Completeness check of the permit application
Article 7
1. No later than 14 working days from receiving the permit application, the single point of contact shall inform the applicant whether this Regulation applies and confirm whether the permit application received is complete. 2. If during the period referred to in paragraph 1 it is determined that information is missing from the permit application, the single point of contact shall request the project promoter to submit the missing information, specifying which information is missing. If the submitted permit application is deemed to be incomplete for a second time, the single point of contact may, within 10 working days of the second submission, make a second and final request for information. The single point of contact shall not request information in areas not covered in the first request for information and shall be entitled only to request further evidence to complete the identified missing information. If the submitted permit application is deemed incomplete for a third time, the process shall be considered terminated for the purposes of this Regulation. 3. Where an environmental impact assessment report or other assessments are required as part of the permit application, a permit application shall be considered to be complete for the purposes of this Regulation only once the part of those assessments falling under the responsibility of the project promoter have been carried out and included in the permit application. 4. The date on which the single point of contact notifies the project promoter that it has received a complete permit application shall serve as the start of the permit-granting process.