Commission Regulation (EU) 2015/1222 Article 28

Commission Regulation (EU) 2015/1222 Article 28

Creation of a common grid model

Article 28

1.   For each capacity calculation time-frame referred to in Article 14(1), each generator or load unit subject to Article 16 shall provide the data specified in the generation and load data provision methodology to the TSO responsible for the respective control area within the specified deadlines. 2.   Each generator or load unit providing information pursuant to Article 16(3) shall deliver the most reliable set of estimations practicable. 3.   For each capacity calculation time-frame, each TSO shall establish the individual grid model for each scenario in accordance with Article 19, in order to merge individual grid models into a common grid model. 4.   Each TSO shall deliver to the TSOs responsible for merging the individual grid models into a common grid model the most reliable set of estimations practicable for each individual grid model. 5.   For each capacity calculation time-frame a single, Union-wide common grid model shall be created for each scenario as set out in Article 18 by merging inputs from all TSOs applying the capacity calculation process as set out in paragraph 3 of this Article.

Read the full instrument → · Read this in context: Section 4 — The capacity calculation process →

Other provisions in Section 4 — The capacity calculation process

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 28 of Commission Regulation (EU) 2015/1222 (LawPlayer, data as of 2026-07-04)

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged.

What to look at next