Maximum financial contribution

Article 11

1.   The maximum financial contribution shall be calculated for each Member State as follows: (a) for 70 % of the amount referred to in point (a) of Article 6(1), converted into current prices, on the basis of the population, the inverse of the GDP per capita and the relative unemployment rate of each Member State as set out in the methodology in Annex II; (b) for 30 % of the amount referred to in point (a) of Article 6(1), converted into current prices, on the basis of the population, the inverse of the GDP per capita and, in equal proportion, the change in real GDP in 2020 and the aggregated change in real GDP for the period 2020-2021 as set out in the methodology in Annex III. The change in real GDP for 2020 and the aggregated change in real GDP for the period 2020-2021 shall be based on the Commission Autumn 2020 forecasts. 2.   The calculation of the maximum financial contribution under point (b) of paragraph 1 shall be updated by 30 June 2022 for each Member State by replacing the data from the Commission Autumn 2020 forecasts with the actual outturns in relation to the change in real GDP 2020 and the aggregated change in real GDP for the period 2020-2021.

Allocation of financial contribution

Article 12

1.   Each Member State may submit a request up to its maximum financial contribution, referred to in Article 11, to implement its recovery and resilience plan. 2.   Until 31 December 2022, the Commission shall make available for allocation 70 % of the amount referred to in point (a) of Article 6(1), converted into current prices. 3.   From 1 January 2023 until 31 December 2023, the Commission shall make available for allocation 30 % of the amount referred to in point (a) of Article 6(1), converted into current prices. 4.   The allocations under paragraphs 2 and 3 are without prejudice to Article 6(2).

Pre-financing

Article 13

1.   Subject to the adoption by 31 December 2021 by the Council of the implementing decision referred to in Article 20(1), and when requested by a Member State together with the submission of its recovery and resilience plan, the Commission shall make a pre-financing payment of an amount of up to 13 % of the financial contribution and, where applicable, of up to 13 % of the loan as set out in Article 20(2) and (3). By derogation from Article 116(1) of the Financial Regulation, the Commission shall make the corresponding payment within, to the extent possible, two months after the adoption by the Commission of the legal commitment referred to in Article 23. 2.   In cases of pre-financing under paragraph 1 of this Article, the financial contributions and, where applicable, the loan to be paid as referred to in point (a) or point (h) of Article 20(5), respectively, shall be adjusted proportionally. 3.   If the amount of pre-financing of the financial contribution under paragraph 1 of this Article exceeds 13 % of the maximum financial contribution calculated in accordance with Article 11(2) by 30 June 2022, the next payment authorised in accordance with Article 24(5), and if needed the following payments, shall be reduced until the excess amount is offset. If the remaining payments are insufficient, the excess amount shall be returned.

Loans

Article 14

1.   Until 31 December 2023, upon request from a Member State, the Commission may grant the Member State concerned a loan for the implementation of its recovery and resilience plan. 2.   A Member State may request loan support at the time of the submission of a recovery and resilience plan referred to in Article 18, or at a different moment in time until 31 August 2023. In the latter case, the request shall be accompanied by a revised recovery and resilience plan, including additional milestones and targets. 3.   The request for loan support by a Member State shall set out: (a) the reasons for the loan support, justified by the higher financial needs linked to additional reforms and investments; (b) the additional reforms and investments in line with Article 18; (c) the higher cost of the recovery and resilience plan concerned compared to the amount of the financial contributions allocated to the recovery and resilience plan respectively pursuant to point (a) or (b) of Article 20(4). 4.   The loan support to the recovery and resilience plan of the Member State concerned shall not be higher than the difference between the total costs of the recovery and resilience plan, as revised where relevant, and the maximum financial contribution referred to in Article 11. 5.   The maximum volume of the loan support for each Member State shall not exceed 6,8 % of its 2019 GNI in current prices. 6.   By derogation from paragraph 5, subject to the availability of resources, in exceptional circumstances the amount of the loan support may be increased. 7.   The loan shall be paid in instalments subject to the fulfilment of milestones and targets in line with Article 20(5)(h). 8.   The Commission shall assess the request for loan support in accordance with Article 19. The Council shall adopt an implementing decision, on a proposal from the Commission, in accordance with Article 20(1). Where appropriate, the recovery and resilience plan shall be amended accordingly.

Loan agreement

Article 15

1.   Before entering into a loan agreement with the Member State concerned, the Commission shall assess whether: (a) the justification for requesting the loan support and its amount is considered reasonable and plausible in relation to the additional reforms and investments; and (b) the additional reforms and investments comply with the criteria set out in Article 19(3). 2.   Where the Commission considers that the request for loan support fulfils the criteria of paragraph 1, and upon adoption of the Council implementing decision referred to in Article 20(1), the Commission shall enter into a loan agreement with the Member State concerned. The loan agreement, in addition to the elements laid down in Article 220(5) of the Financial Regulation, shall contain the following elements: (a) the amount of the loan in euro including, where applicable, the amount of the pre-financed loan in accordance with Article 13; (b) the average maturity; Article 220(2) of the Financial Regulation shall not apply with regard to this maturity; (c) the pricing formula and the availability period of the loan; (d) the maximum number of instalments and the repayment schedule; (e) the other elements needed for the implementation of the loan in relation to the reforms and the investment projects concerned in line with the decision referred to in Article 20(3). 3.   In accordance with point (e) of Article 220(5) of the Financial Regulation, costs related to the borrowing of funds for the loans referred to in this Article shall be borne by the beneficiary Member States. 4.   The Commission shall establish the necessary arrangements for the administration of the lending operations related to loans granted in accordance with this Article. 5.   A Member State benefitting from a loan granted in accordance with this Article shall open a dedicated account for the management of the loan received. It shall also transfer the principal and the interest due on any related loan to an account indicated by the Commission in line with the arrangements put in place in accordance with paragraph 4 twenty business days before the corresponding due date.

Review report

Article 16

1.   By 31 July 2022, the Commission shall present to the European Parliament and the Council a review report on the implementation of the Facility. 2.   The review report shall set out the following elements: (a) an assessment of the extent to which the implementation of the recovery and resilience plans is in line with the scope and contributes to the general objective of this Regulation in line with the six pillars referred to in Article 3, including how the recovery and resilience plans tackle the inequalities between women and men; (b) a quantitative assessment of the contribution of the recovery and resilience plans to: (i) the climate target of at least 37 %, (ii) the digital target of at least 20 %, (iii) each of the six pillars referred to in Article 3; (c) the state of the implementation of the recovery and resilience plans and observations and guidance to the Member States before the update of their recovery and resilience plans referred to in Article 18(2). 3.   For the purposes of the review report referred to in paragraph 1 of this Article, the Commission shall take into account the scoreboard referred to in Article 30, the reports of the Member States referred to in Article 27 and any other relevant information on the fulfilment of the milestones and targets of the recovery and resilience plans as available from the payment, suspension and termination procedures referred to in Article 24. 4.   The competent committee of the European Parliament may invite the Commission to present the main findings of the review report in the context of the recovery and resilience dialogue referred to in Article 26.

Back to Regulation (EU) 2021/241 — full text

Articles on this page are reproduced verbatim from official open data. See the attribution line.

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

What to look at next