Principles governing the Fund
1. The Fund shall provide financial support to Member States to fund the measures and investments set out in their Plans.
2. Payment of financial support pursuant to paragraph 1 of this Article to each Member State shall be conditional upon that Member State achieving the milestones and targets for the measures and investments in accordance with Article 8 of this Regulation. Those milestones and targets shall be compatible with the Union’s climate targets and the objective set out in Regulation (EU) 2021/1119, and shall cover in particular:
(a)
energy efficiency;
(b)
building renovation;
(c)
zero- and low-emission mobility and transport;
(d)
greenhouse gas emission reductions;
(e)
reductions in the number of vulnerable households, in particular households in energy poverty, of vulnerable micro-enterprises and of vulnerable transport users.
3. The Fund shall only support measures and investments which comply with the principle of ‘do no significant harm’ within the meaning of Article 17 of Regulation (EU) 2020/852.
4. The measures and investments supported by the Fund shall reduce fossil fuel dependency and, where relevant, contribute to the implementation of the European Pillar of Social Rights as well as to sustainable and quality jobs in the fields covered by the measures and investments of the Fund.
Eligible measures and investments to be included in the Social Climate Plans
1. The Member State may include in the estimated total costs of the Plan the following measures and investments with lasting impacts, provided they principally target vulnerable households, vulnerable micro-enterprises or vulnerable transport users and intend to:
(a)
support building renovations, in particular for vulnerable households and vulnerable micro-enterprises occupying the worst performing buildings, and including for tenants and people living in social housing;
(b)
support access to affordable energy-efficient housing, including social housing;
(c)
contribute to the decarbonisation, such as through electrification, of heating and cooling of, and cooking in, buildings by providing access to affordable and energy-efficient systems, and by integrating renewable energy generation and storage, including through renewable energy communities, citizen energy communities and other active customers to promote the uptake of the self-consumption of renewable energy, such as energy sharing and peer-to-peer trading of renewable energy, connection to smart grids and to district heating networks, that contributes to achieving energy savings or to reducing energy poverty;
(d)
provide targeted, accessible and affordable information, education, awareness and advice on cost-effective measures and investments, available support for building renovations and energy efficiency, as well as sustainable and affordable mobility and transport alternatives;
(e)
support public and private entities, including social housing providers, in particular public-private cooperatives, in developing and providing affordable energy efficiency solutions and appropriate funding instruments in line with the social goals of the Fund;
(f)
provide access to zero- and low-emission vehicles and bicycles, while maintaining technological neutrality, including financial support or fiscal incentives for their purchase as well as for appropriate public and private infrastructure, in particular, where relevant, purchase of zero- and low-emission vehicles, infrastructure for recharging and refuelling and development of a second-hand zero-emission vehicles market; Member States shall aim to ensure that where zero-emission vehicles are an affordable and deployable solution, support to such vehicles is prioritised in their Plans;
(g)
incentivise the use of affordable and accessible public transport and support private and public entities, including cooperatives, in developing and providing sustainable mobility on demand, shared mobility services and active mobility options.
2. Member States may include in the estimated total costs of the Plans the costs of measures providing direct income support to vulnerable households and vulnerable transport users to reduce the impact of the increase in road transport and heating fuel prices. Such support shall be temporary and decrease over time. Member States may provide temporary direct income support if their Plans contain measures or investments aimed at those vulnerable households and vulnerable transport users in accordance with Article 8(1) of this Regulation. Such support shall be limited to the direct impact of the inclusion of greenhouse gas emissions from buildings and road transport within the scope of Directive 2003/87/EC. The costs of measures providing temporary direct income support shall not represent more than 37,5 % of the estimated total costs of the Plan, as referred to in Article 6(1), point (j), of this Regulation.
3. Member States may include in the estimated total costs of the Plans the costs of technical assistance to cover expenses related to training, programming, monitoring, control, audit and evaluation activities which are required for the management of the Fund and the achievement of its objectives, for example studies, information technology (IT) expenses, public consultation of stakeholders, information and communication actions. The costs of such technical assistance shall be up to 2,5 % of the estimated total costs of the Plan, as referred to in Article 6(1), point (j).
