Commission Regulation (EU) 2016/1719 Article 56

Commission Regulation (EU) 2016/1719 Article 56

Firmness in the event of force majeure

Article 56

1.   In the event of force majeure , TSOs may curtail long-term transmission rights. Such curtailment shall be undertaken in a coordinated manner following liaison with all TSOs directly affected. 2.   The TSO which invokes the force majeure shall publish a notification describing the nature of the force majeure and its probable duration. 3.   In the event of curtailment due to force majeure the concerned holders of long-term transmission rights shall receive compensation for the period of that force majeure by the TSO which invoked the force majeure . In this case, the compensation shall be equal to the amount initially paid for the concerned long-term transmission right during the forward allocation process. 4.   The TSO which invokes a force majeure shall make every possible effort to limit the consequences and duration of the force majeure . 5.   Where a Member State has so provided, upon request by the TSO concerned, the national regulatory authority shall assess whether an event qualifies as force majeure .

Read the full instrument → · Read this in context: CHAPTER 6 — Firmness of allocated cross-zonal capacity →

Other provisions in CHAPTER 6 — Firmness of allocated cross-zonal capacity

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 56 of Commission Regulation (EU) 2016/1719 (LawPlayer, data as of 2026-07-04)

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged.