developed and subsequently integrated in the TSI during the revision process pursuant to Article 6 of Directive 2008/57/EC. If the opinion is negative, the innovative solution proposed cannot be used. 5.   Pending the review of the TSI, the positive opinion delivered by the Commission shall be considered as an acceptable means of compliance with the essential requirements of Directive 2008/57/EC and may be used for the assessment of the subsystem.

Repeal

Article 11

Decisions 2008/284/EC and 2011/274/EU are repealed with effect from 1 January 2015. They shall however continue to apply to: (a) subsystems authorised in accordance with those Decisions; (b) projects for new, renewed or upgraded subsystems which, at the date of publication of this Regulation, are at an advanced stage of development or are the subject of an ongoing contract.

Entry into force

Article 12

This Regulation shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union . It shall apply from 1 January 2015. However, an authorisation for placing in service may be granted in accordance with the TSI as set out in the Annex to this Regulation before 1 January 2015.

Supplementary provisions

ANNEXSupplementary provisions

ANNEX TABLE OF CONTENTS 1. Introduction 188 1.1. Technical scope 188 1.2. Geographical scope 188 1.3. Content of this TSI 188 2. Description of the energy subsystem 188 2.1. Definition 188 2.1.1. Power supply 189 2.1.2. Geometry of the overhead contact line (OCL) and quality of current collection 189 2.2. Interfaces with other subsystems 189 2.2.1. Introduction 189 2.2.2. Interfaces of this TSI with the Safety in railway tunnels TSI 189 3. Essential requirements 189 4. Characterisation of the subsystem 191 4.1. Introduction 191 4.2. Functional and technical specifications of the subsystem 191 4.2.1. General provisions 191 4.2.2. Basic parameters characterising the energy subsystem 192 4.2.3. Voltage and frequency 192 4.2.4. Parameters relating to supply system performance 192 4.2.5. Current capacity, DC systems, trains at standstill 193 4.2.6. Regenerative braking 193 4.2.7. Electrical protection coordination arrangements 193 4.2.8. Harmonics and dynamic effects for AC traction power supply systems 193 4.2.9. Geometry of the overhead contact line 193 4.2.10. Pantograph gauge 194 4.2.11. Mean contact force 205 4.2.12. Dynamic behaviour and quality of current collection 205 4.2.13. Pantograph spacing for overhead contact line design 205 4.2.14. Contact wire material 196 4.2.15. Phase separation sections 196 4.2.16. System separation sections 197 4.2.17. On-ground energy data collecting system 197 4.2.18. Protective provisions against electric shock 197 4.3. Functional and technical specifications of the interfaces 198 4.3.1. General requirements 198 4.3.2. Interface with Rolling Stock subsystem. 198 4.3.3. Interface with Infrastructure subsystem 199 4.3.4. Interface with Control — Command and Signalling subsystems 199 4.3.5. Interface with Operation and traffic management subsystem 199 4.4. Operating rules 199 4.5. Maintenance rules 199 4.6. Professional qualifications 200 4.7. Health and safety conditions 200 5. Interoperability constituents 200 5.1. List of constituents 200 5.2. Constituents' performances and specifications 200 5.2.1. Overhead contact line 200 6. Assessment of conformity of the interoperability constituents and EC verification of the subsystems 201 6.1. Interoperability constituents 201 6.1.1. Conformity assessment procedures 201 6.1.2. Application of modules 201 6.1.3. Innovative solutions for interoperability constituents 202 6.1.4. Particular assessment procedure for the interoperability constituent — overhead contact line 202 6.1.5. EC declaration of conformity of interoperability constituent OCL 203 6.2. Energy subsystem 203 6.2.1. General provisions 203 6.2.2. Application of modules 203 6.2.3. Innovative solutions 204 6.2.4. Particular assessment procedures for energy subsystem 204 6.3. Sub-system containing interoperability constituents not holding an EC declaration 205 6.3.1. Conditions 205 6.3.2. Documentation 205 6.3.3. Maintenance of the subsystems certified according to 6.3.1 206 7. Implementation of the Energy TSI 206 7.1. Application of this TSI to railway lines 206 7.2. Application of this TSI to new, renewed or upgraded railway lines 206 7.2.1. Introduction 206 7.2.2. Implementation plan for voltage and frequency 206 7.2.3. Implementation plan for OCL geometry 207 7.2.4. Implementation of the on-ground energy data collecting system 207 7.3. Application of this TSI to existing lines 207 7.3.1. Introduction 207 7.3.2. Upgrading/renewal of the OCL and/or the power supply 208 7.3.3. Parameters related to maintenance 208 7.3.4. Existing subsystem that are not subject to a renewal or upgrading project 208 7.4. Specific cases 208 7.4.1. General 208 7.4.2. List of specific cases 208 Appendix A — Conformity assessment of interoperability constituents 212 Appendix B — EC verification of the energy subsystem 213 Appendix C — Mean useful voltage 215 Appendix D — Specification of the pantograph gauge 216 Appendix E — List of referenced standards 224 Appendix F — List of open points 225 Appendix G — Glossary 226 1.   INTRODUCTION 1.1.    Technical scope (1) This TSI concerns the energy subsystem and part of the maintenance subsystem of the Union rail system in accordance with Article 1 of Directive 2008/57/EC. (2) The energy subsystem is defined in Annex II (2.2) to Directive 2008/57/EC. (3) The technical scope of this TSI is further defined in Article 2 of this Regulation. 1.2.    Geographical scope The geographical scope of this TSI is defined in Article 2(4) of this Regulation. 1.3.    Content of this TSI (1) In accordance with Article 5(3) of Directive 2008/57/EC, this TSI: (a) indicates its intended scope (Section 2); (b) lays down essential requirements for the energy subsystem (Section 3); (c) establishes the functional and technical specifications to be met by the subsystem and its interfaces vis-à-vis other subsystems (Section 4); (d) specifies the interoperability constituents and interfaces which must be covered by European specifications, including European standards, which are necessary to achieve interoperability within the Union rail system (Section 5); (e) states, in each case under consideration, which procedures are to be used in order to assess the conformity or the suitability for use of the interoperability constituents, on the one hand, or the EC verification of the subsystems, on the other hand (Section 6); (f) sets out the implementation plan of this TSI (Section 7); (g) indicates, for the staff concerned, the professional qualifications and health and safety conditions required at work for the operation and maintenance of the subsystem, as well as for the implementation of this TSI (Section 4). (2) In accordance with Article 5(5) of the Directive 2008/57/EC, provisions for specific cases are indicated in Section 7. (3) Requirements in this TSI are valid for all track gauge systems within the scope of this TSI, unless a paragraph refers to specific track gauge systems or to specific nominal track gauges. 2.   DESCRIPTION OF THE ENERGY SUBSYSTEM 2.1.    