Pass-on of benefits to households, micro-enterprises and transport users
1. Member States may include in the Plans support provided through public or private entities other than vulnerable households, vulnerable micro-enterprises and vulnerable transport users, provided that those entities carry out measures and investments ultimately benefitting vulnerable households, vulnerable micro-enterprises or vulnerable transport users.
2. Member States shall provide for the necessary statutory and contractual safeguards to ensure that the entire benefit is passed on to the vulnerable households, vulnerable micro-enterprises or vulnerable transport users.
Resources of the Fund
1. A maximum amount of EUR 65 000 000 000 for the period from 1 January 2026 to 31 December 2032 in current prices shall be made available, in accordance with Articles 10a(8b), 30d(3) and 30d(4) of Directive 2003/87/EC, for implementation of the Fund. That amount shall constitute external assigned revenue for the purposes of Article 21(5) of Regulation (EU, Euratom) 2018/1046, without prejudice to Article 30d(4), sixth subparagraph, of Directive 2003/87/EC.
The annual amounts allocated to the Fund, within the limit of the maximum amount laid down in the first subparagraph of this paragraph, shall not exceed the amounts referred to in Article 30d(4), fourth subparagraph, of Directive 2003/87/EC.
Where the emission trading system established in accordance with Chapter IVa of Directive 2003/87/EC is postponed until 2028 pursuant to Article 30k of that Directive, the maximum amount to be made available to the Fund shall be EUR 54 600 000 000 and the annual amounts allocated to the Fund shall not exceed the respective amounts referred to in the Article 30d(4), fifth subparagraph, of Directive 2003/87/EC.
2. By way of derogation from Article 22(2) of Regulation (EU, Euratom) 2018/1046 and without prejudice to Article 19 of this Regulation, commitment appropriations covering the relevant maximum amount referred to in paragraph 1 of this Article shall be made available automatically at the beginning of each financial year, starting from 1 January 2026, up to the relevant applicable annual amounts referred to in the second and third subparagraphs of paragraph 1.
3. The amounts referred to in paragraph 1 may also cover expenses pertaining to preparatory, monitoring, control, audit and evaluation activities which are required for the management of the Fund and the achievement of its objectives, in particular studies, meetings of experts, consultation of stakeholders, information and communication actions, including inclusive outreach actions, and corporate communication of the political priorities of the Union, insofar as they are related to the objectives of this Regulation, expenses linked to IT networks focusing on information processing and exchange, corporate IT tools, and all other technical and administrative assistance expenses incurred by the Commission for the management of the Fund. Expenses may also cover the costs of other supporting activities such as quality control and monitoring of projects on the ground and the costs of peer counselling and experts for the assessment and implementation of the eligible actions.
Resources from and to shared management programmes and use of resources
1. Resources allocated to Member States under shared management may, at their request, be transferred to the Fund subject to the conditions set out in the relevant provisions of Regulation (EU) 2021/1060. The Commission shall implement those resources directly in accordance with Article 62(1), first subparagraph, point (a), of Regulation (EU, Euratom) 2018/1046. Those resources shall be used exclusively for the benefit of the Member State concerned.
2. Member States may request in their Plans submitted in accordance with Article 4(1) of this Regulation for the transfer of up to 15 % of their maximum annual financial allocation to the funds under shared management provided for in Regulation (EU) 2021/1060. The transferred resources shall finance measures and investments as referred to in Article 8 of this Regulation and shall be implemented in accordance with the rules of the funds to which the resources are transferred. Resources shall be transferred by Member States through the amendment of one or more programmes, except for programmes under the European territorial cooperation goal (Interreg), in accordance with Article 26a of Regulation (EU) 2021/1060, and shall be implemented in accordance with the rules set out in that Regulation and the rules of the funds to which the resources are transferred.
3. Member States may entrust the managing authorities of the cohesion policy programmes under Regulation (EU) 2021/1060 with the implementation of measures and investments benefitting from the Fund, where applicable, in view of the synergies with those cohesion policy programmes and in conformity with the objectives of the Fund. Member States shall state their intention to thus entrust those authorities in their Plans. In such cases, the existing management and control systems put in place by Member States, as notified to the Commission, shall be deemed to comply with the requirements of this Regulation.
