Commission Regulation (EU) 2016/1388 Article 23

Commission Regulation (EU) 2016/1388 Article 23

Energisation operational notification

Article 23

1.   An EON shall entitle the transmission-connected demand facility owner or transmission-connected distribution system operator to energise its internal network and auxiliaries by using the grid connection that is specified for the connection point. 2.   An EON shall be issued by the relevant TSO, subject to completion of preparations including agreement on the protection and control settings relevant to the connection point between the relevant TSO and the transmission-connected demand facility owner or transmission-connected distribution system operator.

Read the full instrument → · Read this in context: CHAPTER 2 — Operational notification procedure →

Other provisions in CHAPTER 2 — Operational notification procedure

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 23 of Commission Regulation (EU) 2016/1388 (LawPlayer, data as of 2026-07-04)

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged.

What to look at next