Definition (1) This TSI covers all fixed installations necessary to achieve interoperability that are required to supply traction energy to a train. (2) The energy subsystem consists of: (a)    substations : connected on the primary side to the high-voltage grid, with transformation of the high-voltage to a voltage and/or conversion to a power supply system suitable for the trains. On the secondary side, substations are connected to the railway contact line system; (b)    sectioning locations : electrical equipment located at intermediate locations between substations to supply and parallel contact lines and to provide protection, isolation and auxiliary supplies; (c)    separation sections : equipment required to provide the transition between electrically different systems or between different phases of the same electrical system; (d)    contact line system : a system that distributes the electrical energy to the trains running on the route and transmits it to the trains by means of current collectors. The contact line system is also equipped with manually or remotely controlled disconnectors which are required to isolate sections or groups of the contact line system according to operational necessity. Feeder lines are also part of the contact line system; (e)    return circuit : all conductors which form the intended path for the traction return current. Therefore, so far as this aspect is concerned, the return circuit is part of the energy subsystem and has an interface with the infrastructure subsystem. (3) In accordance with Annex II, Section 2.2 of Directive 2008/57/EC, the trackside of the electricity consumption measuring system, referred to in this TSI as on-ground energy data collection system, is set out in point 4.2.17 of this TSI. 2.1.1.    Power supply (1) The objective of the power supply system is to supply every train with power in order to meet the planned timetable. (2) Basic parameters for power supply system are defined in point 4.2. 2.1.2.    Geometry of the overhead contact line (OCL) and quality of current collection (1) The objective is to ensure reliable and continuous power transfer from the power supply system to the rolling stock. The interaction between the overhead contact line and the pantograph is an important aspect of interoperability. (2) Basic parameters referring to the geometry of the OCL and quality of current collection are set out in point 4.2. 2.2.    Interfaces with other subsystems 2.2.1.    Introduction (1) The energy subsystem interfaces with other subsystems of the rail system in order to achieve the envisaged performance. These subsystems are listed below: (a) Rolling stock; (b) Infrastructure; (c) Trackside control command and signalling; (d) On-board control command and signalling; (e) Operation and traffic management. (2) Point 4.3 of this TSI sets out the functional and technical specification of these interfaces. 2.2.2.    Interfaces of this TSI with the Safety in railway tunnels TSI Requirements relating to the energy subsystem for safety in railway tunnels are set out in the TSI relating to Safety in railway tunnels. 3.   ESSENTIAL REQUIREMENTS The following table indicates basic parameters of this TSI and their correspondence to the essential requirements as set out and numbered in Annex III of Directive 2008/57/EC. TSI point Title of TSI point Safety R&A Health Environ-mental protection Tech. Compati-bility Accessibility 4.2.3 Voltage and frequency — — — — 1.5 2.2.3 — 4.2.4 Parameters relating to supply system performance — — — — 1.5 2.2.3 — 4.2.5 Current capacity, DC systems, trains at standstill — — — — 1.5 2.2.3 — 4.2.6 Regenerative braking — — — 1.4.1 1.4.3 1.5 2.2.3 — 4.2.7 Electrical protection coordination arrangements 2.2.1 — — — 1.5 — 4.2.8 Harmonics and dynamic effects for AC traction power supply systems — — — 1.4.1 1.4.3 1.5 — 4.2.9 Geometry of the overhead contact line — — — — 1.5 2.2.3 — 4.2.10 Pantograph gauge — — — — 1.5 2.2.3 — 4.2.11 Mean contact force — — — — 1.5 2.2.3 — 4.2.12 Dynamic behaviour and quality of current collection — — — 1.4.1 2.2.2 1.5 2.2.3 — 4.2.13 Pantograph spacing for overhead contact line design — — — — 1.5 2.2.3 — 4.2.14 Contact wire material — — 1.3.1 1.3.2 1.4.1 1.5 2.2.3 — 4.2.15 Phase separation sections 2.2.1 — — 1.4.1 1.4.3 1.5 2.2.3 — 4.2.16 System separation sections 2.2.1 — — 1.4.1 1.4.3 1.5 2.2.3 — 4.2.17 On-ground energy data collecting system — — — — 1.5 — 4.2.18 Protective provisions against electric shock 1.1.1 1.1.3 2.2.1 — — 1.4.1 1.4.3 2.2.2 1.5 — 4.4 Operating rules 2.2.1 — — — 1.5 — 4.5 Maintenance rules 1.1.1 2.2.1 1.2 — — 1.5 2.2.3 — 4.6 Professional qualifications 2.2.1 — — — — — 4.7 Health and safety conditions 1.1.1 1.1.3 2.2.1 — — 1.4.1 1.4.3 2.2.2 — — 4.   CHARACTERISATION OF THE SUBSYSTEM 4.1.    Introduction (1) The whole rail system, to which Directive 2008/57/EC applies and of which the energy subsystem is a part, is an integrated system whose consistency needs to be verified. This consistency must be checked, in particular, with regard to the specifications of the energy subsystem, its interfaces vis-à-vis the system in which it is integrated, as well as the operating and maintenance rules. The functional and technical specifications of the subsystem and its interfaces, described in points 4.2 and 4.3, do not impose the use of specific technologies or technical solutions, except where this is strictly necessary for the interoperability of the rail network. (2) Innovative solutions for interoperability, which do not fulfil requirements specified in this TSI and are not assessable as stated in this TSI, require new specifications and/or new assessment methods. In order to allow technological innovation, these specifications and assessment methods shall be developed by the process for innovative solutions described in points 6.1.3 and 6.2.3. (3) Taking account of all the applicable essential requirements, the energy subsystem is characterised by the specifications set out in points 4.2 to 4.7. (4) Procedures for the EC verification of the energy subsystem are indicated in point 6.2.4 and Appendix B, Table B.1, of this TSI. (5) For specific cases, see point 7.4. (6) Where reference is made to EN standards in this TSI, any variations called ‘national deviations’ or ‘special national conditions’ in the EN standards are not applicable and do not form part of this TSI. 4.2.    Functional and technical specifications of the subsystem 4.2.1.    General provisions The performance to be achieved by the energy subsystem is specified at least by the required performance of the rail system with respect to: (a) maximum line speed; (b) type(s) of train; (c) train service requirements; (d) power demand of the trains at the pantographs. 4.2.2.    Basic parameters characterising the energy subsystem The basic parameters characterising the energy subsystem are: 4.2.2.1. Power supply: (a) Voltage and frequency (4.2.3); (b) Parameters relating to supply system performance (4.2.4); (c) Current capacity, DC systems, trains at standstill (4.2.5); (d) Regenerative braking (4.2.6); (e) Electrical protection coordination arrangements (4.2.7); (f) Harmonics and dynamic effects for AC traction power supply systems (4.2.8). 4.2.2.2. Geometry of the OCL and quality of current collection: (a) Geometry of the overhead contact line (4.2.9); (b) Pantograph gauge (4.2.10); (c) Mean contact force (4.2.11); (d) Dynamic behaviour and quality of current collection (4.2.12); (e) Pantograph spacing for overhead contact line design (4.2.13); (f) Contact wire material (4.2.14); (g) Phase separation sections (4.2.15); (h) System separation sections (4.2.16). 4.2.2.3. On-ground energy data collecting system (4.2.17) 4.2.2.4. Protective provisions against electric shock (4.2.18) 4.2.3.    Voltage and frequency (1) The voltage and frequency of the energy subsystem shall be one of the four systems, specified in accordance with Section 7: (a) AC 25 kV, 50 Hz; (b) AC 15 kV, 16,7 Hz; (c) DC 3 kV; (d) DC 1,5 kV. (2) The values and limits of the voltage and frequency shall comply with EN 50163:2004, clause 4 for the selected system. 4.2.4.    Parameters relating to supply system performance The following parameters shall be taken in consideration: (a) maximum train current (4.2.4.1); (b) power factor of trains and the mean useful voltage (4.2.4.2). 4.2.4.1.    Maximum train current The energy subsystem design shall ensure the ability of the power supply to achieve the specified performance and allow the operation of trains with a power less than 2 MW without power or current limitation. 4.2.4.2.    