4. Member States may include in their Plans, as part of the estimated total costs, the payments for additional technical support pursuant to Article 7 of Regulation (EU) 2021/240 and the amount of the cash contribution for the purpose of the Member State compartment pursuant to the relevant provisions of Regulation (EU) 2021/523 of the European Parliament and of the Council ( 31 ) . Those costs shall not exceed 4 % of the maximum financial allocation for the Plan, and the relevant measures, as set out in the Plan, shall comply with this Regulation.
Implementation
The Fund shall be implemented by the Commission under direct management in accordance with the relevant rules adopted pursuant to Article 322 TFEU, in particular Regulation (EU, Euratom) 2018/1046 and Regulation (EU, Euratom) 2020/2092 on a general regime of conditionality for the protection of the Union budget.
Additionality and complementary funding
1. Support under the Fund shall be additional to the support provided under other Union funds, programmes and instruments. Measures and investments supported under the Fund may receive support from other Union funds, programmes and instruments provided that such support does not cover the same cost.
2. Support from the Fund, including temporary direct income support referred to in Article 4(3), shall be additional and shall not substitute recurring national budgetary expenditure.
3. For technical assistance to Member States, administrative costs directly linked to the implementation of the Plan shall not be considered as recurring national budgetary expenditure.
Maximum financial allocation
1. The maximum financial allocation shall be calculated for each Member State in accordance with Article 10 and as specified in Annexes I and II.
2. Each Member State may submit a request up to its maximum financial allocation to implement its Plan.
National contribution to the estimated total costs
Member States shall contribute at least to 25 % of the estimated total costs of their Plans.
Commission assessment
1. The Commission shall assess the Plan and, where applicable, any amendment to that Plan submitted by a Member State in accordance with Article 18, for compliance with this Regulation. When carrying out that assessment, the Commission shall act in close cooperation with the Member State concerned. The Commission may make observations or seek additional information within two months from the date of submission of the Plan by the Member State. The Member State shall provide the requested additional information and may revise the Plan if needed, including after the submission of the Plan. The Member State and the Commission may agree to extend the deadline for assessment by a reasonable period if necessary.
2. The Commission shall assess whether transfers requested in accordance with Article 11 meet the objectives of this Regulation.
3. The Commission shall assess the relevance, effectiveness, efficiency and coherence of the Plan, taking into account the specific challenges and the financial allocation of the Member State, as follows:
(a)
for the purpose of assessing relevance, the Commission shall take into account the following criteria:
(i)
whether the Plan represents an adequate response to the social impact on and challenges faced by vulnerable households, vulnerable micro-enterprises and vulnerable transport users in the Member State concerned from the inclusion of greenhouse gas emissions from buildings and road transport within the scope of Directive 2003/87/EC, in particular households in energy poverty or households in transport poverty, duly taking into account the challenges identified in the assessments of the Commission of the update of the concerned Member State’s integrated national energy and climate plan and of its progress pursuant to Article 9(3), and Articles 13 and 29 of Regulation (EU) 2018/1999, as well as in the Commission recommendations to Member States issued pursuant to Article 34 of Regulation (EU) 2018/1999 in view of the Union’s 2030 climate and energy targets and long-term objective of climate neutrality in the Union at the latest by 2050;
(ii)
whether the Plan is expected to ensure that measures and investments included in the Plan do not significantly harm environmental objectives within the meaning of Article 17 of Regulation (EU) 2020/852 and whether the Plan helps reduce fossil fuel dependency;
(iii)
whether the Plan contains measures and investments that contribute to the green transition, including to addressing the social impacts and challenges resulting therefrom and in particular to the achievement of the Union’s 2030 climate and energy targets and long-term objective of climate neutrality in the Union at the latest by 2050 and the 2030 milestones of the Union’s Sustainable and Smart Mobility Strategy;
(b)
for the purpose of assessing effectiveness, the Commission shall take into account the following criteria:
(i)
whether the Plan is expected to have a lasting impact in the Member State on the challenges addressed by that Plan, in line with the Union’s 2030 climate and energy targets and long-term objective of climate neutrality in the Union at the latest by 2050, and in particular on vulnerable households, vulnerable micro-enterprises and vulnerable transport users, in particular households in energy poverty or households in transport poverty;
(ii)
whether the arrangements proposed by the Member State are expected to ensure the effective monitoring and implementation of the Plan, including the envisaged timetable, milestones and targets, and the related indicators;
(iii)
whether the measures and investments proposed by the Member State are consistent and compliant with the requirements of the Directive of the European Parliament and of the Council on energy efficiency (recast), Directive (EU) 2018/2001, the Regulation of the European Parliament and of the Council on the deployment of alternative fuels infrastructure, and repealing Directive 2014/94/EU of the European Parliament and of the Council, Directive 2009/33/EC of the European Parliament and of the Council ( 32 ) and Directive 2010/31/EU; and
(iv)
whether the measures and investments proposed by the Member State foster complementarity, synergy, coherence and consistency with the Union instruments referred to in Article 6(3).
