Update of the list of relevant grid elements
Article 88
1. Before 1 July of each calendar year, all TSOs of each outage coordination region shall jointly re-assess, on the basis of the methodology established pursuant to Article 84(1), the relevance for the outage coordination of grid elements located in a transmission system or a distribution system including a closed distribution system. 2. Where necessary, all TSOs of an outage coordination region shall jointly decide to update the list of relevant grid elements of that outage coordination region before 1 August of each calendar year. 3. All TSOs of an outage coordination region shall make the updated list available on the ENTSO for Electricity operational planning data environment. 4. Each TSO of an outage coordination region shall inform the parties referred to in Article 85(4) about the content of the updated list.