Mean useful voltage The calculated mean useful voltage ‘at the pantograph’ shall comply with EN 50388:2012, clause 8 (except clause 8.3 that is replaced by point C.1 of Appendix C). Simulation shall take into account values of the real power factor of trains. Point C.2 of Appendix C provides additional information to clause 8.2 of the EN 50388:2012. 4.2.5.    Current capacity, DC systems, trains at standstill (1) The OCL of DC systems shall be designed to sustain 300 A (for a 1,5 kV supply system) and 200 A (for a 3 kV supply system), per pantograph when the train is at standstill. (2) The current capacity at standstill shall be achieved for the test value of static contact force given in table 4 of clause 7.2 of EN 50367:2012. (3) The OCL shall be designed taking into account the temperature limits in accordance with EN 50119:2009, clause 5.1.2. 4.2.6.    Regenerative braking (1) AC power supply systems shall be designed to allow the use of regenerative braking able to exchange power seamlessly either with other trains or by any other means. (2) DC power supply systems shall be designed to permit the use of regenerative braking at least by exchanging power with other trains. 4.2.7.    Electrical protection coordination arrangements Electrical protection coordination design of the energy subsystem shall comply with the requirements detailed in EN 50388:2012, clause 11. 4.2.8.    Harmonics and dynamic effects for AC traction power supply systems (1) The interaction of traction power supply system and rolling stock can lead to electrical instabilities in the system. (2) In order to achieve electrical system compatibility, harmonic overvoltages shall be limited below critical values according to EN 50388:2012, clause 10.4. 4.2.9.    Geometry of the overhead contact line (1) The overhead contact line shall be designed for pantographs with the head geometry specified in the LOC & PAS TSI, point 4.2.8.2.9.2 taking into account the rules set out in point 7.2.3 of this TSI. (2) The contact wire height and the lateral deviation of the contact wire under the action of a cross-wind are factors which govern the interoperability of the rail network. 4.2.9.1.    Contact wire height (1) The permissible data for contact wire height is given in Table 4.2.9.1. Table 4.2.9.1 Contact wire height Description v ≥ 250 [km/h] v < 250 [km/h] Nominal contact wire height [mm] Between 5 080 and 5 300 Between 5 000 and 5 750 Minimum design contact wire height [mm] 5 080 In accordance with EN 50119:2009, clause 5.10.5 depending on the chosen gauge Maximum design contact wire height [mm] 5 300 6 200  ( 1 ) (2) For the relation between the contact wire heights and pantograph working heights see EN 50119:2009 figure 1. (3) At level crossings the contact wire height shall be specified by national rules or in the absence of national rules, according to EN 50122-1:2011, clauses 5.2.4 and 5.2.5. (4) For the track gauge system 1 520 and 1 524 mm the values for contact wire height are as follows: (a) Nominal contact wire height: between 6 000 mm and 6 300 mm; (b) Minimum design contact wire height: 5 550 mm; (c) Maximum design contact wire height: 6 800 mm. 4.2.9.2.    Maximum lateral deviation (1) The maximum lateral deviation of the contact wire in relation to the track centre line under action of a cross wind shall be in accordance to table 4.2.9.2. Table 4.2.9.2 Maximum lateral deviation depending on the pantograph length Pantograph length [mm] Maximum lateral deviation [mm] 1 600 400  ( 2 ) 1 950 550  ( 2 ) (2) In the case of the multi-rail track, the requirement for lateral deviation shall be fulfilled for each pair of rails (designed, to be operated as a separated track) that is intended to be assessed against TSI. (3) Track gauge system 1 520 mm: For Member States applying the pantograph profile according to LOC&PAS TSI, point 4.2.8.2.9.2.3 the maximum lateral deviation of the contact wire in relation to the pantograph centre under action of a cross wind shall be 500 mm. 4.2.10.    Pantograph gauge (1) No part of the energy sub-system shall enter the mechanical kinematic pantograph gauge (see Appendix D figure D.2) except for the contact wire and steady arm. (2) The mechanical kinematic pantograph gauge for interoperable lines is specified using the method shown in Appendix D.1.2 and the pantograph profiles defined in LOC&PAS TSI, points 4.2.8.2.9.2.1 and 4.2.8.2.9.2.2. (3) This gauge shall be calculated using a kinematic method, with values: (a) for the pantograph sway e pu of 0,110 m at the lower verification height h′ u  = 5,0 m and (b) for the pantograph sway e po of 0,170 m at the upper verification height h′ o  = 6,5 m, in accordance with point D.1.2.1.4 of Appendix D and other values in accordance with point D.1.3 of Appendix D. (4) Track gauge system 1 520 mm: For Member States applying the pantograph profile according to LOC&PAS TSI, point 4.2.8.2.9.2.3 the static gauge available for pantograph is defined in point D.2 of Appendix D. 4.2.11.    Mean contact force (1) The mean contact force F m is the statistical mean value of the contact force. F m is formed by the static, dynamic and aerodynamic components of the pantograph contact force. (2) The ranges of F m for each of the power supply systems are defined in EN 50367:2012 Table 6. (3) The overhead contact lines shall be designed to be capable to sustain the upper design limit of F m given in EN 50367:2012 Table 6. (4) The curves apply to speed up to 320 km/h. For speeds above 320 km/h procedures set out in point 6.1.3 shall apply. 4.2.12.    Dynamic behaviour and quality of current collection (1) Depending on the assessment method, the overhead contact line shall achieve the values of dynamic performance and contact wire uplift (at the design speed) set out in Table 4.2.12. Table 4.2.12 Requirements for dynamic behaviour and current collection quality Requirement v ≥ 250 [km/h] 250 > v > 160 [km/h] v ≤ 160 [km/h] Space for steady arm uplift 2 S 0 Mean contact force F m See 4.2.11 Standard deviation at maximum line speed σ max [N] 0,3F m Percentage of arcing at maximum line speed, NQ [%] (minimum duration of arc 5 ms) ≤ 0,2 ≤ 0,1 for AC systems ≤ 0,2 for DC systems ≤ 0,1 (2) S 0 is the calculated, simulated or measured uplift of the contact wire at a steady arm, generated in normal operating conditions with one or more pantographs with the upper limit of F m at the maximum line speed. When the uplift of the steady arm is physically limited due to the overhead contact line design, it is permissible for the necessary space to be reduced to 1,5S 0 (refer to EN 50119:2009, clause 5.10.2). (3) Maximum force (F max ) is usually within the range of F m plus three standard deviations σ max ; higher values may occur at particular locations and are given in EN 50119:2009, table 4, clause 5.2.5.2. For rigid components such as section insulators in overhead contact line systems, the contact force can increase up to a maximum of 350 N. 4.2.13.    Pantograph spacing for overhead contact line design The overhead contact line shall be designed for a minimum of two pantographs operating adjacently, in such a way that minimum spacing centre line to centre line of adjacent pantographs heads is equal or lower than values set out in one column ‘A’, ‘B’, or ‘C’ selected from Table 4.2.13: Table 4.2.13 Pantograph spacing for OCL design Design speed [km/h] AC Minimum distance [m] 3 kV DC Minimum distance [m] 1,5 kV DC Minimum distance [m] Type A B C A B C A B C v ≥ 250 200 200 200 200 35 160 < v < 250 200 85 35 200 115 35 200 85 35 120 < v ≤ 160 85 85 35 20 20 20 85 35 20 80 < v ≤ 120 20 15 15 20 15 15 35 20 15 v ≤ 80 8 8 8 8 8 8 20 8 8 4.2.14.    Contact wire material (1) The combination of contact wire material and contact strip material has a strong impact on the wear of contact strips and contact wire. (2) Permissible contact strip materials are defined in point 4.2.8.2.9.4.2 of LOC&PAS TSI. (3) Permissible materials for contact wires are copper and copper-alloy. The contact wire shall comply with the requirements of EN 50149:2012, clauses 4.2, (excluding the reference to annex B of the standard) 4.3 and 4.6 to 4.8. 