Council Decision (CFSP) 2023/927 of 5 May 2023 on an assistance measure under the European Peace Facility to support the Ukrainian Armed Forces through the provision of ammunition

Council Decision (CFSP) 2023/927 of 5 May 2023 on an assistance measure under the European Peace Facility to support the Ukrainian Armed Forces through the provision of ammunition

Decision (CFSP) 2023/927 · Decision · 9 articles

Data as of 2026-07-04 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Establishment, objectives, scope and duration

Article 1

Open ↗

1.   An assistance measure benefitting Ukraine (‘the beneficiary’) to be financed under the European Peace Facility (EPF) (‘the assistance measure’) is hereby established. 2.   The objective of the assistance measure is to contribute to strengthening the capabilities and resilience of the Ukrainian Armed Forces to defend the independence, sovereignty and territorial integrity of Ukraine, and protect the civilian population against the ongoing military aggression, through the provision of 155-mm-calibre artillery rounds and, if requested, missiles, jointly procured from the European defence industry in the fastest way possible. 3.   To achieve the objective set out in paragraph 2, the assistance measure shall finance the provision to the Ukrainian Armed Forces of 155-mm-calibre artillery rounds, and, if requested, missiles. Such ammunition and missiles shall be jointly procured from economic operators established in the Union or Norway and producing these ammunitions and missiles in the Union or Norway. The rules of origin laid down in Article 60 of Regulation (EU) No 952/2013 shall apply. Ammunitions and missiles which have undergone an important stage of manufacture in the Union or Norway which consists of final assembly shall also be deemed eligible. Supply chains of these operators may include operators established or having their production outside of the Union or Norway. The security and defence interests of the Member States shall be taken into account in this regard. The joint procurements made under this assistance measure shall be carried out by the entities listed in Article 4(3) within the parameters defined in the context of an existing European Defence Agency project or through complementary joint acquisition projects led by a Member State. 4.   The duration of the assistance measure shall be 56 months from the date of adoption of this Decision.

Financial arrangements

Article 2

Open ↗

1.   The financial reference amount intended to cover the expenditure related to the assistance measure shall be EUR 1 000 000 000. 2.   All expenditure shall be managed in accordance with Decision (CFSP) 2021/509 and the rules for the implementation of revenue and expenditure financed under the EPF (‘the EPF implementing rules’), including the rules on the origin of military equipment. By way of derogation from Article 50 of Book 3 of the EPF implementing rules, participation in joint procurement procedures shall be open only to economic operators as referred to in Article 1(3). 3.   In accordance with Article 29(5) of Decision (CFSP) 2021/509, the administrator for assistance measures may call for contributions following the adoption of this Decision, up to EUR 1 000 000 000. The funds called by the administrator for assistance measures shall only be used to pay expenditure within the limits approved by the Committee established by Decision (CFSP) 2021/509 in the related amending and annual budgets corresponding to the assistance measure. 4.   Procurement contracts or purchase orders related to the implementation of the assistance measure shall be concluded in the fastest way possible between 20 March 2023 and 30 September 2023. Related expenditure shall be eligible from 20 March 2023 and until a date to be determined by the Council.

Arrangements with the beneficiary

Article 3

Open ↗

1.   The High Representative shall make the necessary arrangements with the beneficiary to ensure its compliance with international law, in particular international human rights and international humanitarian law, and Article 62(2) of Decision (CFSP) 2021/509, as a condition for the provision of support under the assistance measure. 2.   The arrangements referred to in paragraph 1 shall include provisions on the suspension and termination of support under the assistance measure in the event of the beneficiary being found in breach of the obligations referred to in paragraph 1.

