Commission Regulation (EU) 2015/1222 Article 29

Commission Regulation (EU) 2015/1222 Article 29

Regional calculation of cross-zonal capacity

Article 29

1.   For each capacity calculation time-frame, each TSO shall provide the coordinated capacity calculators and all other TSOs in the capacity calculation region with the following items: operational security limits, generation shift keys, remedial actions, reliability margins, allocation constraints and previously allocated cross-zonal capacity. 2.   Each coordinated capacity calculator shall perform an operational security analysis applying operational security limits by using the common grid model created for each scenario in accordance with Article 28(5). 3.   When calculating cross-zonal capacity, each coordinated capacity calculator shall: (a)  use generation shift keys to calculate the impact of changes in bidding zone net positions and of flows on direct current lines; (b)  ignore those critical network elements that are not significantly influenced by the changes in bidding zone net positions according to the methodology set out in Article 21; and, (c)  ensure that all sets of bidding zone net positions and flows on direct current lines not exceeding cross-zonal capacity comply with reliability margins and operational security limits in accordance with Article 21(1)(a)(i) and (ii), and take into account previously allocated cross-zonal capacity in accordance with Article 21(1)(b)(iii). 4.   Each coordinated capacity calculator shall optimise cross-zonal capacity using available remedial actions taken into account in capacity calculation in accordance with Article 21(1)(a)(iv). 5.   Each coordinated capacity calculator shall apply the sharing rules established in accordance with Article 21(1)(b)(vi). 6.   Each coordinated capacity calculator shall respect the mathematical description of the applied capacity calculation approach established in accordance with Article 21(1)(b)(i). 7.   Each coordinated capacity calculator applying the flow-based approach shall: (a)  use data on operational security limits to calculate the maximum flows on critical network elements; (b)  use the common grid model, generation shift keys and contingencies to calculate the power transfer distribution factors; (c)  use power transfer distribution factors to calculate the flows resulting from previously allocated cross-zonal capacity in the capacity calculation region; (d)  calculate flows on critical network elements for each scenario (taking into account contingencies), and adjust them by assuming no cross-zonal power exchanges within the capacity calculation region, applying the rules for avoiding undue discrimination between internal and cross-zonal power exchanges established in accordance with Article 21(1)(b)(ii); (e)  calculate the available margins on critical network elements, taking into account contingencies, which shall equal the maximum flows reduced by adjusted flows referred to in point (d), reliability margins, and flows resulting from previously allocated cross-zonal capacity; (f)  adjust the available margins on critical network elements or power transfer distribution factors using available remedial actions to be considered in capacity calculation in accordance with Article 25. 8.   Each coordinated capacity calculator applying the coordinated net transmission capacity approach shall: (a)  use the common grid model, generation shift keys and contingencies to calculate maximum power exchange on bidding zone borders, which shall equal the maximum calculated exchange between two bidding zones on either side of the bidding zone border respecting operational security limits; (b)  adjust maximum power exchange using remedial actions taken into account in capacity calculation in accordance with Article 25; (c)  adjust maximum power exchange, applying rules for avoiding undue discrimination between internal and cross-zonal exchanges in accordance with Article 21(1)(b)(ii); (d)  apply the rules set out in accordance with Article 21(1)(b)(vi) for efficiently sharing the power flow capabilities of critical network elements among different bidding zone borders; (e)  calculate cross-zonal capacity, which shall be equal to maximum power exchange adjusted for the reliability margin and previously allocated cross-zonal capacity. 9.   Each coordinated capacity calculator shall cooperate with the neighbouring coordinated capacity calculators. Neighbouring TSOs shall ensure such cooperation by exchanging and confirming information on interdependency with the relevant regional coordinated capacity calculators, for the purposes of capacity calculation and validation. Neighbouring TSOs shall provide information on interdependency to the coordinated capacity calculators before capacity calculation. An assessment of the accuracy of this information and corrective measures shall be included in the biennial report drafted in accordance with Article 31, where appropriate. 10.   Each coordinated capacity calculator shall set: (a)  flow-based parameters for each bidding zone within the capacity calculation region, if applying the flow-based approach; or (b)  cross-zonal capacity values for each bidding zone border within the capacity calculation region, if applying the coordinated net transmission capacity approach. 11.   Each coordinated capacity calculator shall submit the cross-zonal capacity to each TSO within its capacity calculation region for validation in accordance with Article 21(1)(c).

Read the full instrument → · Read this in context: Section 4 — The capacity calculation process →

Other provisions in Section 4 — The capacity calculation process

CitationArticle 29 of Commission Regulation (EU) 2015/1222 (LawPlayer, data as of 2026-11-02)

DATA NOTES

About the data

Sources

This page

Law
Article 29 of Commission Regulation (EU) 2015/1222 is headed “Regional calculation of cross-zonal capacity” and is a provision of EU legislation.
Text
The text of Article 29 of Commission Regulation (EU) 2015/1222 begins “1. For each capacity calculation time-frame, each TSO shall provide the coordinated capacity calculators and all other TSOs in the capacity…”.
Location
Article 29 of Commission Regulation (EU) 2015/1222 is placed under “TITLE II: REQUIREMENTS FOR TERMS, CONDITIONS AND METHODOLOGIES CONCERNING CAPACITY ALLOCATION AND CONGESTION MANAGEMENT › CHAPTER 1: Capacity calculation › Section 4: The capacity calculation process”.
Previous
On LawPlayer, the provision listed immediately before Article 29 of Commission Regulation (EU) 2015/1222 is Article 28.
Next
On LawPlayer, the provision listed immediately after Article 29 of Commission Regulation (EU) 2015/1222 is Article 30.
Synced
LawPlayer last synced the text of Commission Regulation (EU) 2015/1222 from EUR-Lex (Publications Office of the European Union) on 2 November 2026.
Consolidated version
The text shown is taken from the EUR-Lex consolidated version of 15 March 2021. That date refers to the consolidated text as a whole and does not indicate that this article changed on that day; some amendments may not yet be included. Consolidated versions are documentation tools only and have no legal effect; the authentic texts are those published in the Official Journal of the European Union.
Article 29 of Commission Regulation (EU) 2015/1222 is reproduced on LawPlayer from EUR-Lex (Publications Office of the European Union).

Sources

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged. · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Data as of 2026-11-02Read the official text ↗

About

On LawPlayer, every article of an EU act has its own page, linked to the full text and, where the act has them, to its Titles, Chapters and Sections; the same site also covers Taiwan's statutes, court judgments and company registration records, and the legislation of 13 other jurisdictions.EU law entry

What to look at next