4.2.15.    Phase separation sections 4.2.15.1.    General (1) The design of phase separation sections shall ensure that trains can move from one section to an adjacent one without bridging the two phases. Power consumption of the train (traction, auxiliaries and no-load current of the transformer) shall be brought to zero before entering the phase separation section. Adequate means (except for the short separation section) shall be provided to allow a train that is stopped within the phase separation section to be restarted. (2) The overall length D of neutral sections is defined in EN 50367:2012, clause 4. For the calculation of D clearances in accordance to EN 50119:2009, clause 5.1.3 and an uplift of S 0 shall be taken into account. 4.2.15.2.    Lines with speed v ≥ 250 km/h Two types of designs of phase separation sections may be adopted, either: (a) a phase separation design where all the pantographs of the longest TSI compliant trains are within the neutral section. The overall length of the neutral section shall be at least 402 m. For detailed requirements see EN 50367:2012, Annex A.1.2, or (b) a shorter phase separation with three insulated overlaps as shown in EN 50367:2012, Annex A.1.4. The overall length of the neutral section is less than 142 m including clearances and tolerances. 4.2.15.3.    Lines with speed v < 250 km/h The design of separation sections shall normally adopt solutions as described in EN 50367:2012, Annex A.1. Where an alternative solution is proposed, it shall be demonstrated that the alternative is at least as reliable. 4.2.16.    System separation sections 4.2.16.1.    General (1) The design of system separation sections shall ensure that trains can move from one power supply system to an adjacent different power supply system without bridging the two systems. There are two methods for traversing system separation sections: (a) with pantograph raised and touching the contact wire; (b) with pantograph lowered and not touching the contact wire. (2) The neighbouring Infrastructure Managers shall agree either (a) or (b) according to the prevailing circumstances. (3) The overall length D of neutral sections is defined in EN 50367:2012, clause 4. For the calculation of D clearances in accordance to EN 50119:2009, clause 5.1.3 and an uplift of S 0 shall be taken into account. 4.2.16.2.    Pantographs raised (1) Power consumption of the train (traction, auxiliaries and no-load current of the transformer) shall be brought to zero before entering the system separation section. (2) If system separation sections are traversed with pantographs raised to the contact wire, their functional design is specified as follows: (a) the geometry of different elements of the overhead contact line shall prevent pantographs short-circuiting or bridging both power systems; (b) provision shall be made in the energy subsystem to avoid bridging of both adjacent power supply systems should the opening of the on-board circuit breaker(s) fail; (c) variation in contact wire height along the entire separation section shall fulfil requirements set in EN 50119:2009, clause 5.10.3. 4.2.16.3.    Pantographs lowered (1) This option shall be chosen if the conditions of operation with pantographs raised cannot be met. (2) If a system separation section is traversed with pantographs lowered, it shall be designed so as to avoid the electrical connection of the two power supply systems by an unintentionally raised pantograph. 4.2.17.    On-ground energy data collecting system (1) Point 4.2.8.2.8 of LOC & PAS TSI contains the requirements for on-board Energy Measuring Systems (EMS) intended to produce and transmit the Compiled Energy Billing Data (CEBD) to an on-ground energy data collecting system. (2) The on-ground energy data collecting system (DCS) shall receive, store and export CEBD without corrupting it. (3) The specification related to interface protocols between EMS and DCS and transferred data format are an open point, which, in any case, shall be closed within 2 years after the entry into force of this Regulation. 4.2.18.    Protective provisions against electric shock Electrical safety of the overhead contact line system and protection against electric shock shall be achieved by compliance with EN 50122-1:2011+A1:2011, clauses 5.2.1 (only for public areas), 5.3.1, 5.3.2, 6.1, 6.2 (excluding requirements for connections for track circuits) and regarding AC voltage limits for the safety of persons by compliance with 9.2.2.1 and 9.2.2.2 of the standard and regarding DC voltage limits by compliance with 9.3.2.1 and 9.3.2.2 of the standard. 4.3.    Functional and technical specifications of the interfaces 4.3.1.    General requirements From the standpoint of technical compatibility, the interfaces are listed in subsystem order as follows: rolling stock, infrastructure, control — command and signalling, and operation and traffic management. 4.3.2.    Interface with Rolling Stock subsystem. Reference in the ENE TSI Reference in the LOC & PAS TSI Parameter Point Parameter Point Voltage and frequency 4.2.3 Operation within range of voltages and frequencies 4.2.8.2.2 Parameters relating to supply system performance: — max train current — power factor of trains and the mean useful voltage 4.2.4 Max current from OCL Power factor 4.2.8.2.4 4.2.8.2.6 Current capacity, DC systems, trains at standstill 4.2.5 Maximum current at standstill 4.2.8.2.5 Regenerative braking 4.2.6 Regenerative brake with energy to OCL 4.2.8.2.3 Electrical protection coordination arrangements 4.2.7 Electrical protection of the train 4.2.8.2.10 Harmonics and dynamic effects for AC traction power supply systems 4.2.8 System energy disturbances for AC systems 4.2.8.2.7 Geometry of the overhead contact line 4.2.9 Working range in height of pantograph Pantograph head geometry 4.2.8.2.9.1 4.2.8.2.9.2 Pantograph gauge 4.2.10 Appendix D Pantograph head geometry Gauging 4.2.8.2.9.2 4.2.3.1 Mean contact force 4.2.11 Pantograph static contact force 4.2.8.2.9.5 Pantograph contact force and dynamic behaviour 4.2.8.2.9.6 Dynamic behaviour and quality of current collection 4.2.12 Pantograph contact force and dynamic behaviour 4.2.8.2.9.6 Pantograph spacing for overhead contact line design 4.2.13 Arrangements of pantographs 4.2.8.2.9.7 Contact wire material 4.2.14 Contact strip material 4.2.8.2.9.4 Separation sections:   phase   system 4.2.15 4.2.16 Running through phase or system separation section 4.2.8.2.9.8 On-ground energy data collecting system 4.2.17 On-board Energy measurement system 4.2.8.2.8 4.3.3.    Interface with Infrastructure subsystem Reference in the ENE TSI Reference in the INF TSI Parameter Point Parameter Point Pantographs gauge 4.2.10 Structure gauge 4.2.3.1 4.3.4.    Interface with Control — Command and Signalling subsystems (1) The interface for power control is an interface between the energy and the rolling stock subsystems. (2) However, the information is transmitted via the control-command and signalling subsystems and consequently the transmission interface is specified in the CCS TSI and the LOC & PAS TSI. (3) The relevant information to perform the switching of the circuit breaker, change of maximum train current, change of the power supply system and pantograph management shall be transmitted via ERTMS when the line is equipped with ERTMS. (4) Harmonic currents affecting control-command and signalling subsystems are set out in the CCS TSI. 4.3.5.    Interface with Operation and traffic management subsystem Reference in the ENE TSI Reference in the OPE TSI Parameter Point Parameter Point Maximum train current 4.2.4.1 Train composition Preparation of the Route Book 4.2.2.5 4.2.1.2.2.1 Separation sections:   Phase   System 4.2.15 4.2.16 Train composition Preparation of the Route Book 4.2.2.5 4.2.1.2.2.1 4.4.    