(c)
for the purposes of assessing efficiency, the Commission shall take into account the following criteria:
(i)
whether the justification provided by the Member State for the amount of the estimated total costs of the Plan is reasonable, plausible, in line with the principle of cost efficiency and commensurate with the expected national environmental and social impact, while also taking into account national specificities that could impact the costs provided in the Plan;
(ii)
whether the arrangements proposed by the Member State are expected to prevent, detect and correct corruption, fraud and conflicts of interests when using the financial allocation provided under the Fund, including the arrangements that aim to avoid double funding from the Fund and other Union programmes;
(iii)
whether the milestones and targets proposed by the Member State are efficient, in view of the scope, objectives and eligible actions of the Fund;
(d)
for the purpose of assessing coherence, the Commission shall take into account whether the Plan contains measures and investments that represent coherent actions.
Commission decision
1. On the basis of the assessment carried out in accordance with Article 16, the Commission shall decide on the Plan of a Member State, by means of an implementing act, no later than five months from the date of the submission of that Plan pursuant to Article 4(1).
2. Where the Commission gives a positive assessment of a Plan, the implementing act referred to in paragraph 1 shall set out:
(a)
the measures and investments to be implemented by the Member State, the amount of the estimated total costs of the Plan, and the milestones and targets;
(b)
the maximum financial allocation allocated in accordance with Article 14(1) to be paid in instalments, in accordance with Article 20, once the Member State has satisfactorily achieved the relevant milestones and targets identified in relation to the implementation of the Plan;
(c)
the national contribution;
(d)
the arrangements and timetable for monitoring and implementation of the Plan, including, where relevant, measures necessary for complying with Article 21;
(e)
the relevant indicators relating to the achievement of the envisaged milestones and targets; and
(f)
the arrangements for providing access by the Commission to the underlying relevant data.
3. The maximum financial allocation referred to in paragraph 2, point (b), of this Article shall be determined on the basis of the estimated total costs of the Plan proposed by the Member State, as assessed by reference to the criteria set out in Article 16(3).
The amount of the maximum financial allocation referred to in paragraph 2, point (b), of this Article shall be set as follows:
(a)
where the Plan complies satisfactorily with the criteria set out in Article 16(3), and the amount of the estimated total costs of the Plan minus the national contribution is equal to, or higher than, the maximum financial allocation for that Member State referred to in Article 14(1), the financial allocation allocated to the Member State shall be equal to the total amount of the maximum financial allocation referred to in Article 14(1);
(b)
where the Plan complies satisfactorily with the criteria set out in Article 16(3), and the amount of the estimated total costs of the Plan minus the national contribution is lower than the maximum financial allocation for that Member State referred to in Article 14(1), the financial allocation allocated to the Member State shall be equal to the amount of the estimated total costs of the Plan minus the national contribution;
(c)
where the Plan complies satisfactorily with the criteria set out in Article 16(3), but the assessment identifies weaknesses in the internal control systems, the Commission may require that additional measures to address those weaknesses be included in the Plan and be achieved by the Member State before the first payment;
(d)
where the Plan does not comply satisfactorily with the criteria set out in Article 16(3), no financial allocation shall be allocated to the Member State.