Implementation

Article 4

Open ↗

1.   The High Representative shall be responsible for ensuring the implementation of this Decision in accordance with Decision (CFSP) 2021/509 and the EPF implementing rules, in line with the Integrated Methodological Framework for assessing and identifying the required measures and controls for assistance measures under the EPF. 2.   The specifications of the 155-mm-calibre artillery rounds and missiles to be provided under the assistance measure shall correspond to the priorities communicated by Ukraine via the EU Military Staff. The Committee established by Decision (CFSP) 2021/509 shall decide on the framework applicable to the financing of the activities outlined in Article 1(3) and on the arrangements for reimbursement, where appropriate. 3.   The implementation of the activities referred to in Article 1(3) may be carried out by the following: (a) the Ministry of Defence of Belgium; (b) the Ministry of Defence of Bulgaria; (c) the Ministry of Defence of Croatia; (d) the Ministry of Defence of Cyprus; (e) the Ministry of Defence of the Czech Republic; (f) the Ministry of Defence of Denmark; (g) the Estonian Centre for Defence Investments (ECDI) on behalf of the Ministry of Defence of Estonia; (h) the Ministry of Defence of Finland; (i) the Ministry of Defence of France; (j) the Ministry of Defence, the Federal Foreign Office and the Federal Ministry of the Interior and Community of Germany; (k) the Ministry of Defence of Greece; (l) the Ministry of Defence of Italy; (m) the Ministry of Defence of Latvia and the State Defence Logistics and Procurement Centre of Latvia; (n) the Ministry of National Defence of Lithuania; (o) the Directorate of Defence of the Ministry of Foreign and European Affairs of Luxembourg; (p) the Ministry of Defence of the Netherlands; (q) the Ministry of Defence of Poland; (r) the Ministry of Defence of Portugal; (s) the Ministry of National Defence of Romania; (t) the Ministry of Defence of the Slovak Republic; (u) the Ministry of Defence of Slovenia; (v) the Ministry of Defence of Spain; (w) the Ministry of Defence of Sweden/the Swedish Defence Materiel Administration.

Support by Member States

Article 5

Open ↗

The Member States shall permit the transit of 155-mm-calibre artillery rounds and missiles, including accompanying personnel, through their territories, including their airspace, in a manner consistent with Article 56(3) of Decision (CFSP) 2021/509.

Monitoring, control and evaluation

Article 6

Open ↗

1.   The High Representative shall monitor the compliance by the beneficiary with the obligations set out in Article 3. This monitoring shall be used to provide awareness of the context and the risks of breaches of the obligations established in accordance with Article 3, and to contribute to the prevention of such breaches, including violations of international human rights law and international humanitarian law by units of the Ukrainian Armed Forces supported under the assistance measure. 2.   The post-shipment control of equipment shall be organised in a manner consistent with the Integrated Methodological Framework for assessing and identifying the required measures and controls for assistance measures under the EPF.

Reporting

Article 7

Open ↗

During the period of implementation, the High Representative shall provide the Political and Security Committee (PSC) with six-monthly reports on the implementation of the assistance measure, in accordance with Article 63 of Decision (CFSP) 2021/509. This will be supplemented by regular monthly updates to the Council on the implementation of the assistance measure including on the progress made towards achieving its objective, based on information, provided by the Member States, on deliveries of 155-mm-calibre artillery rounds, and if requested, missiles. The administrator for assistance measures shall regularly inform the Facility Committee established by Decision (CFSP) 2021/509 on the implementation of revenue and expenditure in accordance with Article 38 of that Decision, including by providing information on the suppliers and subcontractors involved.

Suspension and termination

Article 8

Open ↗

1.   The PSC may decide to suspend wholly or partially the implementation of the assistance measure in accordance with Article 64 of Decision (CFSP) 2021/509. 2.   The PSC may also recommend that the Council terminate the assistance measure.

Entry into force

Article 9

Open ↗

This Decision shall enter into force on the date of its adoption. It shall apply from 20 March 2023.