Operating rules (1) Operating rules are developed within the procedures described in the infrastructure manager safety management system. These rules take into account the documentation related to operation, which forms a part of the technical file, as required in Article 18(3) and as set out in Annex VI of Directive 2008/57/EC. (2) In certain situations involving pre-planned works, it may be necessary to temporarily derogate from the specifications of the energy subsystem and its interoperability constituents defined in Sections 4 and 5 of the TSI. 4.5.    Maintenance rules (1) Maintenance rules are developed within the procedures described in the infrastructure manager safety management system. (2) The maintenance file for ICs and subsystem elements shall be prepared before placing a subsystem into service as the part of the technical file accompanying the declaration of verification. (3) The maintenance plan shall be drawn up for the subsystem to ensure that the requirements set out in this TSI are maintained during its lifetime. 4.6.    Professional qualifications The professional qualifications of staff required for the operation and maintenance of the energy subsystem are covered by the procedures described in the infrastructure manager safety management system and are not set out in this TSI. 4.7.    Health and safety conditions (1) The health and safety conditions of staff required for the operation and maintenance of the energy subsystem shall be compliant with the relevant European and national legislation. (2) This issue is also covered by the procedures described in the infrastructure manager safety management system. 5.   INTEROPERABILITY CONSTITUENTS 5.1.    List of constituents (1) The interoperability constituents are covered by the relevant provisions of Directive 2008/57/EC and they are listed here below for the energy subsystem. (2) Overhead contact line: (a) The interoperability constituent overhead contact line consists of the components listed below to be installed within an energy subsystem and the associated design and configuration rules. (b) The components of an overhead contact line are an arrangement of wire(s) suspended over the railway line for supplying electricity to electric trains, together with associated fittings, in-line insulators and other attachments including feeders and jumpers. It is placed above the upper limit of the vehicle gauge, supplying vehicles with electrical energy through pantographs. (c) The supporting components such as cantilevers, masts and foundations, return conductors, auto-transformer feeders, switches and other insulators are not part of the interoperability constituent overhead contact line. They are covered by subsystem requirements so far as interoperability is concerned. (3) The conformity assessment shall cover the phases and characteristics as indicated in point 6.1.4 and by X in the Table A.1 of Appendix A to this TSI. 5.2.    Constituents' performances and specifications 5.2.1.    Overhead contact line 5.2.1.1.    Geometry of the OCL The design of the overhead contact line shall comply with point 4.2.9. 5.2.1.2.    Mean contact force The overhead contact line shall be designed by using the mean contact force F m stipulated in point 4.2.11. 5.2.1.3.    Dynamic behaviour Requirements for dynamic behaviour of the overhead contact line are set out in point 4.2.12. 5.2.1.4.    Space for steady arm uplift The overhead contact line shall be designed providing the required space for uplift as set out in point 4.2.12. 5.2.1.5.    Pantograph spacing for overhead contact line design The overhead contact line shall be designed for pantograph spacing as specified in point 4.2.13. 5.2.1.6.    Current at standstill For DC systems, the overhead contact line shall be designed for the requirements set out in point 4.2.5. 5.2.1.7.    Contact wire material The contact wire material shall comply with the requirements set out in point 4.2.14. 6.   ASSESSMENT OF CONFORMITY OF THE INTEROPERABILITY CONSTITUENTS AND EC VERIFICATION OF THE SUBSYSTEMS Modules for the procedures for assessment of conformity, suitability for use and EC verification modules are described in the Commission Decision 2010/713/EU. 6.1.    Interoperability constituents 6.1.1.    Conformity assessment procedures (1) The conformity assessment procedures of interoperability constituents as defined in Section 5 of this TSI shall be carried out by application of relevant modules. (2) Assessment procedures for particular requirements for interoperability constituent are set out in point 6.1.4. 6.1.2.    Application of modules (1) The following modules for conformity assessment of interoperability constituents are used: (a) CA Internal production control (b) CB EC type examination (c) CC Conformity to type based on internal production control (d) CH Conformity based on full quality management system (e) CH1 Conformity based on full quality management system plus design examination Table 6.1.2 Modules for conformity assessment to be applied for ICs Procedures Modules Placed on the EU market before entry in force of this TSI CA or CH Placed on the EU market after entry in force of this TSI CB + CC or CH1 (2) The modules for conformity assessment of interoperability constituents shall be chosen from those shown in Table 6.1.2. (3) In the case of products placed on the market before the publication of relevant TSIs, the type is considered to have been approved and therefore EC type examination (module CB) is not necessary, provided that the manufacturer demonstrates that tests and verification of interoperability constituents have been considered successful for previous applications under comparable conditions and are in conformity with the requirements of this TSI. In this case these assessments shall remain valid in the new application. If it is not possible to demonstrate that the solution is positively proven in the past, the procedure for ICs placed on the EU market after publication of this TSI applies. 6.1.3.    Innovative solutions for interoperability constituents If an innovative solution is proposed for an interoperability constituent, the procedure described in Article 10 of this Regulation shall apply. 6.1.4.    Particular assessment procedure for the interoperability constituent — overhead contact line 6.1.4.1.    Assessment of dynamic behaviour and quality of current collection (1) Methodology: (a) The assessment of the dynamic behaviour and the quality of the current collection involves the overhead contact line (energy subsystem) and the pantograph (rolling stock subsystem). (b) Compliance with the requirements on dynamic behaviour shall be verified by assessment of: — Contact wire uplift and either: — Mean contact force F m and standard deviation σ max or — Percentage of arcing (c) The Contracting Entity shall declare the method to be used for verification. (d) The design of overhead contact line shall be assessed with a simulation tool validated according with EN 50318:2002 and by measurement according to EN 50317:2012. (e) If an existing OCL design has been in operation for at least 20 years, then the requirement for simulation defined in the point (2) is optional. The measurement as defined in point (3) shall be carried out for the worst case arrangements of the pantographs regarding the interaction performance of this particular OCL design. (f) The measurement can be conducted on a specially constructed test section or on a line where the overhead contact line is under construction. (2) Simulation: (a) For the purposes of simulation and analysis of the results, representative features (for example tunnels, crossovers, neutral sections etc.) shall be taken into account. (b) The simulations shall be made using at least two different TSI compliant types of pantograph for the appropriate speed  ( 3 ) and supply system, up to the design speed of the proposed interoperability constituent overhead contact line. (c) It is allowed to perform the simulation using types of pantograph that are under the