4. Where the Commission gives a negative assessment of a Plan, the decision referred to in paragraph 1 shall include the reasons for that negative assessment. The Member State shall resubmit the Plan, after taking into account the assessment of the Commission.
Amendment of Social Climate Plans
1. Where a Plan is no longer achievable, including relevant milestones and targets, or needs to be significantly adjusted, either in whole or in part, by a Member State because of objective circumstances, in particular because of the actual direct effects of the inclusion of greenhouse gas emissions from buildings and road transport within the scope of Directive 2003/87/EC, the Member State concerned shall submit an amended Plan to the Commission in order to include the necessary and duly justified changes. Member States may request technical support, in accordance with Article 11(4), for the preparation of the amended Plan.
2. The Commission shall assess the amended Plan in accordance with Article 16.
3. Where the Commission gives a positive assessment of the amended Plan, it shall in accordance with Article 17(1) adopt a decision setting out the reasons for its positive assessment, by means of an implementing act. By way of derogation from Article 17(1), the Commission shall adopt the decision under this paragraph within three months from the date of the submission of the amended Plan by the Member State concerned.
4. Where the Commission gives a negative assessment of the amended Plan, it shall reject the amended Plan within the period referred to in paragraph 3, after having given the Member State concerned the possibility to present its observations within three months from the date of the communication of the Commission’s assessment of the amended Plan.
5. By 15 March 2029 each Member State shall assess the appropriateness of its Plan in view of the actual direct effects of the inclusion of greenhouse gas emissions from buildings and road transport within the scope of Directive 2003/87/EC. Those assessments shall be submitted to the Commission together with the integrated national energy and climate progress reports pursuant to Article 17 of Regulation (EU) 2018/1999.
6. In the case of minor adjustments to the Plan, representing an increase or decrease of less than 5 % of a target set out in the Plan, such as minor updates in the measures and investments set out in the Plan, or the correction of clerical errors, a Member State shall notify such changes to the Commission.
Commitment of the financial allocation
1. After the Commission has adopted a positive decision as referred to in Article 17 of this Regulation, it shall in due time conclude an agreement with the Member State concerned constituting an individual legal commitment within the meaning of Regulation (EU, Euratom) 2018/1046 for the period 2026-2032, without prejudice to Article 30d(4) and Articles 30i and 30k of Directive 2003/87/EC. That agreement shall be concluded at the earliest one year before the year of the start of the auctions under Chapter IVa of Directive 2003/87/EC, or two years before that year, in cases where Article 10(1), third subparagraph, of this Regulation applies.
2. Budgetary commitments may be based on global commitments and, where appropriate, may be broken down into annual instalments spread over several years.
Rules on payments, suspension and termination of agreements regarding financial allocations
1. Payments of financial allocations under this Article to the Member State shall be made upon achievement of the relevant agreed milestones and targets indicated in the Plan, as approved in accordance with Article 17, and subject to the availability of funding. Upon such achievement, the Member State shall submit to the Commission a duly reasoned payment request. The Member State shall submit such payment requests to the Commission once or twice a year, by 31 July or by 31 December.
2. Upon receiving a payment request from a Member State, the Commission shall assess whether the relevant milestones and targets set out in the Commission decision referred to in Article 17 have been satisfactorily achieved. The satisfactory achievement of milestones and targets shall presuppose that measures related to previously satisfactorily achieved milestones and targets have not been reversed by the Member State concerned.
3. Where the Commission makes a positive assessment of an individual payment request, it shall adopt an individual decision authorising the disbursement of the financial allocation in accordance with Regulation (EU, Euratom) 2018/1046, subject to the availability of funding and ensuring the equal treatment of Member States. The Commission shall adopt the individual decision not earlier than two months and not later than three months after the relevant deadline for submission of the payment request in accordance with paragraph 1 of this Article.
