Decision on cross-zonal risk hedging opportunities

Article 30

1.   TSOs on a bidding zone border shall issue long-term transmission rights unless the competent regulatory authorities of the bidding zone border have adopted coordinated decisions not to issue long-term transmission rights on the bidding zone border. When adopting their decisions, the competent regulatory authorities of the bidding zone border shall consult the regulatory authorities of the relevant capacity calculation region and take due account of their opinions. 2.   Where long-term transmission rights do not exist on a bidding zone border at the entry into force of this Regulation, the competent regulatory authorities of the bidding zone border shall adopt coordinated decisions on the introduction of long-term transmission rights no later than six months after the entry into force of this Regulation. 3.   The decisions pursuant to paragraphs 1 and 2 shall be based on an assessment, which shall identify whether the electricity forward market provides sufficient hedging opportunities in the concerned bidding zones. The assessment shall be carried out in a coordinated manner by the competent regulatory authorities of the bidding zone border and shall include at least: (a) a consultation with market participants about their needs for cross-zonal risk hedging opportunities on the concerned bidding zone borders; (b) an evaluation. 4.   The evaluation referred to in paragraph 3(b) shall investigate the functioning of wholesale electricity markets and shall be based on transparent criteria which include at least: (a) an analysis of whether the products or combination of products offered on forward markets represent a hedge against the volatility of the day-ahead price of the concerned bidding zone. Such product or combination of products shall be considered as an appropriate hedge against the risk of change of the day-ahead price of the concerned bidding zone where there is a sufficient correlation between the day-ahead price of the concerned bidding zone and the underlying price against which the product or combination of products are settled; (b) an analysis of whether the products or combination of products offered on forward markets are efficient. For this purpose, at least the following indicators shall be assessed: (i) trading horizon; (ii) bid-ask spread; (iii) traded volumes in relation to physical consumption; (iv) open interest in relation to physical consumption. 5.   In case the assessment referred to in paragraph 3 shows that there are insufficient hedging opportunities in one or more bidding zones, the competent regulatory authorities shall request the relevant TSOs: (a) to issue long-term transmission rights; or (b) to make sure that other long-term cross-zonal hedging products are made available to support the functioning of wholesale electricity markets. 6.   In case the competent regulatory authorities choose to issue a request as referred to in paragraph 5(b), the relevant TSOs shall develop the necessary arrangements and submit them to the competent regulatory authorities' approval no later than six months after the request by the competent regulatory authorities. Those necessary arrangements shall be implemented no later than six months after approval by the competent regulatory authorities. The competent regulatory authorities may extend the implementation time upon request from the relevant TSOs by a period of no more than 6 months. 7.   Where regulatory authorities decide that long-term transmission rights shall not be issued by the respective TSOs or that other long-term cross-zonal hedging products shall be made available by the respective TSOs, Articles 16, 28, 29, 31 to 57, 59 and 61 shall not apply to the TSOs of the bidding zone borders. 8.   Upon a joint request of the TSOs on a bidding zone border or at their own initiative, and at least every 4 years, the competent regulatory authorities of the bidding zone border shall perform, in cooperation with the Agency, an assessment pursuant to paragraphs 3 to 5.

Read the full instrument → · Read this in context: Section 2 — Options for cross-zonal transmission risk hedging →

Other provisions in Section 2 — Options for cross-zonal transmission risk hedging

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04