process of IC certification, provided that they fulfil the other requirements of LOC&PAS TSI. (d) The simulation shall be performed for single pantograph and multiple pantographs with spacing according to the requirements set in point 4.2.13. (e) In order to be acceptable, the simulated current collection quality shall be in accordance with point 4.2.12 for uplift, mean contact force and standard deviation for each of the pantographs. (3) Measurement: (a) If the simulation results are acceptable, a site dynamic test with a representative section of the new overhead contact line shall be undertaken. (b) This measurement can be done before putting into service or under full operation conditions. (c) For the above mentioned site test, one of the two types of the pantograph chosen for the simulation shall be installed on a rolling stock that allows the appropriate speed on the representative section. (d) The tests shall be performed at least for the worst case arrangements of the pantographs regarding the interaction performance derived from the simulations. If it is not possible to test using spacing between pantographs of 8 m, then it is permissible, for tests at speeds of up to 80 km/h, to increase the spacing between two consecutive pantographs to up to 15 m. (e) The mean contact force of each pantograph shall fulfil the requirements of the point 4.2.11 up to envisaged design speed of the OCL under test. (f) In order to be acceptable, the measured current collection quality shall be in accordance with point 4.2.12, for uplift, and either the mean contact force and standard deviation or percentage of arcing. (g) If all the above assessments are passed successfully, the tested overhead contact line design shall be considered to be compliant and may be used on lines where the characteristics of the design are compatible. (h) Assessment of dynamic behaviour and quality of current collection for interoperability constituent pantograph is set out in the point 6.1.3.7 of the LOC & PAS TSI. 6.1.4.2.    Assessment of current at standstill The conformity assessment shall be carried out in accordance with EN 50367:2012, Annex A.3 for the static force defined in point 4.2.5. 6.1.5.    EC declaration of conformity of interoperability constituent OCL According to Annex IV, Section 3 of Directive 2008/57/EC, the EC declaration of conformity shall be accompanied by statement setting out the condition of use: (a) maximum design speed; (b) nominal voltage and frequency; (c) nominal current rating; (d) accepted pantograph profile. 6.2.    Energy subsystem 6.2.1.    General provisions (1) At the request of the applicant, the notified body carries out EC verification in accordance with Article 18 of Directive 2008/57/EC and in accordance with the provisions of the relevant modules. (2) If the applicant demonstrates that tests or verifications of an energy subsystem have been successful for previous applications of a design in similar circumstances, the notified body shall take these tests and verifications into account for the EC verification. (3) Assessment procedures for particular requirements for subsystem are set out in point 6.2.4. (4) The applicant shall draw up the EC declaration of verification for the energy subsystem in accordance with Article 18(1) of and Annex V to Directive 2008/57/EC. 6.2.2.    Application of modules For the EC verification procedure of the energy subsystem, the applicant or its authorised representative established within the Community may choose either: (a) Module SG: EC verification based on unit verification, or (b) Module SH1: EC verification based on full quality management system plus design examination. 6.2.2.1.    Application of module SG In case of module SG, the notified body may take into account evidence of examinations, checking or tests that have been successfully performed under comparable conditions by other bodies or by (or on behalf of) the applicant. 6.2.2.2.    Application of module SH1 The module SH1 may be chosen only where the activities contributing to the proposed subsystem to be verified (design, manufacturing, assembling, installation) are subject to a quality management system for design, production, final product inspection and testing, approved and surveyed by a notified body. 6.2.3.    Innovative solutions If an innovative solution is proposed for the energy subsystem, the procedure described in Article 10 of this Regulation shall apply. 6.2.4.    Particular assessment procedures for energy subsystem 6.2.4.1.    Assessment of mean useful voltage (1) The assessment shall be demonstrated in accordance with EN 50388:2012, clause 15.4. (2) The assessment shall be demonstrated only in the case of newly build or upgraded sub-systems. 6.2.4.2.    Assessment of regenerative braking (1) The assessment for AC power supply fixed installations shall be demonstrated according to EN 50388:2012, clause 15.7.2. (2) The assessment for DC power supply shall be demonstrated by a design review. 6.2.4.3.    Assessment of electrical protection coordination arrangements The assessment shall be demonstrated for design and operation of substations in accordance with EN 50388:2012, clause 15.6. 6.2.4.4.    Assessment of harmonics and dynamic effects for AC traction power supply systems (1) A compatibility study shall be carried out according to EN 50388:2012, clause 10.3. (2) This study shall be carried out only in the case of introducing converters with active semi-conductors in the power supply system. (3) The notified body shall assess if criteria of EN 50388:2012, clause 10.4 are fulfilled. 6.2.4.5.    Assessment of dynamic behaviour and quality of current collection (integration into a subsystem) (1) The main goal of this test is to identify allocation design and construction errors but not to assess the basic design in principle. (2) Measurements of the interaction parameters shall be carried out in accordance with EN 50317:2012. (3) These measurements shall be carried out with an interoperability constituent pantograph, exhibiting the mean contact force characteristics as required by point 4.2.11 of this TSI for the design speed of the line considering aspects related to minimum speed and siding tracks. (4) The installed overhead contact line shall be accepted if the measurement results comply with the requirements in point 4.2.12. (5) For operational speeds up to 120 km/h (AC systems) and up to 160 km/h (DC systems), measurement of the dynamic behaviour is not mandatory. In this case alternative methods of identifying construction errors shall be used, such as measurement of OCL geometry according to point 4.2.9. (6) Assessment of dynamic behaviour and quality of current collection for integration of the pantograph into rolling stock subsystem are set out in point 6.2.3.20 of LOC & PAS TSI. 6.2.4.6.    Assessment of the protective provisions against electric shock (1) For each installation it shall be demonstrated that the basic design of protective provisions against electric shock is in accordance with point 4.2.18. (2) In addition the existence of rules and procedures which ensure that the installation is installed as designed shall be checked. 6.2.4.7.    Assessment of maintenance plan (1) The assessment shall be carried out by verifying the existence of the maintenance plan. (2) The notified body is not responsible for assessing the suitability of the detailed requirements set out in the plan. 6.3.    Sub-system containing interoperability constituents not holding an EC declaration 6.3.1.    