4. Where, as a result of the assessment referred to in paragraph 3 of this Article, the Commission establishes that the milestones and targets set out in the Commission decision referred to in Article 17 have not been satisfactorily achieved, the payment of the part of the financial allocation proportional to the unachieved target or milestone shall be suspended. The Member State may present its observations within one month of the communication of the Commission’s assessment.
The suspension shall only be lifted where the milestones and targets have been satisfactorily achieved as set out in the Commission decision referred to in Article 17.
5. By way of derogation from Article 116(2) of Regulation (EU, Euratom) 2018/1046, the payment deadline shall start running from the date of the communication of the Commission’s decision authorising the disbursement of the financial allocation to the Member State concerned pursuant to paragraph 3 of this Article, or from the date of the communication of the lifting of a suspension pursuant to paragraph 4, second subparagraph, of this Article.
6. Where the milestones and targets have not been satisfactorily achieved within a period of nine months from the suspension referred to in paragraph 4, first subparagraph, the Commission shall reduce the amount of the financial allocation proportionately after having given the Member State the possibility to present its observations within two months from the communication of its conclusions as to the achievement of the milestones and targets.
7. Where, within 15 months from the date of the conclusion of relevant agreements referred to in Article 19, no tangible progress has been made in respect of any relevant milestones and targets by the Member State, the Commission shall terminate those agreements and shall decommit the amount of the financial allocation without prejudice to Article 14(3) of Regulation (EU, Euratom) 2018/1046. The Commission shall take a decision on the termination of those agreements after having given the Member State the possibility to present its observations within a period of two months of the communication of the assessment by the Commission that no tangible progress has been made.
8. All payments shall be made by 31 December 2033.
9. By way of derogation from Article 116 of Regulation (EU, Euratom) 2018/1046 and paragraph 5 of this Article, if, in a given round of payment requests as referred to in paragraph 1 of this Article, the revenue assigned to the Fund in accordance with Article 30d(4) of Directive 2003/87/EC is not sufficient to cover the submitted payment requests, the Commission shall pay the Member States on a pro-rata basis determined as a share of the payment availabilities to the total approved payments. In the following round of payment requests, the Commission shall give priority to those Member States with delayed payments from the previous round of payment requests, and only later to the newly submitted payment requests.
10. By way of derogation from Article 12(4), point (c), of Regulation (EU, Euratom) 2018/1046 and without prejudice to Article 30d(4), sixth subparagraph, of Directive 2003/87/EC, the Commission shall allocate to Member States the amounts corresponding to any appropriations that are unused by 31 December 2033 in accordance with the rules for distribution of allowances defined under Article 30d(5) of Directive 2003/87/EC in order to achieve the objectives referred to in Article 3 of this Regulation.
Protection of the financial interests of the Union
1. The Member States, when implementing the Plans, as beneficiaries of funds under the Fund, shall take all the appropriate measures to protect the financial interests of the Union and to ensure that the use of the financial allocations in relation to measures and investments supported by the Fund, including those carried out by public or private entities other than vulnerable households, vulnerable micro-enterprises and vulnerable transport users in accordance with Article 9, complies with applicable Union and national law, in particular regarding the prevention, detection and correction of fraud, corruption and conflicts of interests. To that effect, the Member States shall provide an effective and efficient internal control system as further set out in Annex III and the recovery of amounts wrongly paid or incorrectly used. Member States may rely on their regular national budget management systems.
