Commission Regulation (EU) 2017/1485 Article 86

Commission Regulation (EU) 2017/1485 Article 86

Update of the lists of relevant power generating modules and relevant demand facilities

Article 86

1.   Before 1 July of each calendar year, all TSOs of each outage coordination region shall jointly re-assess the relevance of power generating modules and demand facilities for outage coordination on the basis of the methodology developed in accordance with Article 84(1). 2.   Where necessary, all TSOs of each outage coordination region shall jointly decide to update the list of relevant power generating modules and relevant demand facilities of that outage coordination region before 1 August of each calendar year. 3.   All TSOs of an outage coordination region shall make the updated list of that outage coordination region available on the ENTSO for Electricity operational planning data environment. 4.   Each TSO of an outage coordination region shall inform the parties referred to in Article 85(4) about the content of the updated list.

Read the full instrument → · Read this in context: CHAPTER 1 — Outage coordination regions, relevant assets →

Other provisions in CHAPTER 1 — Outage coordination regions, relevant assets

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04