Decision on cross-zonal risk hedging opportunities
1. TSOs on a bidding zone border shall issue long-term transmission rights unless the competent regulatory authorities of the bidding zone border have adopted coordinated decisions not to issue long-term transmission rights on the bidding zone border. When adopting their decisions, the competent regulatory authorities of the bidding zone border shall consult the regulatory authorities of the relevant capacity calculation region and take due account of their opinions.
2. Where long-term transmission rights do not exist on a bidding zone border at the entry into force of this Regulation, the competent regulatory authorities of the bidding zone border shall adopt coordinated decisions on the introduction of long-term transmission rights no later than six months after the entry into force of this Regulation.
3. The decisions pursuant to paragraphs 1 and 2 shall be based on an assessment, which shall identify whether the electricity forward market provides sufficient hedging opportunities in the concerned bidding zones. The assessment shall be carried out in a coordinated manner by the competent regulatory authorities of the bidding zone border and shall include at least:
(a)
a consultation with market participants about their needs for cross-zonal risk hedging opportunities on the concerned bidding zone borders;
(b)
an evaluation.
4. The evaluation referred to in paragraph 3(b) shall investigate the functioning of wholesale electricity markets and shall be based on transparent criteria which include at least:
(a)
an analysis of whether the products or combination of products offered on forward markets represent a hedge against the volatility of the day-ahead price of the concerned bidding zone. Such product or combination of products shall be considered as an appropriate hedge against the risk of change of the day-ahead price of the concerned bidding zone where there is a sufficient correlation between the day-ahead price of the concerned bidding zone and the underlying price against which the product or combination of products are settled;
(b)
an analysis of whether the products or combination of products offered on forward markets are efficient. For this purpose, at least the following indicators shall be assessed:
(i)
trading horizon;
(ii)
bid-ask spread;
(iii)
traded volumes in relation to physical consumption;
(iv)
open interest in relation to physical consumption.
5. In case the assessment referred to in paragraph 3 shows that there are insufficient hedging opportunities in one or more bidding zones, the competent regulatory authorities shall request the relevant TSOs:
(a)
to issue long-term transmission rights; or
(b)
to make sure that other long-term cross-zonal hedging products are made available to support the functioning of wholesale electricity markets.
6. In case the competent regulatory authorities choose to issue a request as referred to in paragraph 5(b), the relevant TSOs shall develop the necessary arrangements and submit them to the competent regulatory authorities' approval no later than six months after the request by the competent regulatory authorities. Those necessary arrangements shall be implemented no later than six months after approval by the competent regulatory authorities. The competent regulatory authorities may extend the implementation time upon request from the relevant TSOs by a period of no more than 6 months.
7. Where regulatory authorities decide that long-term transmission rights shall not be issued by the respective TSOs or that other long-term cross-zonal hedging products shall be made available by the respective TSOs, Articles 16, 28, 29, 31 to 57, 59 and 61 shall not apply to the TSOs of the bidding zone borders.
8. Upon a joint request of the TSOs on a bidding zone border or at their own initiative, and at least every 4 years, the competent regulatory authorities of the bidding zone border shall perform, in cooperation with the Agency, an assessment pursuant to paragraphs 3 to 5.
Regional design of long-term transmission rights
1. Long-term cross-zonal capacity shall be allocated to market participants by the allocation platform in the form of physical transmission rights pursuant to the UIOSI principle or in the form of FTRs — options or FTRs — obligations.
2. All TSOs issuing long-term transmission rights shall offer long-term cross-zonal capacity, through the single allocation platform, to market participants for at least annual and monthly time frames. All TSOs in each capacity calculation region may jointly propose to offer long-term cross-zonal capacity on additional time frames.
3. No later than six months after the entry into force of this Regulation, TSOs in each capacity calculation region where long-term transmission rights exist shall jointly develop a proposal for the regional design of long-term transmission rights to be issued on each bidding zone border within the capacity calculation region.
No later than six months after the coordinated decisions of the regulatory authorities of the bidding zone border to introduce long-term transmission rights pursuant Article 30(2), TSOs of the concerned capacity calculation region, shall jointly develop a proposal for the regional design of long-term transmission rights to be issued on each bidding zone border within the concerned capacity calculation region.