Conditions (1) Until 31 May 2021, a notified body is allowed to issue an EC certificate of verification for a subsystem, even if some of the interoperability constituents incorporated within the subsystem are not covered by the relevant EC declarations of conformity and/or suitability for use according to this TSI, if the following criteria are complied with: (a) the conformity of the subsystem has been checked against the requirements of Section 4 and in relation to points 6.2 and 6.3 and Section 7, except point 7.4, of this TSI by the notified body. Furthermore the conformity of the ICs to Section 5 and point 6.1 does not apply, and (b) the interoperability constituents, which are not covered by the relevant EC declaration of conformity and/or suitability for use, have been used in a subsystem already approved and put in service in at least one of the Member State before the entry in force of this TSI. (2) EC Declarations of conformity and/or suitability for use shall not be drawn up for the interoperability constituents assessed in this manner. 6.3.2.    Documentation (1) The EC certificate of verification of the subsystem shall indicate clearly which interoperability constituents have been assessed by the notified body as part of the subsystem verification. (2) The EC declaration of verification of the subsystem shall indicate clearly: (a) which interoperability constituents have been assessed as part of the subsystem, (b) confirmation that the subsystem contains the interoperability constituents identical to those verified as part of the subsystem, (c) for those interoperability constituents, the reason(s) why the manufacturer did not provide an EC declaration of conformity and/or suitability for use before its incorporation into the subsystem, including the application of national rules notified under Article 17 of Directive 2008/57/EC. 6.3.3.    Maintenance of the subsystems certified according to 6.3.1 (1) During and after the transition period and until the subsystem is upgraded or renewed (taking into account the decision of Member State on application of TSIs), the interoperability constituents which do not hold an EC declaration of conformity and/or suitability for use and are of the same type are allowed to be used as maintenance related replacements (spare parts) for the subsystem, under the responsibility of the body responsible for maintenance. (2) In any case the body responsible for maintenance must ensure that the components for maintenance related replacements are suitable for their applications, are used within their area of use, and enable interoperability to be achieved within the rail system while at the same time meeting the essential requirements. Such components must be traceable and certified in accordance with any national or international rule, or any code of practice widely acknowledged in the railway domain. 7.   IMPLEMENTATION OF THE ENERGY TSI Member States shall develop a national plan for the implementation of this TSI, considering the coherence of the entire rail system of the European Union. This plan shall include all new, renewed and upgraded lines, in line with the details mentioned in points 7.1 to 7.4 here below. 7.1.    Application of this TSI to railway lines Sections 4 to 6 and any specific provisions in points 7.2 to 7.3 here below apply in full to the lines within the geographical scope of this TSI, which will be placed in service as interoperable lines after this TSI enters into force. 7.2.    Application of this TSI to new, renewed or upgraded railway lines 7.2.1.    Introduction (1) For the purpose of this section, a ‘new line’ means a line that creates a route where none currently exists. (2) The following situations may be considered as an upgrade or renewal of existing lines: (a) the realignment of part of an existing route; (b) the creation of a bypass; (c) the addition of one or more tracks on an existing route, regardless of the distance between the original tracks and the additional tracks. (3) In accordance with the conditions laid down in Article 20(1) of Directive 2008/57/EC, the implementation plan indicates the way existing fixed installations defined in point 2.1 shall be adapted when it is economically justified to do so. 7.2.2.    Implementation plan for voltage and frequency (1) The choice of power supply system is a Member State's competence. The decision should be taken on economic and technical grounds, taking into account at least the following elements: (a) the existing power supply system in the Member State; (b) any connection to railway line in neighbouring countries with an existing electrical power supply; (c) power demand. (2) New lines with speed greater than 250 km/h shall be supplied with one of the AC systems as defined in point 4.2.3. 7.2.3.    Implementation plan for OCL geometry 7.2.3.1.    Scope of the implementation plan Member States' implementation plan shall take into account the following elements: (a) closing gaps between different OCL geometries; (b) any connection to the existing OCL geometries in neighbouring areas; (c) existing certified ICs OCL. 7.2.3.2.    Implementation rules for 1 435 mm track gauge system The OCL shall be designed taking into account the following rules: (a) New lines with speed greater than 250 km/h shall accommodate both pantographs as specified in the LOC & PAS TSI points 4.2.8.2.9.2.1 (1 600 mm) and 4.2.8.2.9.2.2 (1 950 mm) . If this is not possible, the OCL shall be designed for use by at least a pantograph with the head geometry specified in the LOC & PAS TSI point 4.2.8.2.9.2.1 (1 600 mm) . (b) Renewed or upgraded lines with speed equal or greater than 250 km/h shall accommodate at least a pantograph with the head geometry specified in the LOC & PAS TSI point 4.2.8.2.9.2.1 (1 600 mm) . (c) Other cases: the OCL shall be designed for use by at least one of the pantographs with the head geometry specified in the LOC & PAS TSI points 4.2.8.2.9.2.1 (1 600 mm) or 4.2.8.2.9.2.2 (1 950 mm) . 7.2.3.3.    Track gauge systems different than 1 435mm The OCL shall be designed for use by at least one of the pantographs with the head geometry specified in the LOC & PAS TSI point 4.2.8.2.9.2. 7.2.4.    Implementation of the on-ground energy data collecting system Within 2 years after the ‘open point’ mentioned in point 4.2.17 is closed, Member States shall ensure that an on-ground energy data collecting system capable to exchange compiled energy billing data will be implemented. 7.3.    Application of this TSI to existing lines 7.3.1.    Introduction In case this TSI shall apply to existing lines and without prejudice to point 7.4 (specific cases), the following elements shall be considered: (a) Where Article 20(2) of Directive 2008/57/EC applies, Member States shall decide which requirements of the TSI shall apply, taking into account the implementation plan. (b) Where Article 20(2) of Directive 2008/57/EC does not apply, compliance with this TSI is recommended. Where compliance is not possible, the contracting entity informs the Member State of the reason thereof. (c) When a Member State requires a new authorisation for placing into service, the Contracting Entity shall define the practical measures and different phases of the project which are necessary to achieve the required levels of performance. These project phases may include transition periods for placing equipment into service with reduced levels of performance. (d) An existing subsystem may allow the circulation of TSI-compliant vehicles whilst meeting the essential requirements of Directive 2008/57/EC. The procedure to be used for the demonstration of the level of compliance with the basic parameters of the TSI shall be in accordance with Commission Recommendation 2011/622/EU  ( 4 ) . 7.3.2.    Upgrading/renewal of the OCL and/or the power supply (1) It is possible to gradually modify all or part of the OCL and/or the power supply system — element by element — over an extended period of time to achieve compliance with this TSI. (2) However, compliance of the entire subsystem can only be declared when all elements are compliant with the TSI over a complete section of route. (3) The process of upgrading/renewal should take into consideration the need of maintaining compatibility with the existing energy subsystem and other subsystems. For a project including elements not being TSI compliant, the procedures for the assessment of conformity and EC verification to be applied should be agreed with the Member State. 