2. The agreements referred to in Article 19 shall provide for the following obligations of the Member States:
(a)
to regularly check that the financing provided has been properly used in accordance with all applicable rules and that any measure or investment under the Plan has been properly implemented in accordance with all applicable rules, in particular regarding the prevention, detection and correction of fraud, corruption and conflicts of interests;
(b)
to take appropriate measures to prevent, detect and correct fraud, corruption, and conflicts of interests as defined in Article 61 of Regulation (EU, Euratom) 2018/1046 affecting the financial interests of the Union and to take legal action to recover funds that have been misappropriated, including in relation to any measure or investment implemented under the Plan;
(c)
to accompany a payment request by:
(i)
a management declaration that the financial allocations were used for its intended purpose, that the information submitted with the payment request is complete, accurate and reliable and that the internal control systems put in place give the necessary assurances that the financial allocations were managed in accordance with all applicable rules, in particular rules on avoidance of conflicts of interests, fraud prevention, corruption and double funding from the Fund and other Union programmes in accordance with the principle of sound financial management; and
(ii)
a summary of the audits carried out in accordance with internationally accepted audit standards, including the scope of those audits in terms of amount of spending covered and period of time covered and an analysis of the weaknesses identified and any corrective action taken;
(d)
for the purpose of audit and control and to provide for comparable information on the use of financial allocations in relation to measures and investments implemented under the Plan, to collect, record and store in an electronic system and ensure access to the following standardised categories of data:
(i)
name of the final recipients of the financial allocations, their VAT registration numbers or tax identification numbers and amount of the financial allocations from the Fund;
(ii)
name of the contractor(s) and sub-contractor(s) and their VAT registration number(s) or tax identification number(s) and value of the contract(s) where the final recipient of the financial allocations is a contracting authority in accordance with Union or national law on public procurement;
(iii)
first name(s), last name(s), date(s) of birth and VAT registration number(s) or tax identification number(s), of beneficial owner(s) of the recipient of the financial allocations or contractor, as defined in Article 3, point (6), of Directive (EU) 2015/849 of the European Parliament and of the Council ( 33 ) ;
(iv)
a list of any measures and investments implemented under the Fund with the total amount of public funding of those measures and investments and indicating the amount of funds paid under other funds financed from the Union budget;
(e)
to expressly authorise the Commission, OLAF, the Court of Auditors and, in respect of those Member States participating in enhanced cooperation pursuant to Regulation (EU) 2017/1939, the EPPO, to exert their rights as provided for in Article 129(1) of Regulation (EU, Euratom) 2018/1046 and to impose obligations on all final recipients of the financial allocations paid for implementing the measures and investments included in the Plan, or to all other persons or entities involved in their implementation to expressly authorise the Commission, OLAF, the Court of Auditors and, where applicable, EPPO to exert their rights as provided for in Article 129(1) of Regulation (EU, Euratom) 2018/1046 and to impose similar obligations on all final recipients of funds disbursed;
(f)
to keep records in accordance with Article 132 of Regulation (EU, Euratom) 2018/1046, the point of reference being the payment transaction relevant to the respective measure or investment.
The information referred to in point (d)(ii) of the first subparagraph of this Article shall be required only where the value of public procurement is greater than the Union thresholds set out in Article 4 of Directive 2014/24/EU of the European Parliament and of the Council ( 34 ) . Regarding subcontractors, that information shall be required only:
(a)
for the first level of sub-contracting;
(b)
where that information is recorded regarding the respective contractor; and
(c)
for sub-contracts with a total value greater than EUR 50 000.
3. Personal data as referred to in paragraph 2, point (d), of this Article shall be processed by Member States and by the Commission for the purpose, and corresponding duration, of discharge, audit and control proceedings, and information, communication and visibility activities, related to the use of financial allocations related to the implementation of the agreements referred to in Article 19. The personal data shall be processed in accordance with Regulation (EU) 2016/679 or Regulation (EU) 2018/1725, whichever is applicable. Within the framework of the discharge procedure to the Commission, in accordance with Article 319 TFEU, the Fund shall be subject to reporting under the integrated financial and accountability reporting referred to in Article 247 of Regulation (EU, Euratom) 2018/1046, and, in particular, separately in the annual management and performance report.
4. The agreements referred to in Article 19 shall also provide for the right of the Commission to reduce proportionately the support under the Fund and recover any amount due to the Union budget, in cases of fraud, corruption, and conflict of interests affecting the financial interests of the Union that have not been corrected by the Member State, or a serious breach of an obligation resulting from such agreements.
When deciding on the amount of the recovery and reduction the Commission shall respect the principle of proportionality and shall take into account the seriousness of the fraud, corruption and conflict of interests affecting the financial interests of the Union, or of a breach of an obligation. The Commission shall give the Member State the opportunity to present its observations before the reduction is made.