Article 9
1. Except in cases of force majeure, the successful tenderer shall bear all risks which the goods may incur, in particular loss or determination as far as the supply stage provided for in Article 2 (2). 2. If taking over at the delivery stage is delayed owing to circumstances beyond the control of the successful tenderer, the additional costs shall be reimbursed by the Commission on the basis of supporting documents. 3. The successful tenderer shall apply to the Albanian authorities for a certificate testifying that the quantity delivered has been taken over. 4. The detailed rules for the granting of the taking-over certificate shall be defined in accordance with the procedure laid down in Article 26 of Regulation (EEC) No 2727/75. 5. The supply costs shall be reimbursed in respect of the quantity appearing in the taking-over certificate, no amount being withheld for normal loss of weight.