Subject matter and scope

Article 1

1.   This Regulation lays down detailed rules on cross-zonal capacity allocation in the forward markets, on the establishment of a common methodology to determine long-term cross-zonal capacity, on the establishment of a single allocation platform at European level offering long-term transmission rights, and on the possibility to return long-term transmission rights for subsequent forward capacity allocation or transfer long-term transmission rights between market participants. 2.   This Regulation shall apply to all transmission systems and interconnections in the Union, except the transmission systems on islands which are not connected with other transmission systems via interconnectors. 3.   In Member States where more than one TSO exists, this Regulation shall apply to all TSOs within that Member State. Where a TSO does not have a function relevant to one or more obligations under this Regulation, Member States may provide that the responsibility for complying with those obligations is assigned to one or more different, specific TSOs. 4.   The single allocation platform may be opened to market operators and TSOs operating in Switzerland on the condition that its national law implements the main provisions of Union electricity market legislation and that there is an intergovernmental agreement on electricity cooperation between the Union and Switzerland. 5.   Subject to the conditions of paragraph 4, the participation of Switzerland in the single allocation platform shall be decided by the Commission based on an opinion given by the Agency. The rights and responsibilities of Swiss TSOs joining the single allocation platform shall be consistent with the rights and responsibilities of TSOs operating in the Union, allowing for a smooth functioning of the allocation of the long-term transmission rights implemented at Union level and a level playing field for all stakeholders.

Definitions

Article 2

For the purposes of this Regulation, the definitions in Article 2 of Regulation (EC) No 714/2009, Article 2 of Regulation (EU) 2015/1222, Article 2 of Commission Regulation (EU) No 543/2013  ( 4 ) as well as Article 2 of Directive 2009/72/EC of the European Parliament and of the Council  ( 5 ) shall apply. In addition, the following definitions shall apply: (1) ‘forward capacity allocation’ means the attribution of long-term cross-zonal capacity through an auction before the day-ahead time frame; (2) ‘long-term transmission right’ means a physical transmission right or a FTR — option or a FTR — obligation acquired in the forward capacity allocation; (3) ‘allocation rules’ means the rules for forward capacity allocation applied by the single allocation platform; (4) ‘single allocation platform’ means the European platform established by all TSOs for forward capacity allocation; (5) ‘auction’ means the process by which long-term cross-zonal capacity is offered and allocated to market participants who submit bids; (6) ‘UIOSI’ means the principle according to which the underlying cross-zonal capacity of physical transmission rights purchased and non-nominated is automatically made available for day-ahead capacity allocation and according to which the holder of these physical transmission rights receives remuneration from the TSOs. (7) ‘nomination’ means the notification of the use of long-term cross-zonal capacity by a physical transmission rights holder and its counterparty, or an authorised third party, to the respective TSOs; (8) ‘nomination rules’ means the rules with regard to the notification of use of long-term cross-zonal capacity by a physical transmission rights holder and their counterparty, or an authorised third party, to the respective TSOs; (9) ‘market spread’ means the difference between the hourly day-ahead prices of the two concerned bidding zones for the respective market time unit in a specific direction; (10) ‘compensation rules’ means the rules according to which each TSO responsible for the bidding zone border, where long-term transmission rights have been allocated, compensates transmission right holders for curtailing the long-term transmission rights.

Objectives of forward capacity allocation

Article 3

This Regulation aims at: (a) promoting effective long-term cross-zonal trade with long-term cross-zonal hedging opportunities for market participants; (b) optimising the calculation and allocation of long-term cross-zonal capacity; (c) providing non-discriminatory access to long-term cross-zonal capacity; (d) ensuring fair and non-discriminatory treatment of TSOs, the Agency, regulatory authorities and market participants; (e) respecting the need for a fair and orderly forward capacity allocation and orderly price formation; (f) ensuring and enhancing the transparency and reliability of information on forward capacity allocation; (g) contributing to the efficient long-term operation and development of the electricity transmission system and electricity sector in the Union.

