Duration of the permit-granting process
Article 8
1. The permit-granting process, including the granting of the relevant permit, shall not exceed 42 working days from the date on which the single point of contact notifies the project promoter that it has received a complete permit application in accordance with Article 7(1) and (4). 2. The single point of contact shall, in close cooperation with the competent authorities, draw up a schedule for the permit-granting process and share that schedule with the project promoter, at the start of the permit-granting process. 3. Where a defence readiness project involves a modification or extension of an existing facility already authorised under national law, the competent authority shall determine whether the modification requires a new or updated permit, or whether it may proceed under the existing authorisation, provided that environmental, health and safety standards are not affected. 4. Where a defence readiness project requires the construction of several facilities or units, whether located on a single site or across multiple sites, the project promoter may, in agreement with the single point of contact, split the project into smaller projects for the purpose of complying with the applicable time limits. For such split projects, the start date of the permit-granting process for all projects remains the date on which the single point of contact notifies the project promoter that it has received a complete permit application in accordance with Article 7 (1) and (4). 5. By way of derogation from paragraph 1, and on a case-by-case basis, the competent authority may extend the time limit referred to in paragraph 1 twice, up to a maximum of 60 working days, where: (a) the exceptional nature, complexity, location, or size of the project so requires; or (b) the defence readiness project raises exceptional risks to the health and safety of workers or the general population, or an exceptional environmental risk, and additional time is necessary to adequately assess those risks. In the cases referred to in the first subparagraph, the total duration of the permit-granting process shall not exceed 102 working days. 6. Any extension of the time limit referred to in paragraph 1 shall be notified in writing by the single point of contact to the project promoter within reasonable time before the expiry of that time limit. That notification shall include the substantiated explanation of the reasons for the extension and the expected date of the comprehensive decision. 7. The time limits set out in this Article for any of the permit-granting processes shall be without prejudice to any shorter time limits established by Member States. 8. Where the single point of contact does not inform the project promoter of the outcome of the permit-granting process within the time limit set out in paragraph 1 or, where applicable, the extended time limit, in accordance with paragraph 5, the permits covered by the application shall be deemed to be granted. 9. Where permits are deemed to be granted pursuant to paragraph 8, the single point of contact shall within eight working days from the expiry of the time limits set out pursuant to paragraphs 1 and 5, inform the project promoter thereof and, where relevant, specify the conditions and requirements to which those permits are subject, in accordance with applicable Union or national law. Member States shall ensure that permits deemed to be granted pursuant to paragraph 8 may be challenged by affected parties. 10. By way of derogation from paragraph 8, Member States may, in national law adopted by 24 November 2027, provide that tacit approval in accordance with paragraph 8 shall not apply in strictly limited and exceptional cases. A decision not to apply tacit approval shall be made only following a case-by-case assessment, where the competent authority demonstrates, on the basis of duly substantiated and verifiable evidence, that the specific project raises a grave risk to human health or national security. Any derogation shall be limited to what is strictly necessary to address the identified risk. Member States shall notify the Commission of the adoption of such national law without undue delay, and at the latest one month before it becomes applicable. Any decision not to apply tacit approval to an individual permit application shall be without prejudice to the time limits set out in paragraphs 1 and 5 and shall be adopted and notified to the project promoter before the expiry of the time limits set out therein. It shall include a detailed, evidence-based justification demonstrating compliance with the conditions set out in this paragraph.