7.3.3.    Parameters related to maintenance While maintaining the energy subsystem, formal verifications and authorisations for placing into service are not required. However, maintenance replacements may be undertaken, as far as reasonably practicable, in accordance with the requirements of this TSI contributing to the development of interoperability. 7.3.4.    Existing subsystem that are not subject to a renewal or upgrading project The procedure to be used for the demonstration of the level of compliance of existing lines with the basic parameters of this TSI shall be in accordance with Commission Recommendation 2011/622/EU. 7.4.    Specific cases 7.4.1.    General (1) The specific cases, as listed in point 7.4.2, describe special provisions that are needed and authorised on particular networks of each Member State. (2) These specific cases are classified as: —    ‘P’ cases : ‘permanent’ cases, —    ‘T’ cases : ‘temporary’ cases, where it is planned that the target system is reached in the future. 7.4.2.    List of specific cases 7.4.2.1.    Particular features on the Estonian network 7.4.2.1.1.   Voltage and frequency (4.2.3) P case Maximum allowed voltage of overhead contact line in Estonia is 4 kV (3 kV DC networks). 7.4.2.2.    Particular features on the French network 7.4.2.2.1.   Voltage and frequency (4.2.3) T case The values and limits of the voltage and frequency at the terminals of the substation and at the pantograph of the 1,5 kV DC electrified lines: — Nimes to Port Bou, — Toulouse to Narbonne, may extend the values set out in EN50163:2004, clause 4 (U max2 close to 2 000 V). 7.4.2.2.2.   Phase separation sections — lines with speed v ≥ 250 km/h (4.2.15.2) P case In case of upgrading/renewal of high speed lines LN 1, 2, 3 and 4 special design of phase separation sections is allowed. 7.4.2.3.    Particular features on the Italian network 7.4.2.3.1.   Phase separation sections — lines with speed v ≥ 250 km/h (4.2.15.2) P case In case of upgrading/renewal of high speed line Rome-Naples special design of phase separation sections is allowed. 7.4.2.4.    Particular features on the Latvian network 7.4.2.4.1.   Voltage and frequency (4.2.3) P case Maximum allowed voltage of overhead contact line in Latvia is 4 kV (3 kV DC networks). 7.4.2.5.    Particular features on the Lithuanian network 7.4.2.5.1.   Dynamic behaviour and quality of current collection (4.2.12) P case For existing overhead contact line designs the space for steady arm uplift is calculated according to national technical rules notified for this purpose. 7.4.2.6.    Particular features on the Polish network 7.4.2.6.1.   Electrical protection coordination arrangements (4.2.7) P case For Polish DC 3 kV network the note c in the table 7 of the standard EN 50388: 2012 is replaced by note: The tripping of the circuit breaker should be very rapid for high short-circuits currents. As far as possible, the traction unit circuit breaker should trip in order to try to avoid the substation circuit breaker tripping. 7.4.2.7.    Particular features on the Spanish network 7.4.2.7.1.   Contact wire height (4.2.9.1) P case On some sections of the future lines v ≥ 250 km/h the nominal contact height is allowed 5,60 m. 7.4.2.7.2.   Phase separation sections — lines with speed v ≥ 250 km/h (4.2.15.2) P case In case of upgrading/renewal of existing high speed lines special design of phase separation sections shall be kept. 7.4.2.8.    Particular features on the Swedish network 7.4.2.8.1.   Assessment of mean useful voltage (6.2.4.1) P case Alternatively to assessment of mean useful voltage according to EN 50388:2012, clause 15.4, the power supply performance is also allowed to be assessed by: — A comparison with a reference where the power supply solution has been used for a similar or more demanding train schedule. The reference shall have a similar or larger: — distance to the voltage controlled bus bar (frequency converter station), — impedance of the OCL system. — A rough estimation of U mean useful for simple cases resulting in an increased additional capacity for future traffic demands. 7.4.2.9.    Particular features on the UK network for Great Britain 7.4.2.9.1.   Voltage and frequency (4.2.3) P case It is permissible to continue to upgrade, renew and extend networks equipped with the electrification system operating at 600/750 V DC and utilising conductor rails in a three and/or four rail configuration in accordance with the national technical rules notified for this purpose. Specific case for the United Kingdom of Great Britain and Northern Ireland, applying only to the mainline network in Great Britain. 7.4.2.9.2.   Contact wire height (4.2.9.1) P case For new, upgrade or renewal of the energy subsystem on existing infrastructure it is allowed to design the overhead contact line wire height in accordance with the national technical rules notified for this purpose. Specific case for the United Kingdom of Great Britain and Northern Ireland, applying only to the mainline network in Great Britain. 7.4.2.9.3.   Maximum lateral deviation (4.2.9.2) and pantograph gauge (4.2.10) P case For new, upgrade or renewal of the energy subsystem on existing infrastructure it is allowed to calculate the adjustment to the maximum lateral deviation, the verification heights, and pantograph gauge in accordance with the national technical rules notified for this purpose. Specific case for the United Kingdom of Great Britain and Northern Ireland, applying only to the mainline network in Great Britain. 7.4.2.9.4.   Protective provisions against electric shock (4.2.18) P case For upgrade or renewal of the existing energy subsystem or the construction of new energy subsystems on existing infrastructure, in place of the reference to EN50122-1:2011+A1:2011 clause 5.2.1, it is allowed to design the protective provisions against electric shock in accordance with the national technical rules notified for this purpose. Specific case for the United Kingdom of Great Britain and Northern Ireland, applying only to the mainline network in Great Britain. 7.4.2.9.5.   Conformity assessment of OCL as component P case The national rules may define the procedure for conformity related to points 7.4.2.9.2 and 7.4.2.9.3 and associated certificates. The procedure may include the conformity assessment of parts which are not subject to a specific case. 7.4.2.10.    Particular features on the Eurotunnel network 7.4.2.10.1.   Contact wire height (4.2.9.1) P case For, upgrade or renewal of the existing energy subsystem it is allowed for the overhead contact line wire height to be designed in accordance with the technical rules notified for this purpose. 7.4.2.11.    Particular features on the Luxembourgish network 7.4.2.11.1.   Voltage and frequency (4.2.3) T case The values and limits of the voltage and frequency at the terminals of the substation and at the pantograph of the following 25 kV AC electrified lines between Bettembourg to Rodange (frontier) and the line section between Pétange and Leudelange may exceed the values set out in EN50163:2004, clause 4 (U max1 close to 30 kV and U max2 close to 30,5 kV). ( 1 )   Taking into account tolerances and uplift in accordance with EN 50119:2009 figure 1, the maximum contact wire height shall not be greater than 6 500 mm. ( 2 )   The values shall be adjusted taking into account the movement of the pantograph and track tolerances according to Appendix D.1.4. ( 3 )   i.e. the speed of the two types of pantograph shall be at least equal to the design speed of the simulated overhead contact line. ( 4 )   Commission Recommendation 2011/622/EU of 20 September 2011 on the procedure demonstrating the level of compliance of existing railway lines with the basic parameters of the technical specifications for interoperability ( OJ L 243, 21.9.2011, p. 23 )