Adoption of terms and conditions or methodologies

Article 4

1.   TSOs shall develop the terms and conditions or methodologies required by this Regulation and submit them for approval to the competent regulatory authorities within the respective deadlines set out in this Regulation. Where a proposal for terms and conditions or methodologies pursuant to this Regulation needs to be developed and agreed by more than one TSO, the participating TSOs shall closely cooperate. TSOs, with the assistance of ENTSO for Electricity, shall regularly inform the competent regulatory authorities and the Agency about the progress of the development of these terms and conditions or methodologies. 2.   TSOs deciding on proposals for terms and conditions or methodologies in accordance with Article 4(6) shall decide with qualified majority if no consensus could be reached among them. A qualified majority for proposals in accordance with Article 4(6) shall require a majority of: (a) TSOs representing at least 55 % of the Member States; and (b) TSOs representing Member States comprising at least 65 % of the population of the Union. A blocking minority for decisions in accordance with Article 4(6) must include TSOs representing at least four Member States, failing of which the qualified majority shall be deemed attained. For TSO decisions under Article 4(6), one vote shall be attributed per Member State. If there is more than one TSO in the territory of a Member State, the Member State shall allocate the voting powers among the TSOs. 3.   TSOs deciding on proposals for terms and conditions or methodologies in accordance with Article 4(7) shall decide with qualified majority if no consensus can be reached amongst them and where the regions concerned are composed of more than five Member States. A qualified majority for proposals in accordance with Article 4(7) shall require a majority of: (a) TSOs representing at least 72 % of the Member States concerned; and (b) TSOs representing Member States comprising at least 65 % of the population of the concerned region. A blocking minority for decisions in accordance with Article 4(7) must include at least the minimum number of TSOs representing more than 35 % of the population of the participating Member States, plus TSOs representing at least one additional Member State concerned, failing of which the qualified majority shall be deemed attained. TSOs deciding on proposals for terms and conditions or methodologies in accordance with Article 4(7) in relation to regions composed of five Member States or less shall decide based on consensus. For TSO decisions under Article 4(7), one vote shall be attributed per Member State. If there is more than one TSO in the territory of a Member State, the Member States shall allocate the voting powers among the TSOs. 4.   If TSOs fail to submit a proposal for terms and conditions or methodologies to the national regulatory authorities within the deadlines defined in this Regulation, they shall provide the competent regulatory authorities and the Agency with the relevant drafts of the terms and conditions or methodologies, and explain what has prevented an agreement. The Agency shall inform the Commission and shall, in cooperation with the competent regulatory authorities, at the Commission's request, investigate the reasons for the failure and inform the Commission thereof. The Commission shall take the appropriate steps to make possible the adoption of the required terms and conditions or methodologies within four months from the receipt of the Agency's information. 5.   Each regulatory authority shall be responsible for approving the terms and conditions or methodologies referred to in paragraphs 6 and 7. 6.   The proposals for the following terms and conditions or methodologies shall be subject to approval by all regulatory authorities: (a) the generation and load data provision methodology pursuant to Article 17; (b) the common grid model methodology pursuant to Article 18; (c) the requirements for the single allocation platform pursuant to Article 49; (d) the harmonised allocation rules pursuant to Article 51; (e) the congestion income distribution methodology pursuant to Article 57; (f) the methodology for sharing costs of establishing, developing and operating the single allocation platform pursuant to Article 59; (g) the methodology for sharing costs incurred to ensure firmness and remuneration of long-term transmission rights pursuant to Article 61. 7.   The proposals for the following terms and conditions or methodologies shall be subject to approval by all regulatory authorities of the concerned region: (a) the capacity calculation methodology pursuant to Article 10; (b) the methodology for splitting cross-zonal capacity pursuant to Article 16; (c) the regional design of long-term transmission rights pursuant to Article 31; (d) the establishment of fallback procedures in accordance with Article 42; (e) the regional requirements of the harmonised allocation rules pursuant to Article 52, including the regional compensation rules pursuant to Article 55. 8.   The proposal for terms and conditions or methodologies shall include a proposed timescale for their implementation and a description of their expected impact on the objectives of this Regulation. Proposals on terms and conditions or methodologies subject to the approval by several or all regulatory authorities shall be submitted to the Agency at the same time that they are submitted to regulatory authorities. Upon request by the competent regulatory authorities, the Agency shall issue an opinion within three months on the proposals for terms and conditions or methodologies. 9.   Where the approval of the terms and conditions or methodologies requires a decision by more than one regulatory authority, the competent regulatory authorities shall consult and closely cooperate and coordinate with each other in order to reach an agreement. Where applicable, the competent regulatory authorities shall take into account the opinion of the Agency. Regulatory authorities shall take decisions concerning the submitted terms and conditions or methodologies in accordance with paragraphs 6 and 7, within six months following the receipt of the terms and conditions or methodologies by the regulatory authority or, where applicable, by the last regulatory authority concerned. 10.   Where the regulatory authorities have not been able to reach an agreement within the period referred to in paragraph 9, or upon their joint request, the Agency shall adopt a decision concerning the submitted proposals for terms and conditions or methodologies within six months, in accordance with Article 8(1) of Regulation (EC) No 713/2009. 11.   In the event that one or several regulatory authorities request an amendment to approve the terms and conditions or methodologies submitted in accordance with paragraphs 6 and 7, the relevant TSOs shall submit a proposal for amended terms and conditions or methodologies for approval within two months following the requirement from the regulatory authorities. The competent regulatory authorities shall decide on the amended terms and conditions or methodologies within two months following their submission. Where the competent regulatory authorities have not been able to reach an agreement on terms and conditions or methodologies pursuant to paragraphs 6 and 7 within the two-month deadline, or upon their joint request, the Agency shall adopt a decision concerning the amended terms and conditions or methodologies within six months, in accordance with Article 8(1) of Regulation (EC) No 713/2009. If the relevant TSOs fail to submit a proposal for amended terms and conditions or methodologies, the procedure provided for in paragraph 4 shall apply. 12.   TSOs responsible for developing a proposal for terms and conditions or methodologies or regulatory authorities responsible for their adoption in accordance with paragraphs 6 and 7, may request amendments of these terms and conditions or methodologies. The proposals for amendment to the terms and conditions or methodologies shall be submitted to consultation in accordance with the procedure set out in Article 6 and approved in accordance with the procedure set out in this Article. 13.   TSOs responsible for establishing the terms and conditions or methodologies in accordance with this Regulation shall publish them on the internet after approval by the competent regulatory authorities or, if no such approval is required, after their establishment, except where such information is considered as confidential in accordance with Article 7.

