General provisions

Article 22

1.   The operational notification procedure for the connection of each new transmission-connected demand facility, each new transmission-connected distribution facility and each new transmission-connected distribution system, shall comprise: (a) an energisation operational notification (EON); (b) an interim operational notification (ION); (c) a final operational notification (FON). 2.   Each transmission-connected demand facility owner or transmission-connected distribution system operator to which one or more of the requirements in Title II apply shall demonstrate to the relevant TSO that it has complied with the requirements set out in Title II of this Regulation by completing successfully the operational notification procedure for connection of each transmission-connected demand facility, each transmission-connected distribution facility and each transmission-connected distribution system described in Articles 23 to 26. 3.   The relevant TSO shall specify and make publicly available further details concerning the operational notification procedure.

Read the full instrument → · Read this in context: CHAPTER 2 — Operational notification procedure →

Other provisions in CHAPTER 2 — Operational notification procedure

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 22 of Commission Regulation (EU) 2016/1388 (LawPlayer, data as of 2026-07-04)

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged.

What to look at next