Regulatory authorities of Member States in which the current regional design of long-term transmission rights is part of a TSO cross-border re-dispatch arrangement for the purpose of ensuring that operation remains within operational security limits may decide to maintain physical long-term transmission rights on its bidding zone borders.
4. The proposals referred to in paragraph 3 shall include a time schedule for implementation and at least the description of the following items specified in the allocation rules:
(a)
type of long-term transmission rights;
(b)
forward capacity allocation time frames;
(c)
form of product (base load, peak load, off-peak load);
(d)
the bidding zone borders covered.
5. The proposals shall be subject to consultation in accordance with Article 6. For the proposed long-term transmission rights to be issued, each TSO shall duly consider the result of the consultation.
6. The allocation of physical transmission rights and FTRs — options in parallel at the same bidding zone border is not allowed. The allocation of physical transmission rights and FTRs — obligations in parallel at the same bidding zone border is not allowed.
7. A review of long-term transmission rights offered on a bidding zone border may be launched by:
(a)
all regulatory authorities of the bidding zone border, at their own initiative; or
(b)
all regulatory authorities of the bidding zone border based upon a recommendation from the Agency or joint request by all TSOs of the concerned bidding zone border.
8. All TSOs in each capacity calculation region shall be responsible for undertaking the review as provided for in paragraph 9.
9. Each TSO involved in the review of long-term transmission rights shall:
(a)
assess the offered long-term transmission rights taking into account the characteristics in paragraph 4;
(b)
if considered necessary, propose alternative long-term transmission rights, taking into account the result of the assessment in subparagraph (a);
(c)
carry out a consultation in accordance with Article 6 regarding:
(i)
the results of the assessment of the offered long-term transmission rights;
(ii)
if applicable, the proposal for alternative long-term transmission rights.
10. Following the consultation referred to in paragraph 9(c) and within three months of the issuance of the decision to launch a review, the TSOs of the capacity calculation region concerned shall jointly submit a proposal to the competent regulatory authorities to maintain or amend the type of long-term transmission rights.
Physical transmission rights
1. Each physical transmission right holder shall be entitled to nominate all or part of its physical transmission rights pursuant to Article 36.
2. Where the physical transmission rights holders do not make a nomination by the deadline specified in the nomination rules, they shall be entitled to obtain remuneration in accordance with Article 35.
Financial transmission rights — options
1. Holders of FTRs — options shall be entitled to obtain remuneration in accordance with Article 35.
2. The implementation of FTRs — options shall be subject to the application of day-ahead price coupling in accordance with Articles 38 to 50 of Regulation (EU) 2015/1222.
Financial transmission rights — obligations
1. Holders of FTRs — obligations shall be entitled to receive or obliged to pay the financial remuneration pursuant to Article 35.
2. The implementation of FTRs — obligations shall be subject to the application of day-ahead price coupling according to Articles 38 to 50 of Regulation (EU) 2015/1222.
Principles for long-term transmission rights remuneration
1. The relevant TSOs performing the allocation of transmission rights on a bidding zone border through the single allocation platform shall remunerate the long-term transmission rights holders in case the price difference is positive in the direction of the long-term transmission rights.
2. The holders of FTRs — obligations shall remunerate the relevant TSOs through the single allocation platform allocating transmission rights on a bidding zone border in case the price difference is negative in the direction of the FTRs — obligations.
3. The remuneration of long-term transmission rights in paragraphs 1 and 2 shall comply with the following principles:
(a)
where the cross-zonal capacity is allocated through implicit allocation or another method resulting from a fallback situation in the day-ahead time frame, the remuneration of long-term transmission rights shall be equal to the market spread;
(b)
where the cross-zonal capacity is allocated through explicit auction in the day-ahead time frame, the remuneration of long-term transmission rights shall be equal to the clearing price of the daily auction.
4. In case allocation constraints on interconnections between bidding zones have been included in the day-ahead capacity allocation process in accordance with Article 23(3) of Regulation (EU) 2015/1222, they may be taken into account for the calculation of the remuneration of long-term transmission rights pursuant to paragraph 3.