Stakeholder involvement

Article 5

The Agency, in close cooperation with ENTSO for Electricity, shall organise stakeholder involvement regarding forward capacity allocation and other aspects of the implementation of this Regulation. This shall include regular meetings with stakeholders to identify problems and propose improvements notably related to the operation and development of the forward capacity allocation, including the harmonisation of auction rules. This shall not replace the stakeholder consultations in accordance with Article 6.

Consultation

Article 6

1.   TSOs responsible for submitting proposals for terms and conditions or methodologies or their amendments in accordance with this Regulation shall consult stakeholders, including the relevant authorities of each Member State, on the draft proposals for terms and conditions or methodologies where explicitly set out in this Regulation. The consultation shall last for a period of not less than one month. 2.   The proposals for terms and conditions or methodologies submitted by the TSOs at Union level shall be published and submitted to consultation at Union level. Proposals submitted by the TSOs at regional level shall be submitted to consultation at least at regional level. Parties submitting proposals at bilateral or at multilateral level shall consult at least the Member States concerned. 3.   The entities responsible for the proposal for terms and conditions or methodologies shall duly consider the views of stakeholders resulting from the consultations undertaken in accordance with paragraph 1, prior to its submission for regulatory approval if required in accordance with Article 4 or prior to publication in all other cases. In all cases, a clear and robust justification for including or not the views resulting from the consultation shall be developed and published in a timely manner before or simultaneously with the publication of the proposal for terms and conditions or methodologies.

Confidentiality obligations

Article 7

1.   Any confidential information received, exchanged or transmitted pursuant to this Regulation shall be subject to the conditions of professional secrecy laid down in paragraphs 2, 3 and 4. 2.   The obligation of professional secrecy shall apply to any persons subject to the provisions of this Regulation. 3.   Confidential information received by the persons referred to in paragraph 2 in the course of their duties may not be divulged to any other person or authority, without prejudice to cases covered by national law, the other provisions of this Regulation or other relevant Union legislation. 4.   Without prejudice to cases covered by national law or Union law, regulatory authorities, bodies or persons which receive confidential information pursuant to this Regulation may use it only for the purpose of the performance of their functions under this Regulation.

Back to Commission Regulation (EU) 2016/1719 — full text