Other acts of the same type
Council Decision (EU) 2019/477 of 12 March 2019 on the conclusion of a Protocol to the Euro-Mediterranean Agreement establishing an Association between the European Communities and their Member States, of the one part, and the Hashemite Kingdom of Jordan, of the other part, to take account of the accession of the Republic of Bulgaria and Romania to the European UnionCouncil Decision (EU) 2019/393 of 7 March 2019 on the signing, on behalf of the European Union, of the Protocol between the European Union, the Swiss Confederation and the Principality of Liechtenstein to the Agreement between the European Community and the Swiss Confederation concerning the criteria and mechanisms for establishing the State responsible for examining a request for asylum lodged in a Member State or in Switzerland regarding access to Eurodac for law enforcement purposesCouncil Decision (EU) 2019/394 of 7 March 2019 on the signing, on behalf of the European Union, of the Protocol between the European Union, Iceland and the Kingdom of Norway to the Agreement between the European Community and the Republic of Iceland and the Kingdom of Norway concerning the criteria and mechanisms for establishing the State responsible for examining a request for asylum lodged in a Member State or in Iceland or Norway regarding access to Eurodac for law enforcement purposesCouncil Decision (EU) 2019/395 of 7 March 2019 on the signing, on behalf of the European Union, of the Protocol to the Agreement between the European Community and the Kingdom of Denmark on the criteria and mechanisms for establishing the State responsible for examining a request for asylum lodged in Denmark or any other Member State of the European Union and ‘Eurodac’ for the comparison of fingerprints for the effective application of the Dublin Convention regarding access to Eurodac for law enforcement purposesCouncil Decision (EU) 2019/399 of 7 March 2019 on the position to be taken on behalf of the European Union in the relevant Committees of the United Nations Economic Commission for Europe as regards the proposals for modifications to UN Regulations Nos 0, 3, 4, 6, 7, 9, 10, 19, 23, 27, 38, 41, 48, 50, 51, 53, 55, 58, 62, 67, 69, 70, 73, 74, 77, 86, 87, 91, 92, 98, 104, 106, 107, 110, 112, 113, 116, 119, 122, 123 and 128, the proposal for an amendment to the Consolidated Resolution R.E.5, the proposals for four new UN Regulations, and the proposal for an amendment to Schedule 4 of the Revised 1958 AgreementCouncil Decision (EU) 2019/485 of 5 March 2019 on the conclusion of the relevant Agreements under Article XXI of the General Agreement on Trade in Services with Argentina Australia Brazil Canada China the Separate customs territory of Taiwan Penghu Kinmen and Matsu (Chinese Taipei) Colombia Cuba Ecuador Hong Kong China India Japan Korea New Zealand the Philippines Switzerland and the United States on the necessary compensatory adjustments resulting from the accession of Czechia Estonia Cyprus Latvia Lithuania Hungary Malta Austria Poland Slovenia Slovakia Finland and Sweden to the European UnionCouncil Implementing Decision (CFSP) 2019/351 of 4 March 2019 implementing Decision 2013/255/CFSP concerning restrictive measures against SyriaCouncil Decision (CFSP) 2019/354 of 4 March 2019 amending Decision 2014/119/CFSP concerning restrictive measures directed against certain persons, entities and bodies in view of the situation in UkraineCouncil Decision (EU) 2019/380 of 4 March 2019 on the position to be adopted, on behalf of the European Union, within the EEA Joint Committee concerning the amendment of Annex IX (Financial services) and Annex XIX (Consumer protection) to the EEA Agreement (Text with EEA relevance.)Council Decision (EU) 2019/381 of 4 March 2019 on the position to be adopted, on behalf of the European Union, within the EEA Joint Committee concerning the amendment of Annex II (Technical regulations, standards, testing and certification) and Annex XI (Electronic communication, audiovisual services and information society) to the EEA Agreement (Text with EEA relevance.)Council Decision (EU) 2019/385 of 4 March 2019 on the conclusion of the Protocol on the implementation of the Fisheries Partnership Agreement between the European Union and the Republic of Côte d'Ivoire (2018-2024)Council Decision (EU) 2019/389 of 4 March 2019 on the position to be adopted, on behalf of the European Union, within the EEA Joint Committee, concerning the amendment of Annex IX (Financial Services) to the EEA Agreement (Markets in Financial Instruments Regulation (MiFIR) and Directive MiFID II) (Text with EEA relevance.)

Source: EUR-Lex (Publications Office of the EU), © European Union, reuse permitted under Commission Decision 2011/833/EU.

Contents

What to look at next